2684
|
Tuesday, September 17, 2024, 13:42 |
Frank Song | ITW | Standard Operation | TM4 | TiC#9 | Module Connection | TM4 with target TiC#9 is connected
in ITW. See attachment. |
|
2701
|
Wednesday, October 09, 2024, 14:04 |
Frank Song | ITE | Standard Operation | TM2 | Ta#68 | Module Connection | TM2 with new target Ta#68 installed
is connected in ITE. Pls see form attached. |
|
2717
|
Tuesday, November 12, 2024, 12:30 |
Frank Song | ITW | Standard Operation | TM4 | UCx#46 | Module Connection | TM4 with new target UCx#46 was moved
from TCS to ITW and has been re-connected
right after. see attachment pls. |
|
2729
|
Wednesday, December 04, 2024, 08:05 |
Frank Song | ITE | Standard Operation | TM3 | UCx#47 | Module Connection | TM3 with new target UCx#47 was connected
in ITE right after be moved from TCS. |
|
2460
|
Tuesday, June 20, 2023, 12:37 |
Adam Newsome | Assembly/Bench Test | Development | | | Modifications to wire ropes for pails within existing F-308s | Based on a request from CNL (attached),
modifications were made to the wire ropes
protruding through the tops of F-308s to |
6x |
2681
|
Monday, September 16, 2024, 08:23 |
chad fisher | North Hot-Cell | Repair | | | Model N Remote end #9352 reapir | On Friday, September 6, 2024 Model 'N'
remote arm #9352 was removed from the NHC
right side installed position to investigate |
|
2758
|
Wednesday, January 29, 2025, 11:39 |
chad fisher | North Hot-Cell | Repair | | | Model N Remote Arm #9342 Tong Cable | Model N remote arm serial #9342 tong cable
has been un-jammed from between pulley 3D
(see picture) and casting (this is an ongoing |
|
1555
|
Friday, June 09, 2017, 11:21 |
chad fisher | North Hot-Cell | Maintenance | | | Model 'N' Slave Removal Through Roof | Isaac and Chad disengaged the slave end
of the manipulator and performed a slave
removal through the slave removal roof hatch. |
|
380
|
Tuesday, June 18, 2013, 14:00 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up testing / water block connections | The testing of the mock-up and tooling
has commenced.
Source tray mock-up has been driven |
|
334
|
Thursday, May 09, 2013, 10:13 |
chad fisher | South Hot-Cell | Development | | | Mock-up Progress | The source tray for the mock-up has been
setup for waterline bending and soldering/brazing.
Thanks to Travis for finding the |
![IMG_1056[1].JPG IMG_1056[1].JPG](attachment.png) ![IMG_1057[1].JPG IMG_1057[1].JPG](attachment.png) |
383
|
Friday, June 21, 2013, 09:26 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up Leak Check Results | The Mock-up has been leak tested after
the remote connection of the water blocks
and is leak tight! |
|
381
|
Wednesday, June 19, 2013, 08:15 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock up water block connections | All water block connections on the mock-up
have bben achieved. It is now ready for leak
checking. |
![20130619_080806[1].jpg 20130619_080806[1].jpg](attachment.png) |
2250
|
Thursday, September 23, 2021, 19:04 |
Adam Newsome | Spent Target Vault | Development | | | Mini-Storage: Remote Capability | Remote capability was added for the mini-storage
door control. The control signals originate
from the Opto 22 Module box that is used |
|
2241
|
Wednesday, August 11, 2021, 11:15 |
Adam Newsome | Spent Target Vault | Development | | | Mini-Storage: Cable track for e-chain installed | A cable track was installed between the
mini-storage vault and the silos, for the
purpose of implementing a retractable cable |
|
1528
|
Monday, May 08, 2017, 14:46 |
Travis Cave | Spent Target Vault | Maintenance | | | Mini Vault Door | Mini Vault Door as some difficulty
over coming a small hump on its track. To
open the door one needs to give the door |
|
2469
|
Friday, July 28, 2023, 10:21 |
Adam Newsome | Spent Target Vault | Maintenance | | | Mini Storage Vault: Bearing Lubrication | The bearings on the mini storage vault
were lubricated. It is suspected that this
has never been done. It is suggested that |
|
2470
|
Tuesday, August 01, 2023, 09:06 |
Adam Newsome | Crane | Development | | | Measuring Tape and Camera Removed from Target Hall Crane | In an effort to clean up the camera installation
on top of the ISAC target hall crane to resolve
a fault, the position measuring tape and |
|
942
|
Thursday, June 11, 2015, 13:11 |
chad fisher | Assembly/Bench Test | Repair | TM2 | | Measurements beyween ground Plane and HV TM2 Source tary | I've taken measurements between HV and
ground circuit on TM2 source tray as instructed.
At their closest points: |
|
354
|
Tuesday, May 21, 2013, 11:52 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | No Source Tray | May 16th Long HV conditioning | On May 16th 2013 the module was HV conditioned
all day. As a result the maximum stable voltage
has been increased to about 47kV (~4kV more |
|
2506
|
Monday, November 27, 2023, 12:01 |
chad fisher | South Hot-Cell | Maintenance | | | Manipulator tong cable and wrist replacement | Broken tong cable on SW manipulator (serial
#8106) of SHC was replaced today.
Following ISAC Hot Cell entry procedure, |
|