Entry  Tuesday, October 06, 2015, 12:50, David Wang, ITE, Standard Operation, TM4, Ta#46, 5 Shielding blocks have been transferred from ITW to ITE. 
The ITE is configured to take proton beam.
Entry  Tuesday, October 06, 2015, 12:50, David Wang, ITE, Standard Operation, TM4, Ta#46, 5 Shielding blocks have been transferred from ITW to ITE. 
The ITE is configured to take proton beam.
Entry  Tuesday, October 06, 2015, 13:00, David Wang, ITE, Repair, TM4, , spark on top of TM4 in ITE 
During the weekend condition The TM4 spark at 30KV without vacuum response. It is confirmed the spark is from the top TM4 this morning.The flexible cables
in a  black wire sleeve which is used for febiad X pin connection drooped too close to the TM4 surface plate, and caused the sparking. The problem
is fixed by Anders and David. The cables is put back where it should stay.  After test, no sparking on the top.
Entry  Tuesday, October 06, 2015, 13:25, David Wang, ITE, Standard Operation, TM4, , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Weekly update target hall schedule. See attachment 1,2.
Entry  Thursday, October 08, 2015, 14:08, David Wang, South Hot-Cell, Standard Operation, TM3, Dummy target febiad., TM3 has been moved from SHC to NW silo 
Bill and I moved TM3 from SHC to NW silo with a dummy febiad target installed on it. The move is smooth.
Entry  Tuesday, October 13, 2015, 10:53, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Weekly update schedule. TM3 evaluation schedule in Nov is added.  
update the schedule after  the cancellation of TM2 from SHC to CS trip.see attachments 3,4
Entry  Wednesday, October 14, 2015, 12:42, David Wang, ITW, Standard Operation, TM2, ZrC#7, TM2 has been disconnected in ITW  
Dan and I disconnected TM2 in ITW this morning.
Entry  Wednesday, October 14, 2015, 12:44, David Wang, ITW, Standard Operation, TM2, ZrC#7, TM2 has been moved from ITW to SHC 
Bill and I remotely removed TM2 from ITW to SHC. The move is smooth.
Entry  Wednesday, October 14, 2015, 12:48, David Wang, South Hot-Cell, Standard Operation, TM2, ZrC#7, TM2 ZrC#7 after run electrical check at SHC. ZrC_#7_after_run_electrical_check.pdf
I did an electrical check on TM2 with ZrC #7 on it. The EE is short to 60KV bias. See attachment
Entry  Wednesday, October 14, 2015, 14:49, David Wang, South Hot-Cell, Standard Operation, TM2, , Install new high current cables to TM2 TM2_Febiad_High_current_cables_047.JPGTM2_Febiad_High_current_cables_048.JPGTM2_Febiad_High_current_cables_049.JPG
I installed a set of new high current cables for TM2 Febiad run. The top of TM2  is configured to Febiad mode. See attachments
Entry  Thursday, October 15, 2015, 08:07, David Wang, South Hot-Cell, Standard Operation, TM2, no target, TM2 no target electrical check at SHC. TM2_electrical_check_2015-10-16_no_target.pdf
I did a TM2 no target electrical check at SHC this morning. A to RU at 500v  is 250K which is low.   anode- x pin is dead short to 60kv
bias. RU is dead short to 60kv bias( as before).   see attachment
Entry  Monday, November 16, 2015, 08:04, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Update TH schedule according to changes. See attachment 1,2 .
update TH schedule weekly. See attachments 3,4
Entry  Monday, November 16, 2015, 10:37, David Wang, Conditioning Station, Repair, TM3, , TM3 has been disconnected at TCS. 
I stopped the TM3 and TCS vacuum pumps and water system. The TM3 is disconnected and vented. It will be moved to silo this afternoon.
Entry  Thursday, November 26, 2015, 06:25, David Wang, Conditioning Station, Standard Operation, TM4, UC#14, TM4 vacuum has been connected in TCS. 
TM4 vacuum has been connected in TCS. All vacuum pumps were started yesterday. The pumping down of TM4 and TCS are good so far.
Entry  Thursday, November 26, 2015, 07:34, David Wang, Conditioning Station, Standard Operation, TM4, UC#14, Helium pressure test on TM4 HS line at CS  
I did helium pressure test on TM4 HS line at TCS this morning.  70psi helium 3 minutes, 0.0xE-9 atm.cc/sec base leak rate. No response. No leak.
Entry  Thursday, November 26, 2015, 07:37, David Wang, Conditioning Station, Standard Operation, TM4, UC#14, TM4 has been connected at CS 
TM4 has been connected at TCS. The water system is started. The TCS HV cover for TM4 is installed also. Basically, The TM4 is ready for conditioning.
Entry  Monday, November 30, 2015, 11:46, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Weekly update TH schedule according to changes. see attachment 1,2 .
Update TH schedule before the weekend. see attachment 3,4
Entry  Tuesday, December 01, 2015, 06:41, David Wang, Conditioning Station, Standard Operation, TM4, UC#14, Turned off TCS all vacuum pumps and water pumps. 
I turned off TCS vacuum and water pumps. The TSC and TM4 are still under vacuum condition.
Entry  Tuesday, December 01, 2015, 14:30, David Wang, ITE, Standard Operation, TM4, UCx 13, TM4 has been connected in ITE 
TM4 has been connected in ITE. All turbo-pumps are started. Everything is good so far.
Entry  Friday, January 22, 2016, 14:24, David Wang, South Hot-Cell, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule (sketch) 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp
Post a sketch of 2016 winter shut down target hall schedule. see attachment 1,2
 UPDATE THE SCHEDULE ACCORDING TO CYCLOTRON SIDE JOB. SEE ATTACHMENTS 3,4