ID Date Author Category Type Module Target/Number Subject
  1008   Wednesday, July 22, 2015, 11:31 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical Check

Electrical check done on TM#2 around the 25th of June 2015, this was before the coil line leak was found.

Attachment 1: TM#2elecchksourcetraynotgt62515.PDF
TM#2elecchksourcetraynotgt62515.PDF
  1007   Tuesday, July 21, 2015, 12:38 David WangITWRepair  ITW external water leak on dump circuit has been fixed.

The leaking 1/8 NPT(M)-1/4NPT(F) adapter on the ITW dump circuit is replaced.

  1006   Tuesday, July 21, 2015, 12:29 David WangITEMaintenance  target pit Hepa filter

Target pit Hepa filter has been replaced today. There is 500 counts on swipe which is taken inside of the replaced filter. The field measurement on the filter wood box  is less than 0.5 usv/hr on contact. Right now,The outlets of the old filter are sealed with thick plastic and duct tape. The whole filter is wrapped with plastic sheet and tape. It has been moved to SHC ante room.  It will be moved out of there by Tony.N soon with RPG help.

  1005   Tuesday, July 21, 2015, 10:40 Grant MinorAssembly/Bench TestRepairTM2 TM2 - bench inspection photos from 6-June-2015
Attachment 1: TM2_Source_Tray_Bench_Inspection_6-June-2015_04.JPG
TM2_Source_Tray_Bench_Inspection_6-June-2015_04.JPG
Attachment 2: TM2_Source_Tray_Bench_Inspection_6-June-2015_13.JPG
TM2_Source_Tray_Bench_Inspection_6-June-2015_13.JPG
Attachment 3: TM2_Source_Tray_Bench_Inspection_6-June-2015_11.JPG
TM2_Source_Tray_Bench_Inspection_6-June-2015_11.JPG
  1004   Tuesday, July 21, 2015, 09:21 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical Check Failed

TM#2 has failed the electrical check see attached pdf for details.

Attachment 1: TM#2_elec_chk_source_tray_no_tgt.PDF
TM#2_elec_chk_source_tray_no_tgt.PDF
  1003   Monday, July 20, 2015, 17:11 Grant MinorSouth Hot-CellRepairTM2 TM2 New Source Tray - additional photos 20 July 2015

A few additional higher-resolution photos of the TM2 source tray with new spacer ITA6270, and bent copper ground line clip.

Also attached is a photo of a 3/8" copper line placed in between the loose ECR line and the Mounting Support Plate line, for dimensional reference.

Attachment 1: 3-8ths_gap_check_15July2015.JPG
3-8ths_gap_check_15July2015.JPG
Attachment 2: TM2_New_Source_Tray_20July2015.JPG
TM2_New_Source_Tray_20July2015.JPG
Attachment 3: TM2_Spacer_ITA6270_and_copper_ground_clip_detail_20July2015.JPG
TM2_Spacer_ITA6270_and_copper_ground_clip_detail_20July2015.JPG
  1002   Monday, July 20, 2015, 14:12 chad fisherSouth Hot-CellRepairTM2 TM2 Status

Ultem high voltage spacer installed and 9 pin banana plug plugged in. Target has been inserted into the hot cell and will be installed after base-line electrical checks...probably first thing in the morning.

Attachment 1: 20150720_134819.jpg
20150720_134819.jpg
Attachment 2: 20150720_135747.jpg
20150720_135747.jpg
Attachment 3: 20150720_140100.jpg
20150720_140100.jpg
  1001   Friday, July 17, 2015, 13:51 chad fisherSouth Hot-CellRepairTM2 TM2 Status

Gas lines extensions installed yesterday were too long and gas lines touched top inside of containment box. They have been removed and the gas lines re-installed in their original manner. Gas lines have been "adjusted" as to clear the tube heater lines, which was the original issue.

Attachment 1: 20150717_134123.jpg
20150717_134123.jpg
  1000   Thursday, July 16, 2015, 14:36 chad fisherSouth Hot-CellRepairTM2 TM2 Status

IMG gauge, clip for ground to window lines and gas line extensions were installed today.

