  2269   Wednesday, November 17, 2021, 11:42 Travis CaveSpent Target VaultStandard Operation Ta#57Repacking of the targets.

 Ta#57 was repacked and placed in the mini vault. The pail was changed from #174 to #263. See attached PDF for more details.

Attachment 1: Target_Index_2021-11-17.pdf
Target_Index_2021-11-17.pdf Target_Index_2021-11-17.pdf Target_Index_2021-11-17.pdf
Attachment 2: Target_Index_2021-11-17_mini_vault.pdf
Target_Index_2021-11-17_mini_vault.pdf Target_Index_2021-11-17_mini_vault.pdf
  2270   Thursday, November 18, 2021, 09:47 Travis CaveSpent Target VaultStandard Operation SiC#38 and UC#29Spent Target Move

 The spent targets SiC#38 and UC#29 have been removed from the spent target vault and placed into the mini storage. See attached PDF for details.

Attachment 1: Target_Index_2021-11-18.pdf
Target_Index_2021-11-18.pdf Target_Index_2021-11-18.pdf Target_Index_2021-11-18.pdf
Attachment 2: Target_Index_2021-11-18_mini_vault.pdf
Target_Index_2021-11-18_mini_vault.pdf Target_Index_2021-11-18_mini_vault.pdf
  2278   Friday, November 26, 2021, 10:52 Adam NewsomeSpent Target VaultStandard Operation UC#35Spent Target Move

The spent UC#35 target has been moved from the south hot cell to the spent target vault. It was placed in pail #264 and put in spot 6A of the vault. See attached PDF for more details.

Attachment 1: Target_Index_2021-11-26.pdf
Target_Index_2021-11-26.pdf
  2279   Monday, November 29, 2021, 12:16 David WangSpent Target VaultStandard Operation  Five spent targets have been loaded into F308s

We loaded UCx #29 , SiC #38  , Ta#53, Ta#56 ,and Ta#57 from mini storage  into F308 flasks.  Later, the flasks are transferred from TH to B2 HC service area. In TH, Working area and Mini storage are cleaned and surveyed.  Tools are cleaned and surveyed as well. No contamination.   Mini- storage is empty now.

  2290   Wednesday, January 12, 2022, 14:09 Travis CaveSpent Target VaultStandard Operation UC#36Spent Target Move

 The spent UC#36 target in the north hot cell has been removed and placed in the spent target vault. See attached PDF for detail note that the PDF does not show that spot 2B is occupied by the 2A3M20 pail.

Attachment 1: Target_Index_2022-01-12.pdf
Target_Index_2022-01-12.pdf
  2297   Thursday, January 20, 2022, 11:09 Travis CaveSpent Target VaultStandard Operation Ta#63Spent Target Move
The spent Ta#63 has been moved from the north hot cell to the spent target vault. It was place in pail#266 and 
placed in spot #3B of the vault. see attached PDF for more details.
Attachment 1: Target_Index_2022-01-20.pdf
Target_Index_2022-01-20.pdf
  2302   Thursday, February 10, 2022, 11:45 David WangSpent Target VaultStandard Operation UCx#33.Spent target UCx #33 has been repacked with a new pail and lid in NHC.

Spent target UCx #33 has been repacked with a new pail and lid in NHC. Old pail #255. New pail # 267. Location: Vault slot 1C.  it is an investigation job for  a possible leak pail in vault.  

  2307   Thursday, February 17, 2022, 13:24 David WangSpent Target VaultMaintenance UCx #34Repackage of UCx #34in NHC.

UCX34# in pail 258(Vault lot 7C) has been repacked today. It is an investigation to find a possible leak source of radioactive Iodine in vault. The new pail number is 268. It is back to vault 7c . I wrote down the information in log book. The job is smooth today. I retrieved UCx 34 old pail and liner to TH. The liner from UCx#34 only has 3000 counts.  I bagged it. It could be used later. However, the pail has 500K counts contamination on bottom outside rim. It may accidently be slided out of plastic bag and touched the NHC table during the repackage. I bagged it and store it in silo area. When we do drum clean up, I will throw it in the drum.

  2310   Tuesday, March 01, 2022, 11:51 David WangSpent Target VaultMaintenance  UCx #32 has been repacked in NHC.

UCx 32# P2N target in vault slot 1B is repacked is morning for Ferran to take out his samples( in two small plastic containers) stored in pail last July when Chad did the spent target job. The job went well.  Old pail # is 254# and new pail # is 233. It is put back to 1B in vault.

  2318   Friday, May 06, 2022, 10:12 Adam NewsomeSpent Target VaultMaintenance  Annual Inspection of Mini-Storage Vault

The annual inspection of the mini-storage vault was performed today. The following items were checked:

  • Cabling and cable management
  • Connectors
  • Controls box - internal wiring and components, functionality
  • Limit switches - functionality, wiring, mounting
  • Motor
  • Bearings
  • Set screws
  • Miscellaneous fasteners (some loose, but were tightened)

Everything appears to be in good working order.

Note: in the near future, the bearings should be greased. This is planned to take place during the next inspection of the main storage vault.

  2319   Wednesday, May 11, 2022, 16:15 Nadia JorgensonSpent Target VaultStandard Operation  Emergency Close Mechanism Test

 The emergency close mechanism for the Storage Vault door was tested by Travis Cave, Nadia Jorgenson, and Dan McDonald. The door was opened to its fully open limit, then closed with the emergency system. 

