Entry  Thursday, August 20, 2015, 09:38, David Wang, Conditioning Station, Repair, TM2, , TM2 was disconnected at CS 
Entry  Wednesday, August 19, 2015, 14:52, David Wang, Conditioning Station, Repair, TM2, , TM2 at CS 
Entry  Monday, August 17, 2015, 10:44, Anders Mjos, Conditioning Station, Development, TM2, LP-FEBIAD Test Target (empty), Conditioning TM2 Source Tray with FEBIAD test target FirstBeamTM2SourceTray2015-08-17.pngTM2_Source_Tray_with_FEBIAD_test_target.docx
Entry  Friday, August 14, 2015, 10:00, David Wang, Conditioning Station, Repair, TM2, , Started CS water package for TM2  
Entry  Thursday, August 13, 2015, 17:17, David Wang, Conditioning Station, Repair, TM2, Dummy target, TM2 at CS 
Entry  Thursday, August 13, 2015, 14:36, Travis Cave, Conditioning Station, Standard Operation, TM2, Dummy Target, Module moved 
Entry  Thursday, August 13, 2015, 13:46, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Status 
Entry  Thursday, August 13, 2015, 11:34, Travis Cave, South Hot-Cell, Standard Operation, TM2, Dummy Target, Electrical Check TM2_elechknotgtafterwidget.PDFTM2_elechknotgtshunt.PDFTM2_elecchkdummytgt.PDF
Entry  Thursday, August 13, 2015, 09:17, chad fisher, South Hot-Cell, Repair, TM2, , TM2 status 20150811_132709.jpg20150813_083255.jpg20150813_090814.jpg
Entry  Monday, August 10, 2015, 14:07, Isaac Earle, South Hot-Cell, Repair, TM2, , TM2 Containment Box Removed 
Entry  Friday, August 07, 2015, 10:01, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 19 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Entry  Thursday, August 06, 2015, 11:40, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Module moved 
Entry  Thursday, August 06, 2015, 10:26, Travis Cave, Spent Target Vault, Standard Operation, , , Spent Target Measurments and Assays Vault_Storage_August_6_2015.pdf
Entry  Friday, July 31, 2015, 09:47, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 019 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
Entry  Thursday, July 30, 2015, 14:05, Travis Cave, Spent Target Vault, Standard Operation, , SiC#31, Spent target moved Vault_Storage_July_30_2015.pdf
Entry  Wednesday, July 29, 2015, 10:14, David Wang, ITE, Standard Operation, TM4, , TM4 has been connected in ITE 
Entry  Wednesday, July 29, 2015, 08:59, Travis Cave, ITE, Standard Operation, TM4, UC#13, Module moved 
Entry  Wednesday, July 29, 2015, 06:24, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, Stopped the CS and TM4 pumps and vent with argon. 
Entry  Tuesday, July 28, 2015, 14:40, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#31 UCx#13, SiC#31 removed UCx#13 installed 20150727_115314.jpg
Entry  Tuesday, July 28, 2015, 14:36, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#31, SiC#31 Autopsy 