1489
|
Wednesday, April 12, 2017, 07:26 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | Roughing down overnight. Turbo pumps are
started this morning. Everything looks good
so far. |
|
1491
|
Wednesday, April 12, 2017, 12:51 |
David Wang | South Hot-Cell | Repair | TM3 | | TM3 Ram readings @ SHC | We have a ram installed on SHC pole
which is 0.5 meter to module shielding
block surface. the readings we got today |
|
1495
|
Thursday, April 13, 2017, 11:33 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 water llines at TCS. | LD BLR :0.0 X E-9 atm.cc/sec. BP:0.0XE-4
torr. helium 70 psi. 3 minutes on each circuit
|
|
1497
|
Thursday, April 13, 2017, 14:16 |
David Wang | Crane | Repair | | | TH crane: east side main hoist brake assembly is replaced. | Gordon Crane technician Tom Kauss finished
the replacement of the east side main hoist
brake assembly. A new set up is installed. |
|
1498
|
Wednesday, April 19, 2017, 08:29 |
David Wang | Conditioning Station | Standard Operation | | | TH schedule 132 update in first beam week | Update schedule to show job process in
TH. See attachment 1,2. |
|
1499
|
Friday, April 21, 2017, 08:19 |
David Wang | Conditioning Station | Repair | | | Low frequency on TCS TGHT flow sensor. | Anders and I found a low frequency issue(13hz
only) on TCS TGHT flow sensor when doing
TM4 conditioning. By trouble shooting, We |
|
1500
|
Monday, April 24, 2017, 09:52 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Switch off TCS water system and vacuums | The TCS bias was turn off before that.
The TM2 and TCS are still under vacuum now. |
|
1501
|
Monday, April 24, 2017, 16:06 |
David Wang | South Hot-Cell | Repair | TM2 | | Crane main hoist strane noise when lifting up TM2 | When lifting up TM2 (20000lbs) this
afternoon, TH crane has a strange noise on
main hoist. The module was lift up less than |
|
1502
|
Monday, April 24, 2017, 16:11 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TCS TP1s is restarted. | TCS IG1S is switched on as well.
The reason to start the pump is to prepare
a possible extended TM2 conditioning at TCS |
|
1505
|
Wednesday, April 26, 2017, 10:24 |
David Wang | ITW | Standard Operation | TM2 | | TM2 ITW | TM2 was moved and connected in ITW yesterday
afternoon. After roughing down, ITW turbo
pumps are started. ITW TP4 can not be started |
|
1516
|
Monday, May 01, 2017, 12:32 |
David Wang | Crane | Repair | | | TH crane burning smell | TH crane burning smell showed again this
morning. It appeared after 1-1.5 hours of
continuously using during the F308 flasks |
|
1517
|
Monday, May 01, 2017, 13:11 |
David Wang | South Hot-Cell | Repair | TM3 | | Electrical Check on TM3 after fibergalss is moved in SHC. | RU( coil 1), F (anode), and 60kv bias(HS,
Gasline, and MSP) are shorted together.
Other lines are good. They are measured |
|
1521
|
Thursday, May 04, 2017, 14:06 |
David Wang | Conditioning Station | Repair | TM3 | | A vacuum to air leak on TM3 service cap round side panel was found and fixed.. | During TM3 roughing down yesterday afternoon,The
vacuum gauges CG1 and CG1S stopped at 1.20
torr and refused to drop down. Leak detector |
|
1523
|
Friday, May 05, 2017, 11:06 |
David Wang | Crane | Standard Operation | TM3 | | TH crane is used for 5 shielding blocks transferring. | TH crane is used for transferring
five shielding blocks(30000lbs) today. All
brakes work fine. Mostly, I do not need |
|
1524
|
Friday, May 05, 2017, 11:53 |
David Wang | Conditioning Station | Repair | TM3 | | sparking on TM3 serice cap top. | Sparking was found this morning inside
HV cover on TCS in TH while TM3 was HV conditioning
at TCS. The TCS bias was set to 50KV when |
|
1527
|
Monday, May 08, 2017, 09:49 |
David Wang | Conditioning Station | Standard Operation | | | TH schedule 132 update weekly | Update TH schedule weekly to show the job
process. |
|
1529
|
Tuesday, May 09, 2017, 07:00 |
David Wang | Conditioning Station | Repair | TM3 | | Follow up Aurelia's entry, TM3 and TCS current limits investigation. | Aurelia and I investigated this current
limit issue May 8th. First, By separating
TM3 from TCS. we found the problem is on |
|
1530
|
Tuesday, May 09, 2017, 12:45 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 service tray side panel is cleaned and installed back to TM3 | TM3 service tray side panel is cleaned
and installed back to TM3 this morning. I
visually inspected service tray insulators. |
|
1534
|
Friday, May 12, 2017, 07:42 |
David Wang | Crane | Repair | | | TH crane burning smell, smoke, and big noise on east side main hoist brake assembly. | This morning, when I prepare for today's
crane check, The crane made a very strong
noise without any load during the full speed |
|
1539
|
Wednesday, May 17, 2017, 08:31 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | Leak check on TM4 HS line at SHC | Chad and I finished leak check on HS line
with UCx target installed on it. Base
Leak rate:0.0X 10^-9 atm.cc/sec, Base pressure |
|