1591
|
Wednesday, August 02, 2017, 15:13 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | SHC, TM2 leak check on HS line. |
HS line is leak checked at SHC this afternoon by helium spay. Leak detector base LR 0.0 XE-9atm.cc/sec. Base pressure 0.0Xe-4 torr. No leak has been found. This line will be helium pressured at TCS. It had a 1.7XE-7 atm.cc/sec leak rate on 70 psi helium at TCS during last two target checks.
2017-08-03. Helium pressure test on TM2 HS line at TCS is done. 70psi helium, 3 minutes. base leak rate 0.0xE-7 atm.cc/sec. Result: 1.8XE-7atm.cc/sec leak which is almost same as before. This line has a very small leak on water block seal under helium pressure test which we knew already. |
1606
|
Tuesday, August 29, 2017, 08:59 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 HS line leak checks |
TM4 HS line leak checks are done, at SHC and TCS. SHC: Helium spray. TCS: Helium pressurize 70psi. LD base LR 0.0 X E-9 atm.cc/sec. No leak has been found on both leak checks. |
1607
|
Tuesday, August 29, 2017, 09:01 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 has been connnected at TCS. |
TM4 has been connected at TCS. TCS water system has been started for TM4. TM4 and TCS vacuum pumping down is good so far. |
1609
|
Tuesday, September 05, 2017, 06:33 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Turned off TCS water system and vacuum system. |
Argon vent and disconnect TM4 at TCS. |
1612
|
Friday, September 08, 2017, 14:08 |
David Wang | Conditioning Station | Repair | TM3 | | TCS and TM3 |
TM3 is located at TCS and it is pumping down now. TCS water system has been started. All TCS water lines for TM3 module internal cooling are bypassed and looped at TCS top ground plate. Water only supply to TCS high current conductors. |
1613
|
Wednesday, September 13, 2017, 10:05 |
David Wang | Conditioning Station | Repair | TM3 | | Switch off TCS water system and vacuums |
Preparing vent the TCS/TM3. We will remove TM3 service tray cover plate after venting. |
1614
|
Wednesday, September 13, 2017, 16:05 |
David Wang | Conditioning Station | Repair | TM3 | | remove Tm3 service tray cover plate |
TM3 service tray cover plate has been removed. It is bagged and placed to TH b2 level south wall beside the silo. |
1615
|
Wednesday, September 13, 2017, 16:13 |
David Wang | Conditioning Station | Repair | TM3 | | TCS turbo pumps are started. |
TCS and TM3 all vacuum pumps are started. Everything is fine. |
1624
|
Friday, September 22, 2017, 12:13 |
David Wang | South Hot-Cell | Maintenance | TM2 | | TM2 service cap inside inspection. |
Two side panels on TM2 service cap were removed for TM2 service cap inside inspection. A piece of cable tie was found inside cap closing to service tray entrance area. All blue nylon insulators are inspected. They look good. The broken cable tie is moved out of service cap.
Panels are installed back after the inspection.
See attachments |
Attachment 1: TM2_serica_cap_inspection_002.JPG
|
|
Attachment 2: TM2_serica_cap_inspection_003.JPG
|
|
Attachment 3: TM2_serica_cap_inspection_004.JPG
|
|
Attachment 4: TM2_serica_cap_inspection_005.JPG
|
|
Attachment 5: TM2_serica_cap_inspection_008.JPG
|
|
1629
|
Thursday, September 28, 2017, 10:50 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 window and HS water lines at TCS. |
I did helium pressure test on TM2 containment box window and HS line at TCS. @ 70psi helium for 3 minutes, HS:2.2XE-7 atm.cc/sec., Window:1.2XE-7 atm.cc/sec. There is no change on HS. But LR on window is bigger than before that was in E -9atm.cc/sec range. |
1638
|
Tuesday, October 10, 2017, 10:38 |
David Wang | ITW | Standard Operation | | | 5 shielding blocks have been transferred from ITE to ITW . |
ITW is configured to take proton beam. |
1639
|
Tuesday, October 10, 2017, 10:45 |
David Wang | Conditioning Station | Repair | | | Re-route TCS water lines. |
TCS cooling polyurethane lines have been re-routed to solve to HV sparking issue on old configuration between lines and bais plate. New re-routed system is tested to 70KV without spark. No leak has been found on new lines after the test.
ECO 4369, drawings and models IRH1715, IRH1716 have been issued and released for this job. Drawings and Models are located in PDM-ISAC1 -TCS polyurethane water lines re-route folder. |
Attachment 1: TCS_re-route_001.JPG
|
|
Attachment 2: TCS_re-route_002.JPG
|
|
Attachment 3: TCS_re-route_003.JPG
|
|
Attachment 4: TCS_re-route_004.JPG
|
|
Attachment 5: TCS_re-route_005.JPG
|
|
Attachment 6: TCS_re-route_006.JPG
|
|
Attachment 7: TCS_re-route_007.JPG
|
|
Attachment 8: TCS_re-route_008.JPG
|
|
1647
|
Thursday, October 19, 2017, 10:11 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Leak check on TM4 HS line at SHC and TCS. |
Chad and I leak checked TM4 HS line after new target is installed yesterday. No leak has been found. Also, I helium pressurized the HS line at TCS this morning. TM4 HS line is good on this test. The TM4 gas line configuration on TM4 top is leak check as well. No problem. |
1656
|
Thursday, November 09, 2017, 09:34 |
David Wang | Conditioning Station | Standard Operation | TM2 | Ta#55 | Leak check on TM2 HS line at SHC and TCS. |
The TM2 HS line was leak checked at SHC yesterday . 0.9xE-9 atm.cc/sec.Helium sprayed by Chad, NO leak. It was helium pressurized at TCS this morning. Leak rat:2.5 XE-7 atm.c/sec. The result is same as last time check. No concern. |
1657
|
Thursday, November 09, 2017, 09:35 |
David Wang | Conditioning Station | Standard Operation | TM2 | Ta#55 | TM2 has been connected at TCS |
TCS vacuum system and water system have been started as well. Everything looks fine. |
1662
|
Tuesday, November 14, 2017, 14:34 |
David Wang | ITW | Standard Operation | TM2 | Ta#55 | TM2 has been connected in ITW. |
TM2 has been connected in ITW. All turbo-pumps are started. Everything works fine. |
1663
|
Wednesday, November 15, 2017, 08:55 |
David Wang | Conditioning Station | Standard Operation | | | Install shield plug onto TCS and pumping down TCS. |
Shielding plug is installed onto TCS. TCS is being pumped down to keep it under vacuum for the rest of the year. |
1671
|
Tuesday, January 02, 2018, 10:46 |
David Wang | ITE/ITW Cooling | Standard Operation | | | Start High active water system. |
High active water system was checked before restart. A small water leak on resin can supply valve was found. It is fixed. MP1 and MP2 were started and checked separately. System pressure and flow rate are normal.MP1 is in operation now. |
1672
|
Tuesday, January 02, 2018, 11:28 |
David Wang | ITE | Standard Operation | TM4 | | ITE annual water interlock check. |
Eric and I finished ITE annual water interlock check. Everything works properly. |
1676
|
Tuesday, January 16, 2018, 06:50 |
David Wang | ITE/ITW Cooling | Standard Operation | | | Field measurement on old resin tank in silo |
The old resin tank has been stored in silo since last year March. Without crane the tank up, We use the pole monitor measured the field around the bottom of the tank in silo. The average contact field on the bottom is about 4.0msv/hr. @0.5meter , the field is about 900usv/hr. It is still too hot to remove it. |