Entry  Monday, March 14, 2016, 11:24, David Wang, ITE/ITW Cooling, Maintenance, , , HALCW resin tank filter cartridges are changed today 002.JPG003.JPG006.JPG
Two of resin tank filter cartridges(supply and return) are changed today. Old cartridges and bagged and tagged. The contact field on them are 650usv/hr.
The new cartridges are fiber-glass, Triumf store item. After replacement, the field on contact with the filter case are about 10 usv/hr. But the field
on contact with top resin tank  has been increased from 45usv/hr  to 225 usv/hr
Entry  Monday, March 14, 2016, 15:22, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp
update schedule according to change. See attachment 1,2
 
Entry  Thursday, March 17, 2016, 14:57, David Wang, South Hot-Cell, Repair, TM2, , TM2 first round leak check in SHC 
Chad and I finished the first round check on Tm2 water lines.  The lines and spots checked are: Target oven + and - (front side braze  joints) , Tube
heater+and -(front side braze joints and water blocks),  coil2 and coil 1(front side braze joints and area close to water  blocks),. No leak has been found
on all above of them.  The last, we  checked   the GE which has the biggest leak so far. The leak detector  base leak rate only can get
Entry  Friday, March 18, 2016, 09:34, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Sep) Target_Hall_shedule_130_Apr_to_Sep_2016.xlsxTarget_Hall_shedule_130_Apr_to_Sep_2016.pdf
I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for  beam schedule
130 is under construction, and will be posted later.
Entry  Friday, March 18, 2016, 09:42, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum sysytem has been connected at TCS 
TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far.
Entry  Monday, March 21, 2016, 10:25, David Wang, Conditioning Station, Repair, TM2, , TM2 Helium pressure Test Result in TCS and ITW 
TM2 has been helium pressure tested in ITW and TCS. They are both tested with 70psi helium, each circuit for 3minutes. 
The leak detector base leak rate: 0.0X E-9 atm.cc/sec, base pressure 0.0 xE-4 torr  for both ITW and TCS. The test results are:
 
Entry  Monday, March 21, 2016, 11:30, David Wang, Conditioning Station, Repair, TM2, , TM2 and TCS vacuum pumps are stopped 
I stopped TM2 and TCS vacuum pumps. It will be vented and disconnected this afternoon for tomorrow  moving.   
Entry  Monday, March 21, 2016, 15:27, David Wang, Conditioning Station, Repair, TM2, , TM2 has been disconnected at TCS 
TM2 vacuum system has been disconnected at TCS. Venting is in process now.
Entry  Wednesday, March 23, 2016, 11:32, David Wang, South Hot-Cell, Repair, TM2, , TM2 Helium spray leak check on GE and MSP lines at SHC 
  Chad and I did the helium spray leak check on TM2 GE and MSP  water lines at SHC this morning. We confirmed the GE leak on water  blocks. We can
not found the MSP leak by using the helium spray since  its leak rate in TCS is much smaller than GE leak.  The leak check  process are as below:
Entry  Thursday, March 24, 2016, 13:15, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 and TCS vacuum system has been connected  
TM1 and TCS vacuum system have been connected. All turbo-pumps are started. The pumping down is fine.
Entry  Tuesday, March 29, 2016, 08:38, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 water lines helium pressure check at TCS TM1_PNG1_panel_o-ring_replacement_001.JPGTM1_PNG1_panel_o-ring_replacement_002.JPGTM1_PNG1_panel_o-ring_replacement_004.JPGTM1_PNG1_panel_o-ring_replacement_005.JPGTM1_PNG1_panel_o-ring_replacement_006.JPG
TM1 water lines helium pressure check at TCS is done. 70 psi helium was applied to water circuits. Leak detector base leak rate 0.0 x E-9 atm.cc/sec,
base pressure 0.0 x E-4 torr. The result shows as below:
 
Entry  Wednesday, March 30, 2016, 08:40, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp
update the schedule according to changes.See attachment1, 2.
Entry  Wednesday, March 30, 2016, 15:49, David Wang, Assembly/Bench Test, Repair, TM2, , TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo. 7x
On each water circuit in side the service cap, there are 4 soldering stems which two of them are inside blue nylon insulator and other two are connected
to service tray. Each stem has two soldering spots. See attachment pictures for detail location. I sprayed 15 psi helium on each soldering spots on stems 
for 20second on each circuit. I sprayed tons of helium inside each blue nylon.No any leak has been found during the check. The leak detector base leak
Entry  Friday, April 01, 2016, 14:41, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 and TCS vacuum system has been connected. TCS control page white out. 
I can not start the TCS pumps due to control page white out. Control group is working on this issue.
Control group fixed the white out problem. I started all turbo-pumps. The pumping down is good so far. The TM1 IG1 is broken. I will check it on
next Monday. It could be a broken filament. Then, the filament will be replaced.
Entry  Monday, April 04, 2016, 11:14, David Wang, Conditioning Station, Standard Operation, TM1, , Helium pressure test on TM1 HS line at CS 
New UCx target is installed on the module. 70psi helium,3 minutes. NO response on LD.  LD is pumped to bottom LR and LP during test.
Entry  Tuesday, April 05, 2016, 07:12, David Wang, Conditioning Station, Standard Operation, TM1, UC#15, stop CS vacuum pumps. 
Stop TCS vacuum pumps . Preparing argon venting on TM1 and TCS.
7:34 AM, Disconnected TM1 at TCS, argon venting now.
Entry  Tuesday, April 05, 2016, 12:36, David Wang, ITW, Standard Operation, TM1, , TM1 vacuum system has been connected in ITW. 
 All turbo -pumps are started.
Entry  Tuesday, April 05, 2016, 12:40, David Wang, ITE, Standard Operation, TM4, , I stopped ITE turbo pumps this morning 
The ITE and TM4 have been vented with Argon . TM4 vacuum system is disconnected in ITE.
Entry  Friday, April 08, 2016, 07:10, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 vacuum has been connected in ITE. 
All turbo pumps are started yesterday. The pumping down is good over night.
Entry  Friday, April 08, 2016, 07:13, David Wang, ITW, Standard Operation, TM1, UCx15, TM1 has been connected in ITW. 
After ITW HV test is done, TM1 has been connected to ITW. Water signals are checked in electrical room. They are good.