ID Date Author Category Type Module Target/Number Subject Text Attachments
  1063   Tuesday, September 08, 2015, 10:11 David WangITWStandard OperationTM2ZrC5 Shielding blocks have been transferred from ITE to ITW.Maico and Dan moved 5 shielding blocks
from ITE to ITW. The ITW is configured to
take proton beam.
  
  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015I attach new Target Hall schedules here
for 2015 fall and winter runs (beam schedule
129). The TH excel sheet schedule for beam
 Target_Hall_shedule_129_Sep_to_Dec.xlsxTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1061   Tuesday, September 01, 2015, 16:55 Anders MjosConditioning StationMaintenance  TBHT power supply remvoed The power supply is needed as a spare
for the failed TGHT p/s in ITW
  
  1060   Tuesday, September 01, 2015, 16:03 Grant MinorITWStandard OperationTM2ZrC #7Photos of TM2 Connection Procedure on Docushare 1Sept2015https://documents.triumf.ca/docushare/dsweb/View/Collection-15323   
  1059   Tuesday, September 01, 2015, 14:54 David WangITWStandard OperationTM2 TM2 has been connectec in ITW.TM2 has been connected in ITW. During the
connection, Anders and I  found the
TM2  high current cables used in ITE
  
  1058   Tuesday, September 01, 2015, 10:38 David WangITWMaintenanceTM2 ITW top tank flange clean up and r-ring replacement.During last run, ITW dump circuit
had a water leak on an adaptor below the
pressure gauge. The top tank flange, slot,
 ITW_o-ring_replacement_2015-09-01_008.JPGITW_o-ring_replacement_2015-09-01_007.JPGITW_o-ring_replacement_2015-09-01_006.JPG 
  1057   Tuesday, September 01, 2015, 10:32 Travis CaveITWStandard OperationTM2ZrC #7Module movedTM#2 with ZrC#7 has been moved from the
conditioning station  to the west target
station.
  
  1056   Tuesday, September 01, 2015, 06:25 David WangConditioning StationStandard OperationTM2ZrCArgon venting TM2 at CSArgon venting TM2 at CS.   
  1055   Thursday, August 27, 2015, 10:10 Anders MjosConditioning StationStandard OperationTM2ZrC#7Conditioning new Source TrayThursday, August 27, 2015, 10:10: Started
water system. TK2 level reduced from 24.9
to 23.5 in. 
 2015-08-31_Service_Cap_Sparking_on_Rubber_Plug.pdfTM2_Source_Tray_with_ZrC#7.docxVacuum_gague_calibration.xlsx 
  1054   Thursday, August 27, 2015, 08:43 Travis CaveConditioning StationStandard OperationTM2ZrC #7Electrical CheckElectrical check of TM#2 at the conditioning
station under vacuum. The resistance value
of the target to 60kV common is a bit lower
 TM2_elec_chk_ZrC7_CS.PDF 
  1053   Wednesday, August 26, 2015, 14:52 David WangConditioning StationStandard OperationTM2ZrCHelium pressure test on TM2 HS and window lines at CSLD base LR 0.0xE-9 atm.cc/sec , 80 psi
helium 2 minutes on HS and window circuits.
No leak. Also, the reinstalled(after rewiring
  
  1052   Wednesday, August 26, 2015, 14:30 David WangConditioning StationStandard OperationTM2ZrCTM2 and Cs vacuum sysyem has been connected at CS.Turbo-pumps are started . The pumping down
is good so far.
  
  1051   Wednesday, August 26, 2015, 14:28 David WangConditioning StationStandard OperationTM2ZrCLeak check on TM2 HS and windowwater line with new ZrC target at SHCChad and I leak checked TM2 HS and window
circuit VCR joints with ZrC target and containment
box installed at SHC. No leak has been found.
  
  1050   Wednesday, August 26, 2015, 11:12 Travis CaveConditioning StationStandard OperationTM2ZrC #7Module movedTM#2 with ZrC#7 has been moved to the conditioning
station from the south hot cell.
  
  1049   Wednesday, August 26, 2015, 10:55 chad fisherSouth Hot-CellRepairTM2ZrC#7New wiring and targetNew wiring was installed yesterday as well
as ZrC#7 which had its high current fasteners
torqued to 130 in lbs.
 20150826_090047.jpg 
  1048   Wednesday, August 26, 2015, 09:54 Anders MjosConditioning StationMaintenance  Topped up water in TCS:TK2 Filled to 24.9 in   
  1047   Wednesday, August 26, 2015, 09:20 Travis CaveSouth Hot-CellStandard OperationTM2ZrC #7Electrical CheckElectrical check of TM#2 with ZrC #7 installed  TM2_elec_chk_ZrC7_SHC.PDF 
  1046   Tuesday, August 25, 2015, 13:54 Grant MinorSouth Hot-CellRepairTM2ZrC#7TM2 - Electrical / HV Short Repair and Current Status (ZrC target)Hello all, 

TM2's first performance in the Conditioning
 TM2_Loose_Wires_Touching_Febiad_Gas_Line_notes_21Aug2015.jpgTM2_Wire_Bundle_Clear_of_Febiad_Gas_Line_notes_25Aug2015.jpg 
  1045   Friday, August 21, 2015, 11:38 Anders MjosSouth Hot-CellRepairTM2FEBIAD Test TargetSteerer wires found to be touching the gas linesYesterday TM2 was inspected in the SHC.
Spark marks were found both on the steerer
wires and on the ANODE wire. The steerer
  
  1044   Thursday, August 20, 2015, 13:48 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - Sep 08 2015 Weekly update target hall schedule.See
attachment 1,2
Spring and summer run is close to
 Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf 