  1098   Wednesday, October 14, 2015, 12:42 David WangITWStandard OperationTM2ZrC#7TM2 has been disconnected in ITW

Dan and I disconnected TM2 in ITW this morning.

  1097   Tuesday, October 13, 2015, 10:53 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Weekly update schedule. TM3 evaluation schedule in Nov is added.  

update the schedule after  the cancellation of TM2 from SHC to CS trip.see attachments 3,4

  1096   Thursday, October 08, 2015, 14:08 David WangSouth Hot-CellStandard OperationTM3Dummy target febiad.TM3 has been moved from SHC to NW silo

Bill and I moved TM3 from SHC to NW silo with a dummy febiad target installed on it. The move is smooth.

  1095   Tuesday, October 06, 2015, 21:12 Aurelia LaxdalSouth Hot-CellRepairTM3 TM3 service cap inspection in target hall

David Wang and I did the service cap inspection in target hall: see WP I2015-10-06-10.<br>

Signs of sparking were seen underneath 3 insulators: E ("Cavity"), A ("Oven+") and B ("Oven -") at the pair water lines coming out of the  feed-through and going to the HV chase. Specifically one water line of E is very close to the feed-through insulator (2-3mm gap) and here the sparking sings are more prominent: see picture.

  1094   Tuesday, October 06, 2015, 13:25 David WangITEStandard OperationTM4 Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Weekly update target hall schedule. See attachment 1,2.

  1093   Tuesday, October 06, 2015, 13:00 David WangITERepairTM4  spark on top of TM4 in ITE

During the weekend condition The TM4 spark at 30KV without vacuum response. It is confirmed the spark is from the top TM4 this morning.The flexible cables in a  black wire sleeve which is used for febiad X pin connection drooped too close to the TM4 surface plate, and caused the sparking. The problem is fixed by Anders and David. The cables is put back where it should stay.  After test, no sparking on the top.

  1092   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.

The ITE is configured to take proton beam.

  1091   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.

The ITE is configured to take proton beam.

  1090   Monday, October 05, 2015, 10:19 Anders MjosConditioning StationMaintenance  Chiller maintenance

 will be performed Tuesday October 6th

Tuesday, October 06, 2015: Maintenance re-schedlued for Wednesday October 7th

  1089   Thursday, October 01, 2015, 09:18 Travis CaveSpent Target VaultStandard Operation  Targets transfered to mini storage.

In preparation for shipping of the spent targets five have been moved to the mini storage. The following target were moved to the mini storage, SiC#26, Ta#36, UC#9,10,11.

  1088   Wednesday, September 30, 2015, 11:14 Travis CaveSouth Hot-CellRepairTM3no targetElectrical Check

TM#3 electrical check at the south hot cell, no target, all value are done at 1000Volts. See the attached PDF for the results.

  1087   Wednesday, September 30, 2015, 08:50 Travis CaveSouth Hot-CellMaintenanceTM3no targetModule moved

TM#3 is in the south hot cell it was moved from the north west silo.

  1086   Tuesday, September 29, 2015, 12:31 David WangITEStandard OperationTM4Ta#46TM4 has been connected in ITE

Dan and I connected TM4 in ITE. The turbo- pumps are started. Water supply to TM4 only at this stage. Everything is good so far.

  1085   Tuesday, September 29, 2015, 09:38 Travis CaveITEStandard OperationTM4Ta#46Module moved

TM#4 with Ta#46 has been moved to ITE from the conditioning station.

  1084   Monday, September 28, 2015, 10:10 David WangConditioning StationStandard OperationTM4Ta#46Switched off CS vacuum pumps and water system

I switched off CS vacuum pumps and water system after Isac opps finished the TM4 conditioning at CS.

  1083   Friday, September 25, 2015, 08:21 Travis CaveSouth Hot-CellStandard Operation UC#13Spent Target move

The spent UC#13 target has been moved from the south hot cell to the ISAC spent target vault. It was placed pail #128 and in tray spot 1A. It was 21.5mSv/hr upon removal from the hot cell. See attached PDF for details.

  1082   Friday, September 25, 2015, 07:56 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

weekly update see attachment

  1081   Thursday, September 24, 2015, 14:59 Friedhelm AmesConditioning StationStandard OperationTM4Ta#46start high voltage conditioning
  1080   Thursday, September 24, 2015, 07:00 David WangConditioning StationMaintenanceTM4Ta#46Turned off TCS all vacuum pumps and water pumps.

TCS:MP1 back up pressure went up too high (700mtorr).I turned off all the pumps.The TCS is under vacuum still. TCS water  package cooling fans showed error on control page.The water pumps are stopped  also.

Restarted the vacuum pumps 40 minutes after stopping. Everything is back to normal. The MP1 back up pressure need to be monitored frequently before we have a final solution on this issue.

Reset the CS cooling package on roof and restarted the water  pumps. The system is running good so far.

  1079   Wednesday, September 23, 2015, 14:35 David WangConditioning StationStandard OperationTM4Ta#46TM4 has been connected at CS

TM4 has been connected at CS. Turbo- pumps and water system are started and running . The HV cover has been installed on the module. Everything is good so far.