Entry  Wednesday, August 26, 2015, 10:55, chad fisher, South Hot-Cell, Repair, TM2, ZrC#7, New wiring and target 20150826_090047.jpg
New wiring was installed yesterday as well as ZrC#7 which had its high current fasteners torqued to 130 in lbs.
 
Entry  Wednesday, August 26, 2015, 09:54, Anders Mjos, Conditioning Station, Maintenance, , , Topped up water in TCS:TK2 
 Filled to 24.9 in
Entry  Wednesday, August 26, 2015, 09:20, Travis Cave, South Hot-Cell, Standard Operation, TM2, ZrC #7, Electrical Check TM2_elec_chk_ZrC7_SHC.PDF
Electrical check of TM#2 with ZrC #7 installed
Entry  Tuesday, August 25, 2015, 13:54, Grant Minor, South Hot-Cell, Repair, TM2, ZrC#7, TM2 - Electrical / HV Short Repair and Current Status (ZrC target) TM2_Loose_Wires_Touching_Febiad_Gas_Line_notes_21Aug2015.jpgTM2_Wire_Bundle_Clear_of_Febiad_Gas_Line_notes_25Aug2015.jpg
Hello all, 

TM2's first performance in the Conditioning Station with the new source  tray was not great, with sparking and HV degradation beginning to occur
Entry  Friday, August 21, 2015, 11:38, Anders Mjos, South Hot-Cell, Repair, TM2, FEBIAD Test Target, Steerer wires found to be touching the gas lines 
Yesterday TM2 was inspected in the SHC. Spark marks were found both on the steerer wires and on the ANODE wire. The steerer wires (GND)  were touching
the gas lines (60kV). This is likely the cause of the sparking observed at the Conditioning Station (e-log).
Photos are available on DocuShare
Entry  Thursday, August 20, 2015, 13:48, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - Sep 08 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
 Weekly update target hall schedule.See attachment 1,2
Spring and summer run is close to the end. This will be the last update on this old schedule. See attachment3,4.    A new schedule
for TH activities after mini shut down will be posted next time.
Entry  Thursday, August 20, 2015, 11:00, Travis Cave, Conditioning Station, Standard Operation, TM2, Dummy Target, Electrical Check TM2_elecchkdummytgtatCS.PDF
TM#2 electrical check at the conditioning station. All pumps were off but the module was not vented.
Entry  Thursday, August 20, 2015, 10:15, Travis Cave, South Hot-Cell, Standard Operation, TM2, Dummy Target, Module moved 
TM#2 is now in the south hot cell.
Entry  Thursday, August 20, 2015, 09:38, David Wang, Conditioning Station, Repair, TM2, , TM2 was disconnected at CS 
TM2 was disconnected at CS. Travis and I did  electrical check before the venting. After,The module was vented and moved to SHC. The moving is smooth.
Entry  Wednesday, August 19, 2015, 14:52, David Wang, Conditioning Station, Repair, TM2, , TM2 at CS 
During the TM2 HV test at CS, It failed. In order to confirm there is no any water leak inside the module after the heaters and beam extraction test,
I disconnected all the water lines on the TM2, and purged the water lines with pressure air. Leak detector was reconnected back to the TM2 service cap,
and all water lines are pressurized with 80psi helium again each for 2 minutes.No any leak had been found during the test. All the water lines are still
Entry  Monday, August 17, 2015, 10:44, Anders Mjos, Conditioning Station, Development, TM2, LP-FEBIAD Test Target (empty), Conditioning TM2 Source Tray with FEBIAD test target FirstBeamTM2SourceTray2015-08-17.pngTM2_Source_Tray_with_FEBIAD_test_target.docx
TGHT, TBHT, ANODE and COIL power tested (some amps/volts)
Monday, August 17, 2015, 10:43: BIAS/EL/EE to 15/7.5/1.5 kV
Monday, August 17, 2015, 10:45 : COIL 20A, ANODE 200V
Entry  Friday, August 14, 2015, 10:00, David Wang, Conditioning Station, Repair, TM2, , Started CS water package for TM2  
I finished the rest TM2 connections to CS, and started CS cooling package. Everything works fine so far.
Entry  Thursday, August 13, 2015, 17:17, David Wang, Conditioning Station, Repair, TM2, Dummy target, TM2 at CS 
TM2 has been moved to CS. All turbo-pumps have been started. The pumping down is good so far.  I connected the leak detector to service cap, and
finished the leak check today.  The LD base LR:0.0Xe-9atm.cc/sec. 80psi helium were applied to coil1, coil 2. HS and window circuits, each for 2minutes.
No any response has been found on LD. So all water lines are leak tight now. I also sprayed   helium to top service cap checking all air to  
Entry  Thursday, August 13, 2015, 14:36, Travis Cave, Conditioning Station, Standard Operation, TM2, Dummy Target, Module moved 
TM#2 with the dummy target has been moved to the conditioning station.
Entry  Thursday, August 13, 2015, 13:46, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Status 
As previously mentioned, dump target installed with new mounting and high current fasteners.
Leak Check complete and ready to move to CS at 1:30
Entry  Thursday, August 13, 2015, 11:34, Travis Cave, South Hot-Cell, Standard Operation, TM2, Dummy Target, Electrical Check TM2_elechknotgtafterwidget.PDFTM2_elechknotgtshunt.PDFTM2_elecchkdummytgt.PDF
Electrical check of TM2 without target after that widget has installed, electrical check with the shunts on, electrical check with the dummy target installed.
Entry  Thursday, August 13, 2015, 09:17, chad fisher, South Hot-Cell, Repair, TM2, , TM2 status 20150811_132709.jpg20150813_083255.jpg20150813_090814.jpg
Tuesday, August 11,  insulator ITA6272 was installed onto the "pin x" line (unused plasma electrode) and tested; it seems to have successfully
eliminated the shorts on that line.
Wednesday, August 12  "shunts" installed on tube heater and oven circuit and electrically  tested.
Entry  Monday, August 10, 2015, 14:07, Isaac Earle, South Hot-Cell, Repair, TM2, , TM2 Containment Box Removed 
The containment box was taken off TM2 in preparation for installation of a new coil line isolator.
ITA6272 and ITA6273 have been received from the Scintillator Shop.  ITA6274 should be ready by the end of today.
Entry  Friday, August 07, 2015, 10:01, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 19 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Weekly update target hall schedule and activities. See attachment 1,2
Update and extend Target Hall schedule to Sep 08.  See attachment 3,4
Entry  Thursday, August 06, 2015, 11:40, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Module moved 
TM#2 is now in the south hot cell