Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 82 of 140  Not logged in ELOG logo
Entry  Thursday, November 26, 2015, 07:37, David Wang, Conditioning Station, Standard Operation, TM4, UC#14, TM4 has been connected at CS 
TM4 has been connected at TCS. The water system is started. The TCS HV cover for TM4 is installed also. Basically, The TM4 is ready for conditioning.
Entry  Monday, November 30, 2015, 11:46, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Weekly update TH schedule according to changes. see attachment 1,2 .
Update TH schedule before the weekend. see attachment 3,4
Entry  Tuesday, December 01, 2015, 06:41, David Wang, Conditioning Station, Standard Operation, TM4, UC#14, Turned off TCS all vacuum pumps and water pumps. 
I turned off TCS vacuum and water pumps. The TSC and TM4 are still under vacuum condition.
Entry  Tuesday, December 01, 2015, 14:30, David Wang, ITE, Standard Operation, TM4, UCx 13, TM4 has been connected in ITE 
TM4 has been connected in ITE. All turbo-pumps are started. Everything is good so far.
Entry  Friday, January 22, 2016, 14:24, David Wang, South Hot-Cell, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule (sketch) 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp
Post a sketch of 2016 winter shut down target hall schedule. see attachment 1,2
 UPDATE THE SCHEDULE ACCORDING TO CYCLOTRON SIDE JOB. SEE ATTACHMENTS 3,4
Entry  Friday, February 12, 2016, 13:00, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule  6x
2016 Winter shut down target hall schedule. See attachments1,2.
 update the schedule weekly. Everything is on time so far. see attachment 3,4.
Update the schedule according to beam new beam schedule and target process. see attachment 5,6
Entry  Thursday, February 25, 2016, 06:48, David Wang, ITE, Standard Operation, , , 4 Shielding blocks have been transferred from ITE to block storage area. 
Dan and I transferred 4 shielding blocks from ITE to block storage area. The ITE pit is opened now.
Entry  Thursday, February 25, 2016, 06:52, David Wang, Conditioning Station, Standard Operation, , , stop CS vacuum pumps. 
I stopped the conditioning station vacuum pumps. The CS is still under vacuum without venting.
Entry  Thursday, February 25, 2016, 09:27, David Wang, ITW, Standard Operation, TM2, , TM2 has been disconnected in ITW 
TM2 has been disconnected in ITW (except vacuum lines). The vacuum system is still operating.
Entry  Thursday, February 25, 2016, 09:29, David Wang, ITE, Standard Operation, TM4, , TM4 has been disconnected in ITE. 
TM4 has been disconnect in ITE(except  vacuum lines). The ITE vacuum system is still operating.
Entry  Wednesday, March 02, 2016, 09:51, David Wang, ITW, Standard Operation, TM2, , all water lines on TM2 and TM4 are purged. 
All water lines on TM2 and TM4 are purged for upcoming water lines helium pressure test.
Entry  Wednesday, March 02, 2016, 10:04, David Wang, ITW, Standard Operation, TM2, , Leak check on ITW and TM2. 
Dan and I leak checked TM2 and ITW primary vacuum vessel. It was found a 1X E-7 atm.cc/sec leak on top T flange seal between TM2 and dump module in first
time check. But it is not a repeatable leak. I checked the same spot and around area two more times with increased helium volume.It did not show up again.
The first response could  be a helium drift to dry scroll pump. I will check it again later. The primar vacuum vessel on ITW and TM2 are leak free. 
Entry  Friday, March 04, 2016, 12:34, David Wang, ITE, Standard Operation, TM4, , TM4 ITE annual leak check 
Dan and I finished TM4 and ITE annual leak check on primary and secondary vacuum vessel. We found one leak on a KF25  blank off which is located
on the top of the service cap. It is a low E-7 atm.cc/sec range leak. But, it is very close to turbo-pumps so ITE IG1 and other gauges are not affected
by it very much. It is an easy fix. TheKF -25 center ring on the blank off  will be replaced  after vent . It be will leak checked again at CS
Entry  Friday, March 04, 2016, 13:58, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule 8x
Update Schedule according to changes.See attachment1, 2.
 Re-post it after some minor correction See attachment 3,4.
Update schedule according changes. See attachments 5,6
Entry  Monday, March 14, 2016, 11:24, David Wang, ITE/ITW Cooling, Maintenance, , , HALCW resin tank filter cartridges are changed today 002.JPG003.JPG006.JPG
Two of resin tank filter cartridges(supply and return) are changed today. Old cartridges and bagged and tagged. The contact field on them are 650usv/hr.
The new cartridges are fiber-glass, Triumf store item. After replacement, the field on contact with the filter case are about 10 usv/hr. But the field
on contact with top resin tank  has been increased from 45usv/hr  to 225 usv/hr
Entry  Monday, March 14, 2016, 15:22, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp
update schedule according to change. See attachment 1,2
 
Entry  Thursday, March 17, 2016, 14:57, David Wang, South Hot-Cell, Repair, TM2, , TM2 first round leak check in SHC 
Chad and I finished the first round check on Tm2 water lines.  The lines and spots checked are: Target oven + and - (front side braze  joints) , Tube
heater+and -(front side braze joints and water blocks),  coil2 and coil 1(front side braze joints and area close to water  blocks),. No leak has been found
on all above of them.  The last, we  checked   the GE which has the biggest leak so far. The leak detector  base leak rate only can get
Entry  Friday, March 18, 2016, 09:34, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Sep) Target_Hall_shedule_130_Apr_to_Sep_2016.xlsxTarget_Hall_shedule_130_Apr_to_Sep_2016.pdf
I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for  beam schedule
130 is under construction, and will be posted later.
Entry  Friday, March 18, 2016, 09:42, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum sysytem has been connected at TCS 
TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far.
Entry  Monday, March 21, 2016, 10:25, David Wang, Conditioning Station, Repair, TM2, , TM2 Helium pressure Test Result in TCS and ITW 
TM2 has been helium pressure tested in ITW and TCS. They are both tested with 70psi helium, each circuit for 3minutes. 
The leak detector base leak rate: 0.0X E-9 atm.cc/sec, base pressure 0.0 xE-4 torr  for both ITW and TCS. The test results are:
 
ELOG V2.9.2-2455