Entry  Monday, June 04, 2018, 16:02, Anders Mjos, , , , , , , Problems/Solutions, MB1 timeout 
Mass separator magnet timed out. Tried reconfigure. Called Kyle from  controls who power cycled the CANbus card. This resolved the issue

(From the Source tray swap out.) - AS
Tuesday, June 05, 2018, 11:25: BIAS / EZL / EE @ 52 / 24 / 2.8 kV. SPARK  *knocked out optics, magnet & Turbo TMS:TP6. IV4  closed/opened/reset.
Entry  Wednesday, June 06, 2018, 14:01, Aaron Schmidt, , , , , , , Problems/Solutions, Emittance scanner (E-rig) communication issues. 
Wednesday, June 06, 2018, 13:50:
It was noted yesterday during the TM2 Source HV tests that the E-rig was not running accordingly through the beam.
Upon turning on the PS, there a 45 second or so delay before the needle drops to the right at +500V and the PS no longer responds. (similar issue
Entry  Thursday, June 07, 2018, 09:21, Aaron Schmidt, , , , , , , Problems/Solutions, Pump down empty chamber. Anode check 20180608_100402.jpg20180608_100835.jpg20180608_100840.jpg20180613_080550.jpg20180613_080605.jpg
TM2 Source tray still in.
Thursday, June 07, 2018, 09:20: Roughing.
Thursday, June 07, 2018, 12:42: Turbo pumps started.
Entry  Friday, August 10, 2018, 10:56, Aaron Schmidt, , , , , , , Problems/Solutions, New PS installation and Cathode BIAS set 
Friday, August 10, 2018, 10:25: Remove TBHT 500 PS and replace with TBHT 600 PS.
Friday, August 10, 2018, 10:50: Switch wiring in the high voltage cage from and Anode BIAS to Cathode BIAS setting.
Friday, August 10, 2018, 11:32: TBHT limit increased from 500A to 600A by Controls group.
Entry  Tuesday, August 21, 2018, 12:54, Anders Mjos, , , , , , , Problems/Solutions, 9-pin connection configuration 
Pin configuration between top 9-pin connector on Source Tray and terminal in high voltage rack. Measured 2018-08-21 by Aaron and Anders

    
        
            Grounded
             

            
            X
             
             
             
           
Entry  Friday, August 31, 2018, 10:16, Aaron Schmidt, , , , , , , Problems/Solutions, RGA connection loss. 
Friday, August 31, 2018, 10:10: The RGA will not re-connect to the computer. Manually turned it off while under vacuum to protect the filament before
shutting down the turbo pumps.
Friday, August 31, 2018, 10:15: Ion gauge & turbo pumps off.
Entry  Monday, October 15, 2018, 14:38, Aaron Schmidt, , , , , , , Problems/Solutions, Anode / Cathode PS to Negative 
Monday, October 15, 2018, 13:00-14:00 Anode / Cathode BIAS PS polarity reversed by John Chow.
PS: Negative
Entry  Monday, October 29, 2018, 10:56, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, Problems/Solutions, TS communications issues. 
Sometime around 00:30 Sunday, October 28, 2018, the ISAC test stand lost communication to the PLC and shut down abruptly.
Monday, October 29, 2018, 09:00: PLC communications issues.
Rod N. was contacted this morning& the issues fixed by controls group.
Entry  Monday, November 19, 2018, 14:22, Aaron Schmidt, , , , , , , Problems/Solutions, Vacuum issues. 






Normal
0




false
false
false

EN-US
X-NONE
X-NONE

Entry  Wednesday, December 05, 2018, 10:22, Aaron Schmidt, , , , , , , Problems/Solutions, RGA Filament & Ionizer replacement 12x
RGA Ionizer & Filament replaced as per SRS RGA manual.
The ionizer was found to be dirty and the previous RGA filament was broken. Initially the  old filament appeared to have warped and looked
stuck to the anode grid/cage.
Entry  Thursday, December 06, 2018, 11:02, Aaron Schmidt, , , , , , , Problems/Solutions, FC0 Bellows Replacement. 20181206_Old_Bellows.jpg20181210_112528.jpg20181210_115310.jpg20181211_New_Bellows_installed.jpg
Thursday, December 06, 2018, 11:02: Turbo pumps (TP6 & TP2) off on beamline side. IG6 off.
Thursday, December 06, 2018, 14:06: Turbo pumps restarted. FC0 bellows replacement to occur Monday.

