  Test-Stand, Page 13 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Target/No.#down Source Station Module Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  72   Monday, April 16, 2012, 11:16 Anders MjosNb#6LP-SISITWTM1  In progressVenting, purging cooling linesVenting chamber and purging cooling lines
in preparation for target removal
  
  73   Monday, April 16, 2012, 11:56 Anders MjosNb#6LP-SISITWTM1  In progressVenting, purging cooling lines

    

       
            
  
  77   Friday, April 20, 2012, 08:56 Anders MjosNb#6LP-SISITWTM1  Problems/SolutionsInsulator stand-off failure When the target was removed from
the test stand it was discovered that the
custom designed insulator stand-off (ITD0400
 ITW-TM1-Nb#6-LP-SIS_-_TestStand.pdf 
  978   Friday, August 25, 2023, 17:21 Aaron SchmidtNb#11LP-IG-LISITWTM245447-942132-4In progressConditioning Nb#11Replacement for Nb#10
Friday, August 25, 2023, 17:15: Roughing.
Friday, August 25, 2023, 17:57: Vacuum
 Nb#11_Conditioning.docx 
  971   Thursday, July 06, 2023, 16:55 Aaron SchmidtNb#10LP-IG-LISITWTM245447-742132-2In progressConditioning Nb#10Thursday, July 06, 2023, 16:13: Roughing.
Thursday, July 06, 2023, 16:41: TP1B
on.
 Nb#10_Conditioning.docx 
  194   Thursday, September 06, 2012, 09:23 Friedhelm AmesNB#7       start high voltage and heaters   
  195   Friday, September 07, 2012, 12:11 Friedhelm AmesNB#7LP-SIS    In progressmass scan startedmass scan has been started after optimization
on 23Na
  
  199   Tuesday, September 11, 2012, 19:48 Friedhelm AmesNB#7HP-SIS    Donecool down finished, all source power supplies off.    
  68   Friday, March 09, 2012, 13:30 Friedhelm AmesNB#6      heater ramping downFc0 23 nA
IG1 9.9e-7 T
start automatic heater ramping down
  
  156   Friday, August 10, 2012, 11:29 Pierre BricaultNA   N ANAIn progressTest FEBIADThe helium bottle was found empty.
Rick will refill it and hook the
leak detector on the system to find out
  
  157   Friday, August 10, 2012, 12:44 Pierre BricaultNALP-FEBIAD  NANAIn progressFEBIAD testRick put the helium bottle back in the
rack.
Waiting for status of the gas lines.
  
  160   Friday, August 10, 2012, 15:29 Pierre BricaultNALP-FEBIAD  NANA finishing the gas installation and its pump1524H Start small pump.
1529H stop the pump.
 
  
  162   Saturday, August 11, 2012, 13:34 Pierre BricaultNALP-FEBIAD  NANAIn progressTest FEBIAD anode bias 120 V    
  49   Friday, March 02, 2012, 08:53 Anders MjosFEBIAD test     Problems/SolutionsTube heater insulator glowing   The insulator for the tube
heater was observed to be glowing with a
blue shine when the target was on high voltage.
 glowing_insulator.jpg 
  50   Friday, March 02, 2012, 13:28 Anders MjosFEBIAD test      Venting test standVenting for target exchange   
  106   Tuesday, June 26, 2012, 18:04 Anders MjosFEBIAD anode end cap test   Tube only38307-9In progressFEBIAD anode end cap test - readyTesting FEBIAD anode end cap as per dwg
ITD0304 REV C
Target with TUBE ONLY. Do not use
  
  126   Wednesday, July 04, 2012, 15:37 Anders MjosFEBIAD anode end cap test     In progressPumping down Replaced grid containing ring (target side)
with new ring. No contact between target
and anode measured in lab.
 photo_8.jpg 
  127   Thursday, July 05, 2012, 08:41 Anders MjosFEBIAD anode end cap test     In progressWater opened - reduced flow heat shield

    

       
            
  
  5   Thursday, September 15, 2011, 13:46 Anders MjosFEBIAD TestHP-FEBIAD    FailedFEBIAD Broken TubeSee attached file for photos of the broken
tube 
 FEBIAD_Broken_Tube.pdf 
  24   Monday, October 17, 2011, 10:22 Anders MjosFEBIAD     Problems/SolutionsVariable leak valve replacedVariable leak valve with serial number
F3-592 has been replaced by F3-649 due
to regulating problems described previously
 F3-649.PDF 