David and I also tried to locate the short between the coil line and MSP/Heat Shield...it went away for a bit...but is back.

Attachment 1: 20150716_110247.jpg
20150716_110247.jpg
Attachment 2: 20150716_142818.jpg
20150716_142818.jpg
  999   Thursday, July 16, 2015, 07:38 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 07 2015

Update the TH schedule according to present TM2 refurbishment process. See attachments 1,2

2015-07-20 , Update the TH schedule after some changes on TM2 and TM4 arrangement. See attachments 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  998   Wednesday, July 15, 2015, 11:18 David WangSouth Hot-CellRepairTM2 leak check coil line(R,U) on TM2 at SHC

Chad and I leak checked the coil 1 circuit(R,U) after rebuilt coil line is installed on TM2 source tray. The pumping down on the circuit is very quick and smooth. The LD base lake rate 0.0xE-9 atm.cc/sec. Base pressure0.0xE-4 torr.

Chad sprayed lots helium on the R( coil 1+)and U(coil 1 -) water blocks. During  1 minute waiting time, there is no any response on LD. The R and U water blocks and C-seals are leak tight.

Attachment 1: 007.JPG
007.JPG
Attachment 2: 008.JPG
008.JPG
  997   Wednesday, July 15, 2015, 11:02 chad fisherSouth Hot-CellRepairTM2 TM2 Coil Line Vacuum Leak Check

TM2 coil line R,U has been vacuum leaked check at the hot cell and has passed with no response from the leak detector.

  996   Wednesday, July 15, 2015, 09:44 chad fisherSouth Hot-CellRepairTM2 Coil Line replacement

water block jig installed, module side sealing surfaces re-polished and cleaned. Coil line inserted into the hot cell and installed onto the module. Bolts torqued to 90 in.lbs. Received .13mSv.

Attachment 1: TM2_20150715_093157.jpg
TM2_20150715_093157.jpg
Attachment 2: TM2_20150715_094745.jpg
TM2_20150715_094745.jpg
  995   Tuesday, July 14, 2015, 12:56 chad fisherSouth Hot-CellRepairTM2 TM2 containment box removed

Containment box was removed from Tm2 this morning  in preparation for installation of coil line and all the trimmings.

  994   Tuesday, July 14, 2015, 08:42 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule moved

TM#2, no target, has been moved from the north east silo to the south hot cell.

  993   Monday, July 13, 2015, 11:31 Travis CaveConditioning StationStandard OperationTM1no targetModule moved

TM#1 has been moved back to the south west silo from the conditioning station.

  992   Friday, July 10, 2015, 14:41 Anders MjosConditioning StationMaintenanceTM1 Replaced roughing pump

 The roughing pump was replaced with a more leak tight pump due to the discovery of Rn-220 migration while roughing on TM1 in TCS

  991   Friday, July 10, 2015, 09:33 chad fisherSouth Hot-CellRepairTM2 Coil Line Decon

Coil line has been in RPG's ultrasonic decon over night. Initial swipes this morning picked up 5000 counts. It has been decontaminated to the point no more contamination is being found and nothing can be found with the frisker...so...it's ready for Maico and Dan?

  990   Thursday, July 09, 2015, 14:02 David WangConditioning StationDevelopmentTM1 TM1 is pumping down at CS

TM1 and CS  vacuum system are connected. All turbo-pumps are started. The new TP1S works fine also. The pumping down looks good so far. During the TM1 and CS roughing down time, Joe .M noticed a Rn-220 level surge up in TH . Then,the Rn220  level slowly dropped back. Anders suspected this Rn-220 surging is related to the TM1 roughing down at CS. We decided we will stop the pumps , vent the CS , and roughing  again tomorrow. During the same time Joe will monitor  Rn-220 level in TH to see if the surging is repeatable. We want to learn more on this TH Rn-220 issue.

  989   Thursday, July 09, 2015, 13:51 chad fisherSouth Hot-CellRepairTM2 Coil line removal hot cell

coil line has been removed from the hot cell. Initial decon was performed...after it still appears to have approximately 200 counts. It will now be transfered to the rad waste decon facility for further decon.