Monday, December 10, 2018, 11:00: Vented on beam side of IV4. Turbo pumps & backing valves closed preemptively on chamber side due
Entry  Thursday, March 07, 2019, 07:55, Aaron Schmidt, , LP-FEBIAD, , , , , Problems/Solutions, TS restart - Troubleshoot BIAS spark BIAS_spark_out_issue_-_2019.docxTS-2019-03-07-07-51.rga
Thursday, March 07, 2019, 07:48: IV4 reset, BV6 & TMS TP6 reset.
Turbo pump restarted.
Auto cooling @ 2A per min.
Entry  Tuesday, March 26, 2019, 10:44, Aaron Schmidt, , , , , , , Problems/Solutions, EZL PS replaced. Test New_EZL_PS_testing_-_2019.docx
EZL checked. OK @ 5kV
BIAS PS issues.
2.3kV on screen. Read back on PS 3kV. Direct measurement reads 5.8 kV
Entry  Wednesday, March 27, 2019, 11:01, Aaron Schmidt, , , , , , , Problems/Solutions, BIAS PS replaced. Test NEW_BIAS_PS_testing_-_2019.docx
Wednesday, March 27, 2019, 10:25: BIAS @ 1 kV
952V - 548uA on controls readback - Scaling req'd
964V  direct from the PS - 25 uA
Entry  Monday, June 03, 2019, 11:35, Aaron Schmidt, , LP-SIS, , TM4, 395530-3, 42752-5, Problems/Solutions, TGHT PS Failed. 
Monday, June 03, 2019, 10:36: BIAS Near 55 kV, brought back down to  50 kV. Multiple sparks. Optics tripped, wire scanners & FC0 began  running independently.
Anode current dropped from 7.328 mA to 6.105 mA.  Knocked out the TGHT
The target heater dropped from 580A to 3.1 A. Attempted reset. Non-responsive.
Entry  Monday, June 24, 2019, 15:41, Fernando Maldonado, , , , , , , Problems/Solutions, TMS:Q3 polarity 
Monday, June 24, 2019, 15:25: Current quadrupole polarities:

    
        
             

           Top/Bottom
            North/South
        
    
    
Entry  Tuesday, June 25, 2019, 17:19, Fernando Maldonado, , , , , , , Problems/Solutions, Burnt cables on top of the test stand 20190625_154015.jpg20190625_153834.jpg20190625_165001.jpg
Tuesday, June 25, 2019, 16:15: While inspecting the 9-pin connection with Ferran, it was noticed how two braided cables were burnt out pretty bad to
the point they were separated in half (see attached pictures).  Additionally the plastic insulator for the anode wire was melted.
Tuesday, June 25, 2019, 16:30: Braided cables need to be changed and anode wire redone. 
Entry  Wednesday, June 26, 2019, 14:41, Carla Babcock, none, , , , , , Problems/Solutions, Issues with test stand wiring in service cap area isk4523d_ITSrewiring_June2019.png
The wiring on the top of the test stand was burned, see entry 737.
Probable cause of this is as follows:
Coil lines are connected by a wire to HV common, the 9-pin feedthrough etc to maintain same voltage on all the insulator tops. This is also directly
Entry  Thursday, June 27, 2019, 09:51, Fernando Maldonado, , , , , , , Problems/Solutions, Melted cables changed 
See elog 737 

    
        
            Fernando
Entry  Thursday, July 04, 2019, 15:16, Aaron Schmidt, , , , , , , Problems/Solutions, TBHT insulator changed 
Thursday, July 04, 2019, 15:00: TBHT insulator was swapped out on the source tray side.  
The old one is very chipped.