IDdown Date Author Category Type Module Target/Number Subject
  1020   Tuesday, July 28, 2015, 10:17 David WangITERepair  ITE TP4 has been replaced

Tony and I replaced the ITE TP4 turbo pump today. The pumping time on controller has been reset to 0. The replaced broken  pump is bagged and stored at west end of TH.

  1019   Tuesday, July 28, 2015, 10:12 David WangConditioning StationStandard OperationTM4UCx 13Helium pressure test on TM4 HS line at CS

I did the helium pressure test on TM4 HS line at CS. Applied 70 psi helium  2 minutes. base leak rate0.0x E-9 atm.cc/sec.  No response during the test. No leak.

  1018   Monday, July 27, 2015, 17:03 David WangConditioning StationStandard OperationTM4UCx 13UCx13 and TM4 under vacuum at CS.

I connected the CS  vacuum system  to TM4. The CS and TM4 turbo pumps are started. Everything is good so far. The HS line will be pressured with helium tomorrow for leak checking. The CS and TM4 will be vented with Argon on Wednesday morning as planned before moved to ITE.

  1017   Monday, July 27, 2015, 15:46 David WangSouth Hot-CellStandard Operation  The yellow steel plug is put on SHC in TH

The yellow steel plug is put on SHC in TH. The spent target is inside the SHC.The field around the SHC area in TH is so high that we have put it on. It will be moved out on this Thursday just before the spent target move. 

  1016   Monday, July 27, 2015, 15:34 David WangITEStandard OperationTM4 Leak check on TM4 HS water line with new UCX target. at SHC

Chad and I leak checked the HS line at SHC after UCX target installation. On first round helium spray, one of VCR fitting has a leak to E-6 atm.cc/sec range. Chad tightened the fitting, and solved the problem. We leak checked both VCR fittings twice. No leak. The line will be helium pressured at CS tomorrow.

  1015   Monday, July 27, 2015, 14:37 Travis CaveSouth Hot-CellStandard OperationTM4UC#13Module moved

TM#4 has been moved from the east target station (morning with SiC#31), and moved to the conditioning station from the south hot cell with UC#13 on it.

  1014   Monday, July 27, 2015, 13:38 Travis CaveSouth Hot-CellStandard OperationTM4UC#13Electrical Check

Electrical check of TM#4 with UC#13 at the south hot cell. See PDF for details.

  1013   Monday, July 27, 2015, 12:12 Travis CaveSouth Hot-CellStandard OperationTM4SiC#31Electrical Check

Electrical check of TM#4 post beam with target (SiC#31) on and module without target on. There is a short between the target and EE when the target is on and when the target was removed short went away. See the PDF for details.

  1012   Friday, July 24, 2015, 14:41 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule moved

TM#2 has been moved from the south hot cell to north east silo.

  1011   Friday, July 24, 2015, 10:04 David WangITEStandard Operation  5 Shielding blocks have been moved from ITE to block storage area.

Dan and I moved 5 shielding blocks from ITE to block storage area. The move is smooth.

  1010   Thursday, July 23, 2015, 10:23 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015

Update Target Hall schedule after the changing on TM2 process. See attachment 1,2

  1009   Wednesday, July 22, 2015, 12:13 chad fisherSouth Hot-CellRepairTM2 TM2 Short Findings

Pin X was unplugged, short remained, however any slight pressure on the block towards the source tray makes the short go away.

Confirmed clearance between the EE and thr R / U coil lines as well as MSP of coil line.

Camera inspection would seem to indicate that ALL issues stem from a common location...there is a spot where both the pin X waterline and the one of the R / U waterline  contact the heat shield waterline...one on one side of the heat shield line and the other on the other side.

 

 

  1008   Wednesday, July 22, 2015, 11:31 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical Check

Electrical check done on TM#2 around the 25th of June 2015, this was before the coil line leak was found.

  1007   Tuesday, July 21, 2015, 12:38 David WangITWRepair  ITW external water leak on dump circuit has been fixed.

The leaking 1/8 NPT(M)-1/4NPT(F) adapter on the ITW dump circuit is replaced.

  1006   Tuesday, July 21, 2015, 12:29 David WangITEMaintenance  target pit Hepa filter

Target pit Hepa filter has been replaced today. There is 500 counts on swipe which is taken inside of the replaced filter. The field measurement on the filter wood box  is less than 0.5 usv/hr on contact. Right now,The outlets of the old filter are sealed with thick plastic and duct tape. The whole filter is wrapped with plastic sheet and tape. It has been moved to SHC ante room.  It will be moved out of there by Tony.N soon with RPG help.

  1005   Tuesday, July 21, 2015, 10:40 Grant MinorAssembly/Bench TestRepairTM2 TM2 - bench inspection photos from 6-June-2015
  1004   Tuesday, July 21, 2015, 09:21 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical Check Failed

TM#2 has failed the electrical check see attached pdf for details.

  1003   Monday, July 20, 2015, 17:11 Grant MinorSouth Hot-CellRepairTM2 TM2 New Source Tray - additional photos 20 July 2015

A few additional higher-resolution photos of the TM2 source tray with new spacer ITA6270, and bent copper ground line clip.

Also attached is a photo of a 3/8" copper line placed in between the loose ECR line and the Mounting Support Plate line, for dimensional reference.

  1002   Monday, July 20, 2015, 14:12 chad fisherSouth Hot-CellRepairTM2 TM2 Status

Ultem high voltage spacer installed and 9 pin banana plug plugged in. Target has been inserted into the hot cell and will be installed after base-line electrical checks...probably first thing in the morning.

  1001   Friday, July 17, 2015, 13:51 chad fisherSouth Hot-CellRepairTM2 TM2 Status

Gas lines extensions installed yesterday were too long and gas lines touched top inside of containment box. They have been removed and the gas lines re-installed in their original manner. Gas lines have been "adjusted" as to clear the tube heater lines, which was the original issue.