  930   Wednesday, June 03, 2015, 11:22 David WangConditioning StationStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015I revised the Target Hall schedule to July
21 2015. It is the time new TM2 with ZrC
target started at ITW.
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp 
  929   Tuesday, June 02, 2015, 14:39 David WangConditioning StationStandard OperationTM4SiC #31TM4 and CS turbo- pumps are started .TM4 and CS turbo-pumps are started this
afternoon. Everything is good so far.
  
  928   Tuesday, June 02, 2015, 14:38 David WangConditioning StationRepairTM4 replace broken TM4 IG1 TM4 IG1 filament was broken during
last run  at ITE.  The broken filament
is replaced with a new one today when TM4
 002.JPG006.JPG 
  927   Tuesday, June 02, 2015, 14:32 David WangSouth Hot-CellStandard OperationTM4SiC #31Leak check on TM4 HS water line with new SiC #31 target. at SHCChad and I leak checked TM4 HS water line
with SiC #31 target installed. leak rate:0.0xE-9atm.cc/sec. 
No leak.  The line will be helium pressurized
 003.JPG005.JPG001.JPG 
  926   Tuesday, June 02, 2015, 11:54 Travis CaveConditioning StationStandard OperationTM4SiC#31Module movedTM#4 with SiC#31 has been moved from the
south hot cell to the conditioning station.
  
  925   Tuesday, June 02, 2015, 10:39 Travis CaveSouth Hot-CellStandard OperationTM4SiC#31Electrical CheckElectrical check on TM#4 with SiC#31. See
attached PDF for details.
 TM4_SiC31_elecchk_SHC.PDF 
  924   Tuesday, June 02, 2015, 09:43 chad fisherSouth Hot-CellStandard OperationTM4SiC#31SiC#31 installedTa #45 has been removed from TM4 and SIC#31installed.   
  923   Tuesday, June 02, 2015, 06:51 David WangSouth Hot-CellStandard OperationTM4 Target Hall Scheduled Activities April 07 - June 26 2015Target Hall schedule weekly update. All
jobs are finished on time so far.
 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf 
  922   Monday, June 01, 2015, 14:24 Travis CaveSouth Hot-CellStandard OperationTM4Ta#45Electrical CheckPost beam electrical check on the Ta#45
target installed on TM#4. See attached PDF.
 TM4_Ta45_elecchk_postbeam.PDF 
  921   Monday, June 01, 2015, 11:23 Travis CaveITEStandard OperationTM4Ta#45Module movedTM#4 with Ta#45 has been moved from the
east target station to the south hot cell.
  
  920   Friday, May 29, 2015, 09:16 Travis CaveConditioning StationStandard OperationTM2no targetModule movedTM#2 with no source tray has been moved
from the conditioning station to the north
east silo.
  
  919   Wednesday, May 27, 2015, 08:57 Travis CaveConditioning StationStandard OperationTM2 Module movedTM#2 with no source tray has been moved
from the south hot cell to the conditioning
station.
  
  918   Tuesday, May 26, 2015, 14:34 chad fisherSouth Hot-CellRepairTM2 Shutter replacementThe shutter in TM2 was successfully replaced
today.
New lock washer and nut were installed
 Shutter.jpg 
  917   Tuesday, May 26, 2015, 11:49 Grant MinorAssembly/Bench TestRepairTM2 TM2 New Source Tray - Braze & Solder Report - 22 May 2015Hello,

For reference, I have attached a list
 6x 
  916   Friday, May 22, 2015, 15:44 David WangITWStandard OperationTM1UCx125 Shielding blocks have been transferred from ITE to ITW.5 shielding blocks have been transferred
from ITE to ITW. I  checked all ITW
water signals, and they are good.  ITW
  
  915   Wednesday, May 13, 2015, 13:55 chad fisherSouth Hot-CellRepairTM2 Shutter removalTM2 has been successfully de-shuttered.
All went pretty much according to
plan except I had to remove one fastener
 TM2_20150513_131339.jpgTM2_20150513_134232.jpg 
  914   Monday, May 11, 2015, 11:20 David WangSouth Hot-CellStandard OperationTM2 Target Hall Scheduled Activities April 07 - June 26 2015The schedule has some changes due to 
new TM2 source tray coil cooling line leaking
at test stand. Now,It is re-scheduled in
 6x 
  913   Monday, May 11, 2015, 10:45 Anders MjosConditioning StationMaintenance  RGA electronics box installed The communications chip has been
replaced. The electronics box has been grounded
(see attached pdf).
 2015-05_RGA_GND_connection.pdf 
  912   Thursday, May 07, 2015, 11:02 Travis CaveSouth Hot-CellRepairTM2No targetWiring of TM#2Wires in TM#2 have been terminated at the
top of the module.
  
  911   Wednesday, May 06, 2015, 14:30 Travis CaveSouth Hot-CellRepairTM2No targetWiring of TM#2Wires for TM#2 steering elements, and png
gauge have been run down to the containment
box level. Chad has placed them in the little
 Photo_2015-05-06_8_26_10_AM.JPGPhoto_2015-05-06_8_26_17_AM.JPG 