Thursday, August 20, 2015, 09:38, David Wang, Conditioning Station, Repair, TM2, , TM2 was disconnected at CS
|
TM2 was disconnected at CS. Travis and I did electrical check before the venting. After,The module was vented and moved to SHC. The moving is smooth. |
Wednesday, August 19, 2015, 14:52, David Wang, Conditioning Station, Repair, TM2, , TM2 at CS
|
During the TM2 HV test at CS, It failed. In order to confirm there is no any water leak inside the module after the heaters and beam extraction test,
I disconnected all the water lines on the TM2, and purged the water lines with pressure air. Leak detector was reconnected back to the TM2 service cap,
and all water lines are pressurized with 80psi helium again each for 2 minutes.No any leak had been found during the test. All the water lines are still |
Monday, August 17, 2015, 10:44, Anders Mjos, Conditioning Station, Development, TM2, LP-FEBIAD Test Target (empty), Conditioning TM2 Source Tray with FEBIAD test target 
|
TGHT, TBHT, ANODE and COIL power tested (some amps/volts)
Monday, August 17, 2015, 10:43: BIAS/EL/EE to 15/7.5/1.5 kV
Monday, August 17, 2015, 10:45 : COIL 20A, ANODE 200V |
Friday, August 14, 2015, 10:00, David Wang, Conditioning Station, Repair, TM2, , Started CS water package for TM2
|
I finished the rest TM2 connections to CS, and started CS cooling package. Everything works fine so far. |
Thursday, August 13, 2015, 17:17, David Wang, Conditioning Station, Repair, TM2, Dummy target, TM2 at CS
|
TM2 has been moved to CS. All turbo-pumps have been started. The pumping down is good so far. I connected the leak detector to service cap, and
finished the leak check today. The LD base LR:0.0Xe-9atm.cc/sec. 80psi helium were applied to coil1, coil 2. HS and window circuits, each for 2minutes.
No any response has been found on LD. So all water lines are leak tight now. I also sprayed helium to top service cap checking all air to |
Thursday, August 13, 2015, 14:36, Travis Cave, Conditioning Station, Standard Operation, TM2, Dummy Target, Module moved
|
TM#2 with the dummy target has been moved to the conditioning station. |
Thursday, August 13, 2015, 13:46, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Status
|
As previously mentioned, dump target installed with new mounting and high current fasteners.
Leak Check complete and ready to move to CS at 1:30 |
Thursday, August 13, 2015, 11:34, Travis Cave, South Hot-Cell, Standard Operation, TM2, Dummy Target, Electrical Check  
|
Electrical check of TM2 without target after that widget has installed, electrical check with the shunts on, electrical check with the dummy target installed. |
Thursday, August 13, 2015, 09:17, chad fisher, South Hot-Cell, Repair, TM2, , TM2 status  
|
Tuesday, August 11, insulator ITA6272 was installed onto the "pin x" line (unused plasma electrode) and tested; it seems to have successfully
eliminated the shorts on that line.
Wednesday, August 12 "shunts" installed on tube heater and oven circuit and electrically tested. |
Monday, August 10, 2015, 14:07, Isaac Earle, South Hot-Cell, Repair, TM2, , TM2 Containment Box Removed
|
The containment box was taken off TM2 in preparation for installation of a new coil line isolator.
ITA6272 and ITA6273 have been received from the Scintillator Shop. ITA6274 should be ready by the end of today. |
Friday, August 07, 2015, 10:01, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 19 2015   
|
Weekly update target hall schedule and activities. See attachment 1,2
Update and extend Target Hall schedule to Sep 08. See attachment 3,4 |
Thursday, August 06, 2015, 11:40, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Module moved
|
TM#2 is now in the south hot cell |
Thursday, August 06, 2015, 10:26, Travis Cave, Spent Target Vault, Standard Operation, , , Spent Target Measurments and Assays
|
All targets but one ( SiC#31 went in last week) have been measured or assayed. See attached PDF for the details. |
Friday, July 31, 2015, 09:47, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 019 2015 
|
Weekly update of Target Hall schedule after so many jobs have been finished in this week. See attachment 1, 2 |
Thursday, July 30, 2015, 14:05, Travis Cave, Spent Target Vault, Standard Operation, , SiC#31, Spent target moved
|
SiC#31 has been moved to the spent target vault. It is in pail #127 and placed in spot 3C of the vault is was 489mSv/hr when removed from the south hot
cell. See attached pdf for vault status |
Wednesday, July 29, 2015, 10:14, David Wang, ITE, Standard Operation, TM4, , TM4 has been connected in ITE
|
Dan and I connected TM4 in ITE. We checked all water signals on ITE cooling circuits. Everything is good. |
Wednesday, July 29, 2015, 08:59, Travis Cave, ITE, Standard Operation, TM4, UC#13, Module moved
|
TM#4 with UC#13 has been moved from the conditioning station to the east target station. |
Wednesday, July 29, 2015, 06:24, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, Stopped the CS and TM4 pumps and vent with argon.
|
Dan and I stopped the CS and TM4 pumps. We are venting the CS with argon for UCX13 target. |
Tuesday, July 28, 2015, 14:40, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#31 UCx#13, SiC#31 removed UCx#13 installed
|
SiC#31 has been removed from TM4 and UCx#13 installed. UCx#13 connection to the 9 pin connector was VERY VERY tight to the tube heater insulator on both
the test jig and module.
|
Tuesday, July 28, 2015, 14:36, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#31, SiC#31 Autopsy
|
Extraction electrode was removed from SiC#31 and target inspected.
Pictures of findings can be found at https://documents.triumf.ca/docushare/dsweb/View/Collection-15131
|
|