  160   Tuesday, May 12, 2015, 21:20 Grant MinorStandard OperationTarget 1TargetT1 & T2 Targets moved from pos. 0 to pos. 4Grant moved the T1 and T2 targets from
position 0 to position 4 this evening at
around 9pm.
  
  184   Thursday, December 17, 2015, 13:31 Grant MinorDevelopmentOtherTargetT1/T2 Target Cassette - window / end cap manufacturing change (WO 41527)Isaac Earle has recently been managing
the fabrication of some new Be  target cassettes
for the T1 / T2 Meson Hall target ladders
 Left_new_right_old_ref_TBP1683_16Dec2015.JPGTBP1690_left_new_right_old_16Dec2015.JPGTBP1683_forming_tool_16Dec2015.JPGNew_Frame_Ref_TBP1696_16Dec2015.pdf 
  333   Tuesday, October 17, 2023, 10:16 Eric LaheMaintenanceOtherActive SumpTesting the Remote Handling Lab Active Sump Level SensorThe level sensor for the active sump in
the RH lab was tested.
The level sensor is working properly
  
  315   Wednesday, February 01, 2023, 14:23 Albert KongMaintenanceTarget 1CoolingT1 Cooling Package: flow test after resin exchange / valve leak check / faulty(?) dial pressure gauge Maico/Eric/Albert:
The expansion tank in T1 was filled
to ~36cm in the morning.
 IMG_1038.JPEG 
  316   Thursday, February 02, 2023, 10:35 Albert KongMaintenanceTarget 1CoolingT1 Cooling Package Draining (Prep for Valve Replacement)Water reservoir in T1 started draining
at ~7.30 am, will leave till tomorrow or
overnight to fully drain. 
  
  317   Thursday, February 02, 2023, 15:14 Albert KongMaintenanceTarget 1CoolingT1 Cooling Package: Leaked Valve InspectionA 0.75" SwageLok ball valve that was
taken out from the T1 cooling package was
inspected (SS-45S12).
 CompiledPictures.pdf 
  318   Friday, February 17, 2023, 14:36 Albert KongRepairOtherWater LeakT1/T2 Water Cooling Package Ball Valve Replacement5 and 3 Swagelok ball valves were replaced
from the T1 and T2 cooling packages respectively.
These are compression fit valves,
 fdb0d111-3348-483d-a78f-98eabbc45507.jpg 
  319   Tuesday, February 21, 2023, 16:56 Albert KongMaintenanceTarget 2OtherM20 BB moved to meson hall hot cell roofThe M20 beam blocker was moved from the
T2 monolith to the meson hall hot cell with
the remote handling flask (completed ~4pm).
 IMG_1255.JPEG 
  320   Wednesday, March 01, 2023, 13:10 Albert KongMaintenanceOtherCoolingT1/T2 Water Cooling Package Heat Exchanger Ball Valve Replacement3x 3/4" swagelok ball valves (2x at
T2 and 1x at T1) were replaced after the
water cooling line was shut off at the BL1A
 IMG_1452.JPEGIMG_1431.JPEGIMG_1438.JPEGIMG_1455.JPEG 
  323   Friday, March 03, 2023, 16:00 Albert KongMaintenanceTarget 2OtherM20 Return to T2 Monolith + Vaccum Leak / T1-T2 Valve Re-inspection We moved M20 back to the T2 monolith
and re did the connections for air + limit
switches + T2 profile monitor air.
 IMG_1755.JPEGIMG_1657.JPEGIMG_1763.jpegScreenshot_2023-03-30_124716.png 
  324   Monday, March 06, 2023, 16:58 Albert KongRepairTarget 2CoolingM20 O-Ring Replacement and Valve Replacement Leak Check We replaced tha O-ring on M20 at
T2 and brought the target station down to
vacuum, which allowed the target water pump
 T1_Mar06_2023.pngT2_Mar06_2023.png 
  325   Wednesday, March 15, 2023, 15:56 Albert KongMaintenanceTarget 2ControlsT2 - M9 and M20 beam blocker actuation and vacuum test We tested the actuation of the M9/M20
beam blockers on the T2 monolith (3-4pm).
Vacuum levels remained steady throughout
 6x 
  326   Thursday, March 30, 2023, 13:17 Albert KongMaintenanceOtherTargetAir Amplifier Testing: M9 BB (AKA T2 blocker), M20 BB, T2 MK1 prof. monitor, T1 MK1 prof. monitor actuationWe tested the air amplifiers by actuating
the beam blockers and profile monitors on
the T1 and T2 target stations. 
 T1_Mar30_2023_Vacuum.pngT2_Mar30_2023_Vacuum.pngIMG_1907.JPEG 
  327   Thursday, April 06, 2023, 13:35 Albert KongMaintenanceTarget 1ControlsT1 Motor Controller Hearbeat Trip (+T2 Heartbeat Trip)The T1 motor controller hearbeat tripped
(noticed this morning). 
This does not seem prevent beam delivery
 MotorControllerHB.pngScreenshot_2023-04-11_145420.png0367549f-9672-4009-be34-df7abacf4a32.jpgScreenshot_2023-05-16_091027.png 
  330   Tuesday, June 06, 2023, 15:42 Albert KongStandard OperationTarget 1CoolingT1 Heat Exchanger Low Flow DiagnosticsOn May 31, the low active water in BL1A
was turned off briefly and upon re-starting,
the flow to the T1 heat exchanger was very
 Picture1.pngPicture2.png 
  332   Thursday, August 03, 2023, 10:33 Albert KongRepairTarget 2CoolingT2 Expansion Tank Water Level Low (Leak Identified)The water level in the T2 cooling system
expansion tank dropped to below the trip
treshold of 20 cm (ref Cyclotron fault #16123),
 7x 
  334   Tuesday, October 17, 2023, 14:25 Albert KongMaintenanceOtherOtherT1/T2 Air Amplifier Spool O-Ring ServicingToday we re-lubricated the o-rings on the
top air amplifier for T1/T2, and replaced
the o-rings on the bottom air amplifier with
 IMG_2576.JPEGIMG_2575.JPEG 
  335   Monday, December 04, 2023, 09:22 Albert KongStandard OperationTarget 2CoolingT2 TGT Low Flow See Cyclotron fault 16553. 
"B1A:T2CS:FGTGT readback is
toggling at the warn limit of 3.0 GPM and
 T2FlowAlwaysCloseTo3GPM.pngT2TGTWaterTempOK.pngWarnTripLevels.pngFlowWarnTripLevels.pngPicture1.png 
  336   Wednesday, January 10, 2024, 12:25 Albert KongStandard OperationOtherCoolingT1/T2 cooling packages drainedJan 10, 2024:
The cooling packages for T1/T2 was
drained this morning. ~150 L from each of
 T1T2EPICSPages.PNGIMG_3943.JPEGIMG_4231.JPEG 
  337   Wednesday, January 10, 2024, 12:47 Albert KongStandard OperationTarget 1TargetT1 target ladder exchange (T1-MK1 to hot cell roof, T1-MK2 from pit to station)T1-MK1 was moved from the target station
to the hot cell roof. 
Radiation surveys report 140 mSv/hr
 T1_and_T2_Beryllium_Target_Beamtime_Spreadsheet_-_(10Jan2024).xlsxMeson_Hall_Storage_Pit_Target_Device_Location_Record_-_(10Jan2024).pptmVacuumAt2.56PM.PNG 