1860
|
Monday, January 21, 2019, 16:27 |
Isaac Earle | North Hot-Cell | Development | | | NHC in-cell camera wired to right side monitor | The NHC right side monitor has been
wired to display the signal from the in-cell
camera. This was tested using a snake |
|
1864
|
Thursday, January 31, 2019, 14:16 |
Isaac Earle | North Hot-Cell | Development | | | NHC grounding approval | Franco Mammarella was consulted regarding
electrical grounding of the NHC design (RS103
of Document-131915). After discussing |
|
1782
|
Thursday, September 13, 2018, 16:57 |
Isaac Earle | North Hot-Cell | Development | | | NHC grounding and mili-ohm testing | The
following equipment has been connected to
the building ground located in the Target |
|
2196
|
Thursday, March 04, 2021, 16:30 |
Isaac Earle | North Hot-Cell | Development | | | NHC gas delivery lines leak checked | The North Hot Cell gas delivery lines
(labeled 1, 2, and 3 on the hot and cold
side panels) were leak checked today. |
|
1442
|
Tuesday, February 28, 2017, 17:51 |
Isaac Earle | North Hot-Cell | Development | | | NHC flanged ducting connection sealed | The North Hot Cell ducting (IRH1617)
has been sealed with a bead of Sikaflex 1a
polyurethane construction sealant where the |
|
2430
|
Tuesday, April 11, 2023, 11:35 |
chad fisher | North Hot-Cell | Standard Operation | | | NHC fields post sample removal | The fields in the NHC after removal of
Ferran's graphite sample is 238 uSv/h. This
again seems to emanate for the items in the |
|
2432
|
Tuesday, April 18, 2023, 07:28 |
chad fisher | North Hot-Cell | Maintenance | | | NHC entry summary | NHC was entered on April 17, 2023 for inspection
and maintenance. Summary :
Compressible and non-compressible |
|
1421
|
Tuesday, January 17, 2017, 13:45 |
Isaac Earle | North Hot-Cell | Development | | | NHC ducting installed | The new ducting section connecting
the existing duct termination in the TCS
space to the NHC partition wall has been |
   |
1596
|
Wednesday, August 09, 2017, 16:39 |
Isaac Earle | North Hot-Cell | Development | | | NHC drain line into sump identified | The NHC drain line was tested by
pouring approximately 10 gallons of water
through the drain grate at the base of the |
|
1761
|
Wednesday, August 01, 2018, 09:47 |
Isaac Earle | North Hot-Cell | Development | | | NHC diagnostic signals and control panel tested | On July 30th the NHC diagnostic
signals were tested:
- 9 pin CPC: a shorting plug was |
|
1756
|
Thursday, July 19, 2018, 14:22 |
Isaac Earle | North Hot-Cell | Development | | | NHC diagnostic signals - connector and wiring details | Installation of the diagnostic connections
between the NHC hot and cold sides has been
completed. The cable bundle was prepared |
|
1825
|
Thursday, November 22, 2018, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | NHC design approved by High Voltage Engineer | To satisfy RS 101 from the NHC requirements
specification (Document-131915) Tomislav
Hurskovec was consulted regarding high voltage |
|
1847
|
Friday, January 04, 2019, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | NHC cameras tested | The NHC module support flange cameras (4
total) as well as the NHCSA camera were tested
today and confirmed to be working properly. |
  |
1577
|
Wednesday, July 05, 2017, 15:36 |
Isaac Earle | North Hot-Cell | Development | | | NHC and SHC nuclear ventilation flow sensors installed | Installation of new flow sensors
and transmitters for the NHC and SHC duct
lines was completed in the target hall today. |
 |
1780
|
Wednesday, September 12, 2018, 15:22 |
Isaac Earle | North Hot-Cell | Development | | | NHC air and gas supply lines - test and leak check | Testing was completed today on the NHC
air and gas supply lines. For each
line a Staubli plug was installed on the |
|
1345
|
Wednesday, September 07, 2016, 11:39 |
Isaac Earle | North Hot-Cell | Development | | | NHC North / South Wall Gap Measurements | Measurements were taken today of
the NHC north/south wall gap at the location
where the NHC/TCS partition wall will be |
|
1353
|
Thursday, September 15, 2016, 11:05 |
Isaac Earle | North Hot-Cell | Development | | | NHC / SHC feedthrough panel removed | The sheet metal panel covering the NHC/SHC
feedthrough port was removed today using
a slide-hammer to pull out the concrete anchors |
  |
2391
|
Tuesday, November 22, 2022, 14:53 |
Carla Babcock | North Hot-Cell | Maintenance | TM4 | | Multipin connector alignment pin on TM4 module loose | The pin on TM4 has become loose again,
making it very difficult to remove the multipin
connector with the last target, C#4. For |
|
65
|
Wednesday, January 04, 2012, 13:49 |
Travis Cave | Spent Target Vault | Standard Operation | | | Moving the spent targets to mini storage. | Well the first of this year's lucky winners
to win a fabulous one way trip to Chalk River
are as follows. UC#1, UC#2, Ta#25, Ta#26, |
|
113
|
Friday, May 25, 2012, 10:48 |
Travis Cave | Spent Target Vault | Standard Operation | | | Moving the spent targets to mini storage. | Five targets were moved to the mini storage
today in preparation for transfer of the
targets to the F308s later next week. The |
 |