  ID Date Author Category Type Module Target/Number Subjectdown Text Attachments
  380   Tuesday, June 18, 2013, 14:00 chad fisherSouth Hot-CellDevelopmentTM3 Mock-up testing / water block connectionsThe testing of the mock-up and tooling
has commenced.
Source tray mock-up has been driven
  
  334   Thursday, May 09, 2013, 10:13 chad fisherSouth Hot-CellDevelopment  Mock-up ProgressThe source tray for the mock-up has been
setup for waterline bending and soldering/brazing.
Thanks to Travis for finding the
 IMG_1056[1].JPGIMG_1057[1].JPGIMG_1058[1].JPG 
  383   Friday, June 21, 2013, 09:26 chad fisherSouth Hot-CellDevelopmentTM3 Mock-up Leak Check ResultsThe Mock-up has been leak tested after
the remote connection of the water blocks
and is leak tight!
  
  381   Wednesday, June 19, 2013, 08:15 chad fisherSouth Hot-CellDevelopmentTM3 Mock up water block connectionsAll water block connections on the mock-up
have bben achieved. It is now ready for leak
checking.
 20130619_080806[1].jpg20130619_080808[1].jpg 
  2250   Thursday, September 23, 2021, 19:04 Adam NewsomeSpent Target VaultDevelopment  Mini-Storage: Remote CapabilityRemote capability was added for the mini-storage
door control. The control signals originate
from the Opto 22 Module box that is used
  
  2241   Wednesday, August 11, 2021, 11:15 Adam NewsomeSpent Target VaultDevelopment  Mini-Storage: Cable track for e-chain installedA cable track was installed between the
mini-storage vault and the silos, for the
purpose of implementing a retractable cable
 PXL_20210811_165201449.jpg 
  1528   Monday, May 08, 2017, 14:46 Travis CaveSpent Target VaultMaintenance  Mini Vault Door Mini Vault Door as some difficulty
over coming a small hump on its track. To
open the door one needs to give the door
  
  2469   Friday, July 28, 2023, 10:21 Adam NewsomeSpent Target VaultMaintenance  Mini Storage Vault: Bearing LubricationThe bearings on the mini storage vault
were lubricated. It is suspected that this
has never been done. It is suggested that
 PXL_20230728_162515733.jpg 
  2470   Tuesday, August 01, 2023, 09:06 Adam NewsomeCraneDevelopment  Measuring Tape and Camera Removed from Target Hall CraneIn an effort to clean up the camera installation
on top of the ISAC target hall crane to resolve
a fault, the position measuring tape and
  
  942   Thursday, June 11, 2015, 13:11 chad fisherAssembly/Bench TestRepairTM2 Measurements beyween ground Plane and HV TM2 Source taryI've taken measurements between HV and
ground circuit on TM2 source tray as instructed.
At their closest points:
  
  354   Tuesday, May 21, 2013, 11:52 Bevan MossConditioning StationStandard OperationTM3No Source TrayMay 16th Long HV conditioningOn May 16th 2013 the module was HV conditioned
all day. As a result the maximum stable voltage
has been increased to about 47kV (~4kV more
 16052013_TM3_long_HV_conditioning.xlsx 
  2506   Monday, November 27, 2023, 12:01 chad fisherSouth Hot-CellMaintenance  Manipulator tong cable and wrist replacementBroken tong cable on SW manipulator (serial
#8106) of SHC was replaced today. 
Following ISAC Hot Cell entry procedure,
  
  771   Tuesday, October 21, 2014, 08:55 chad fisherSouth Hot-CellRepair  Manipulator repairThe east manipulator handle has been adjusted
and is ready for use.
  
  1907   Wednesday, April 17, 2019, 12:03 chad fisherSouth Hot-CellRepair  Manipulator repairBroken handle cable of east manipulator
has been replaced and manipulator is operational
again.
  
  1324   Thursday, August 18, 2016, 13:57 chad fisherSouth Hot-CellMaintenance  Manipulator maitenanceSouth hot cell was entered to check to
replace cable if needed. Wrist cable showed
no signs of fraying or broken strands.
  
  1110   Wednesday, October 21, 2015, 09:49 chad fisherSouth Hot-CellRepair  Manipulator handle repairRebuild handle of manipulator serial 7986
(currently in the east position) and replaced
broken snap ring 5555-18h on west side of
  
  1744   Friday, June 29, 2018, 10:12 chad fisherSouth Hot-CellMaintenance  Manipulator Tong Cable ReplacementTuesday, June 26 the broken tong cable
was replaced on the west manipulator in the
south hot cell. Wednesday the tong cable
  
  1377   Monday, October 24, 2016, 10:10 chad fisherSouth Hot-CellRepair  Manipulator Repair CompleteMaico entered the hot cell and re-strung
the skipped cable back onto the pulleys this
morning. Manipulator is now operational.
  
  351   Friday, May 17, 2013, 10:04 chad fisherSouth Hot-CellRepair  Manipulator RepairManipulator has been sucessfully repaired.
Recieved 0.19 mSv. Took Approx. 10-20 minutes
  
  770   Monday, October 20, 2014, 14:18 chad fisherSouth Hot-CellRepair  Manipulator RepairThe broken cable on the east manipulator
has been replaced.
The handle will need some adjustments
  