The test was successful.

  2320   Wednesday, May 11, 2022, 16:29 Nadia JorgensonSpent Target VaultStandard Operation  Routine mechanical inspection: storage vault

 An inspection was performed on drive systems for the main storage vault by Dan McDonald, Travis Cave and Nadia Jorgenson. The functionality was not tested. Some areas for improvement noted, but otherwise nothing concerning was discovered. 

 

Notes:

  • The wire insulation to the motor is showing wear and tear. Should be replaced in the future. For now was patched with electrical tape, see picture. May be beneficial to add an e-chain for the portion of the wiring that moves when door is opening and closing

  • Emergency close mechanism cable should be changed to have a 5/32” Nico Sleeve

  • Moving parts still need to be lubricated


  • Chain inspected (OK)

  • Gearbox inspected - OK

  • All drive system set screws checked and tightened

  • Sprocket alignment checked - OK

  • Limit switches checked - OK

  • Emergency close mechanism cable checked - OK

 

 

 

Attachment 1: Motor_wiring_ISAC_storage_vault.jpg
Motor_wiring_ISAC_storage_vault.jpg
  2322   Thursday, May 19, 2022, 11:42 Travis CaveSpent Target VaultStandard Operation Sic#39, Ta#59, C#2, UC# 32 & 30Targets moved to the mini vault.

 Sic#39, Ta#59, C#2, UC# 32 & 30 have been moved from the spent target vault to the mini vault. See the attached pdf for details of the vaults.

Attachment 1: Target_Index_2022-05-19.pdf
Target_Index_2022-05-19.pdf
Attachment 2: Mini_Vault_Target_Index_2022-05-19.pdf
Mini_Vault_Target_Index_2022-05-19.pdf Mini_Vault_Target_Index_2022-05-19.pdf
  2324   Wednesday, May 25, 2022, 10:23 Nadia JorgensonSpent Target VaultRepair  F-308 Loading, Mini-Storage Vault Failure

5 pails were moved from the mini-storage vault into F-308's

At one point during the loading the mini-storage vault door would not close. Cause was a blown fuse, which was replaced and operations were able to continue as usual. Possible reason the fuse blow was a tilted pail that may have become jammed between the tray and the roof of the mini-storage vault. 

 

[Edit 2022-12-01, Adam Newsome]: the pails which were removed were: 220, 227, 233, 235, 238

  2339   Thursday, June 23, 2022, 10:22 Travis CaveSpent Target VaultStandard Operation UC#37Spent Target Move

 UC#37 was placed in pail #228 and place in spot 1B it was removed the north hot cell. See attached PDF for more details of it and the vault.

Attachment 1: Target_Index_2022-06-23.pdf
Target_Index_2022-06-23.pdf
  2344   Monday, July 04, 2022, 11:54 Nadia JorgensonSpent Target VaultMaintenance  Added Lubrication,fittings need to be changed

Dan lubricated components on the target storage vault (This was an outstand task from annual inspection). No issues on the main storage vault but we were not able to lubricate the mini storage vault because the position of the grease nipple on the fittings makes them inaccessible, see attached pictures. All four should be replaced with 90 deg fittings. 

Attachment 1: Mini_Vault_Grease_Fitting.jpg
Mini_Vault_Grease_Fitting.jpg
  2345   Wednesday, July 06, 2022, 10:30 Travis CaveSpent Target VaultStandard Operation SiC#42Spent Target Move

 The spent SiC#42 was moved from the north hot cell to the spent target vault, it was placed in pail #271 and put in spot 2B. see attached PDF for more details.

Attachment 1: Target_Index_2022-07-06.pdf
Target_Index_2022-07-06.pdf
  2351   Thursday, July 28, 2022, 10:47 Travis CaveSpent Target VaultStandard Operation SiC#43Spent Target Move

 The spent target SiC#43 was moved from the north hot cell in pail #272 and place in 5A of the spent target vault. See attached PDF for details.

Attachment 1: Target_Index_2022-07-28.pdf
Target_Index_2022-07-28.pdf
  2357   Thursday, August 18, 2022, 10:13 Travis CaveSpent Target VaultStandard Operation Ta#64Spent Target Move

 The spent Ta#64 target in the north hot cell has been packaged and placed in the spent target vault. Pail#273 spot #5C 86.6mSv/hr upon removal from the north hot cell. For detail on the vault see attached PDF.

Attachment 1: Target_Index_2022-08-18.pdf
Target_Index_2022-08-18.pdf
  2366   Wednesday, September 14, 2022, 13:45 Adam NewsomeSpent Target VaultDevelopment  Storage Vault: cable replaced and e-chain upgrade

The motor cable for the storage vault was replaced as the old one was showing signs of wear. The U-track that the old cable ran through was also bent as a result of being hit.

In the process of replacing the cable, an e-chain was installed for cable management purposes. Mounting brackets were modified and a new U-track was installed as well. The new hardware is more robust than what was previously installed.

The vault door was opened and closed multiple times while observing the e-chain - everything behaved as expected. The system is operational.

 

Solidworks model IRH0189 is updated to show the changes

Attachment 1: PXL_20220914_183329159.jpg