Entry  Tuesday, October 06, 2015, 14:04, Isaac Earle, Other, Other, Controls, Instructions for loading display screen for T1/T2  
Entry  Monday, October 05, 2015, 15:25, Isaac Earle, Standard Operation, Other, Other, Old T2 Protect Monitor Cassette Update 
Entry  Friday, October 02, 2015, 17:25, Ron Kuramoto, Standard Operation, Target 1, Target, Raise Target to lower Rad levels for 1AM7 repair 
Entry  Thursday, October 01, 2015, 11:43, Isaac Earle, Repair, Target 2, Target, T2-MK2 Target Ladder Drive Motor Failure 
Entry  Wednesday, September 30, 2015, 17:07, Isaac Earle, Standard Operation, Target 2, Target, Target Moves for Profile Check - Possible Motor or Control Box Failure 
Entry  Monday, September 28, 2015, 11:33, Isaac Earle, Repair, Other, Water Leak, Warm Cell Water Window Repair Complete 
Entry  Monday, September 28, 2015, 10:29, Isaac Earle, Standard Operation, Other, Active Sump, RH Hot Cell Lab Active Sump High Level Sensor Tested 
Entry  Thursday, August 27, 2015, 15:47, Isaac Earle, Repair, Other, Water Leak, Warm Cell Water Window Seal Replacement Update 
Entry  Wednesday, August 19, 2015, 12:10, Isaac Earle, Repair, Other, Other, Warm Cell Water Window Seal Replacement Status 6x
Entry  Thursday, August 13, 2015, 09:47, Isaac Earle, Development, Other, Other, "Clamp A" disassembled and used to build clamp "TRH1257-#01" 
Entry  Friday, July 17, 2015, 10:14, Isaac Earle, Development, Target 1, Target, T1/T2 Be Target Failure History & Replacement Plan T1_and_T2_Be_Target_History_-_July_17_2015.pdf
Entry  Wednesday, July 15, 2015, 10:33, Isaac Earle, Standard Operation, Target 1, Cooling, T1 & T2 Cooling System Check 
Entry  Thursday, July 09, 2015, 13:51, Isaac Earle, Development, Other, Target, New T1 and T2 Beryllium Targets Ordered 
Entry  Wednesday, July 08, 2015, 16:21, Isaac Earle, Development, Target 1, Target, 0.003" 347 SS Sheet for T1/T2 Targets Received 347SS_Mill_Spec_Test_Report_-_July_8_2015.pdf
Entry  Tuesday, June 23, 2015, 10:24, Isaac Earle, Standard Operation, Other, Other, BL1A Holding Tank Water Released 
Entry  Friday, June 19, 2015, 17:11, Isaac Earle, Development, Other, Controls, PLC Test of Ultrasonic Level Sensor Overnight_Level_Sensor_PLC_Test.jpg
Entry  Thursday, June 11, 2015, 16:59, Isaac Earle, Development, Other, Controls, Lab Test of New T1/T2 Level Sensors 
Entry  Monday, May 25, 2015, 12:48, Isaac Earle, Repair, Target 1, Controls, T1/T2 Controls System Crash 
Entry  Tuesday, May 12, 2015, 21:20, Grant Minor, Standard Operation, Target 1, Target, T1 & T2 Targets moved from pos. 0 to pos. 4 
Entry  Friday, May 08, 2015, 09:48, Isaac Earle, Standard Operation, Other, Other, BL1A Blocks Restored 1A_Shield_Blocks_Restored_for_1A_beam_2015_&_2014.pdf