|
ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
Text |
|
|
327
|
Friday, August 23, 2013, 11:16 |
Anders Mjos | | | | | | | Problems/Solutions | Possible leak between BV1A, BV1B and PV1 | CG1A is climbing from 0.016 to 0.130 in
30 seconds when isolated.
The leak was confirmed to be between |
|
|
328
|
Monday, August 26, 2013, 13:49 |
Anders Mjos | | | | | | | Problems/Solutions | TP1A time out/fault sometime this weekend | Monday, August 26, 2013, 14:07: The turbo
could be restarted, but it does not sound
happy (Dimo was consulted earlier today). |
|
|
329
|
Wednesday, August 28, 2013, 11:28 |
Anders Mjos | | | | | | | Problems/Solutions | Hall probe controller for MB1 removed | Jens Lassen provided a new controller for
the Hall prove. With the help from Graham
from controls it was reconfigured and is |
|
|
330
|
Friday, August 30, 2013, 15:09 |
Anders Mjos | NiO#2 | HP-FEBIAD | ITE | TM3 | 39530-6 | 39069-4 | Done | Conditioning of NiO#2 | Friday, August 30, 2013, 15:09 : Turbos
stopped in preparation for installation.
Friday, August 30, 2013, 16:22: Venting |
|
|
331
|
Monday, September 09, 2013, 09:12 |
Anders Mjos | | | | | | | Problems/Solutions | Coil power supply back | Ray D. installed the "standard"
6V 200A FEBIAD COIL P/S on Friday morning.It
has not yet been tested as water supply was |
|
|
332
|
Monday, September 09, 2013, 09:14 |
Anders Mjos | | | | | | | Problems/Solutions | Ground Electrode cleaned | Monday, September 16, 2013, 17:04: Cleaned
GE. Copper shavings were removed from below
the guide pins for the Heat Shield. The shavings |
|
|
333
|
Monday, September 16, 2013, 17:07 |
Anders Mjos | NiO#2 | HP-FEBIAD | ITE | TM3 | 39530-6 | 39069-4 | Done | Conditioning NiO#2 take 2 | The GE on the Source tray and EE on the
target was cleaned. The target will be conditioned
again to verify if sparking has been reduced. |
|
|
334
|
Tuesday, September 17, 2013, 10:06 |
Anders Mjos | | | | | | | Problems/Solutions | TGHT insulator cracked | The coil insulator has been observed to
have cracked earlier. |
|
|
335
|
Wednesday, September 18, 2013, 14:54 |
Anders Mjos | | | | | | | Problems/Solutions | Hall probe calibration | New calibration of the m/q based on
the hall probe after exchanging the controller(MASSOVERQ2).
Based on NiO#2-HP-FEBIAD with Ne supplied |
|
|
336
|
Wednesday, September 18, 2013, 16:18 |
Anders Mjos | | HP-FEBIAD | | | Tube only | 38307-9 | Done | Test Target - FEBIAD COIL | Wednesday, September 18, 2013, 16:18: Starting
turbos
Wednesday, September 18, 2013, 16:26 |
|
|
337
|
Friday, September 27, 2013, 11:41 |
Anders Mjos | Ta#41 | HP-SIS | ITW | TM4 | 39069-5 | 38817-10 | Done | Ta#41 Conditioning | Friday, September 27, 2013, 11:41: Roughing
Friday, September 27, 2013, 12:08:
Turbos started |
|
|
338
|
Monday, September 30, 2013, 15:19 |
Anders Mjos | | | | | | | Problems/Solutions | New purging valves installed on Heat Shield water circuit | The Heat Shield circuit can now be separately
purged for water. Use valves on heat shield
circuit to purge the lines for target exchanges |
|
|
339
|
Thursday, October 03, 2013, 08:43 |
Anders Mjos | | | | | | | Problems/Solutions | TMS:TP2 tripped off - controller replaced. | This morning the turbo was found tripped
off.
The controller was replaced by Edi |
|
|
340
|
Thursday, October 03, 2013, 14:15 |
Anders Mjos | | | | | | | Problems/Solutions | TMS:Q1 and Q6 tripped | |
|
|
341
|
Tuesday, October 15, 2013, 16:17 |
Anders Mjos | | | | | | | Done | TGHT and TB HT test bar test | HS line is looped. Cu-test bars installed
on TGHT and TBHT. Torqued all bolts
to 120 in lbs. |
|
|
343
|
Tuesday, November 05, 2013, 15:50 |
Anders Mjos | | | | | | | Problems/Solutions | Backing pressure TSG:CG1A and CG1B elevated | Pressure around 140 mTorr. The pressure
started increasing early November 2nd. Will
continue to monitor. |
|
|
344
|
Tuesday, November 12, 2013, 12:38 |
Anders Mjos | | | | | | | Problems/Solutions | Vacuumed desk, on and around the beam line | |
|
|
345
|
Wednesday, November 20, 2013, 08:57 |
Anders Mjos | | | | | | | Problems/Solutions | Backing pressure TSG:CG1A and CG1B elevated |
|
|
|
346
|
Wednesday, November 27, 2013, 08:27 |
Anders Mjos | | | | | | | Problems/Solutions | EPICS whiteout | Since yesterday around 4pm. Due to attempt
to use the TMS:ER0 device.
IOC rebooted this morning. Archivers |
|
|
347
|
Monday, December 02, 2013, 08:36 |
Anders Mjos | | | | | | | Problems/Solutions | Sources archiver started | |
|