4
|
Thursday, September 15, 2011, 09:20 |
Anders Mjos | | | | | | | | ISAC TestStand old e-log | link
to old e-log |
|
5
|
Thursday, September 15, 2011, 13:46 |
Anders Mjos | FEBIAD Test | HP-FEBIAD | | | | | Failed | FEBIAD Broken Tube | See attached file for photos of the broken
tube |
|
10
|
Friday, September 23, 2011, 16:40 |
Anders Mjos | | | | | | | Problems/Solutions | 9-pin connectors swapped on source tray | Friday, September 23, 2011, 16:3: The connection
on the 9-pin connector for FEBIAD targets
showed burn marks from the previous FEBIAD |
|
11
|
Friday, September 23, 2011, 16:42 |
Anders Mjos | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | In progress | Target ready to be heated | Friday, September 23, 2011, 16:4: Target
installed and roughing started.
Friday, September 23, 2011, 17:12: |
|
13
|
Monday, September 26, 2011, 16:14 |
Anders Mjos | | | | | | | Problems/Solutions | Fixed leak on water line for HS, added Kapton insulation |
While testing SiC#26 a leak
was discovered on the water line to the heat
shield. The leak was in the right joint (see |
|
19
|
Monday, October 03, 2011, 13:56 |
Anders Mjos | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | Done | Venting |
|
|
20
|
Monday, October 03, 2011, 14:46 |
Anders Mjos | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | Done | Target stored under vacuum |
|
|
21
|
Wednesday, October 12, 2011, 13:14 |
Anders Mjos | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | Done | Target removed |
|
|
23
|
Thursday, October 13, 2011, 15:42 |
Anders Mjos | Training | HP-FEBIAD | | | | | Problems/Solutions | Target ready to be heated |
|
|
24
|
Monday, October 17, 2011, 10:22 |
Anders Mjos | FEBIAD | | | | | | Problems/Solutions | Variable leak valve replaced | Variable leak valve with serial number
F3-592 has been replaced by F3-649 due
to regulating problems described previously |
|
25
|
Monday, November 14, 2011, 15:40 |
Anders Mjos | | | | | | | Problems/Solutions | Variable leak valve repaired |
|
|
28
|
Tuesday, December 20, 2011, 16:09 |
Anders Mjos | | | | | | | Problems/Solutions | Variable leak valve repaired |
|
|
33
|
Thursday, February 16, 2012, 15:59 |
Anders Mjos | | | | | | | Problems/Solutions | He and Ne installed and gas lines leak checked | New supply of He and Ne was installed yesterday
and gas lines leak checked. The He bottle
is currently closed. |
|
49
|
Friday, March 02, 2012, 08:53 |
Anders Mjos | FEBIAD test | | | | | | Problems/Solutions | Tube heater insulator glowing | The insulator for the tube
heater was observed to be glowing with a
blue shine when the target was on high voltage. |
|
50
|
Friday, March 02, 2012, 13:28 |
Anders Mjos | FEBIAD test | | | | | | | Venting test stand | Venting for target exchange |
|
72
|
Monday, April 16, 2012, 11:16 |
Anders Mjos | Nb#6 | LP-SIS | ITW | TM1 | | | In progress | Venting, purging cooling lines | Venting chamber and purging cooling lines
in preparation for target removal |
|
73
|
Monday, April 16, 2012, 11:56 |
Anders Mjos | Nb#6 | LP-SIS | ITW | TM1 | | | In progress | Venting, purging cooling lines |
|
|
74
|
Wednesday, April 18, 2012, 12:19 |
Anders Mjos | | | | | | | Problems/Solutions | Noise from roughing pump TSGRP1 | Wednesday, April 18, 2012, 12:15: Blanked
off cooling lines. Chamber ready to be pumped
down. |
|
75
|
Wednesday, April 18, 2012, 13:09 |
Anders Mjos | | | | | | | Problems/Solutions | Noise from roughing pump TSGRP1 |
|
|
76
|
Wednesday, April 18, 2012, 13:10 |
Anders Mjos | No target | | | | | | In progress | Pumping down empty vacuum chamber | Wednesday, April 18, 2012, 13:10: Roughing
the vacuum chamber.
Wednesday, April 18, 2012, 13:34 |
|