Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 80 of 139  Not logged in ELOG logo
  ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  1044   Thursday, August 20, 2015, 13:48 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - Sep 08 2015 Weekly update target hall schedule.See
attachment 1,2
Spring and summer run is close to
 Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf 
  1051   Wednesday, August 26, 2015, 14:28 David WangConditioning StationStandard OperationTM2ZrCLeak check on TM2 HS and windowwater line with new ZrC target at SHCChad and I leak checked TM2 HS and window
circuit VCR joints with ZrC target and containment
box installed at SHC. No leak has been found.
  
  1052   Wednesday, August 26, 2015, 14:30 David WangConditioning StationStandard OperationTM2ZrCTM2 and Cs vacuum sysyem has been connected at CS.Turbo-pumps are started . The pumping down
is good so far.
  
  1053   Wednesday, August 26, 2015, 14:52 David WangConditioning StationStandard OperationTM2ZrCHelium pressure test on TM2 HS and window lines at CSLD base LR 0.0xE-9 atm.cc/sec , 80 psi
helium 2 minutes on HS and window circuits.
No leak. Also, the reinstalled(after rewiring
  
  1056   Tuesday, September 01, 2015, 06:25 David WangConditioning StationStandard OperationTM2ZrCArgon venting TM2 at CSArgon venting TM2 at CS.   
  1058   Tuesday, September 01, 2015, 10:38 David WangITWMaintenanceTM2 ITW top tank flange clean up and r-ring replacement.During last run, ITW dump circuit
had a water leak on an adaptor below the
pressure gauge. The top tank flange, slot,
 ITW_o-ring_replacement_2015-09-01_008.JPGITW_o-ring_replacement_2015-09-01_007.JPGITW_o-ring_replacement_2015-09-01_006.JPG 
  1059   Tuesday, September 01, 2015, 14:54 David WangITWStandard OperationTM2 TM2 has been connectec in ITW.TM2 has been connected in ITW. During the
connection, Anders and I  found the
TM2  high current cables used in ITE
  
  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015I attach new Target Hall schedules here
for 2015 fall and winter runs (beam schedule
129). The TH excel sheet schedule for beam
 Target_Hall_shedule_129_Sep_to_Dec.xlsxTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1063   Tuesday, September 08, 2015, 10:11 David WangITWStandard OperationTM2ZrC5 Shielding blocks have been transferred from ITE to ITW.Maico and Dan moved 5 shielding blocks
from ITE to ITW. The ITW is configured to
take proton beam.
  
  1068   Tuesday, September 15, 2015, 08:24 David WangSouth Hot-CellRepairTM1UCx 13Leak check on TM1 window circuit soldering stems in service cap.I did a leak check on TM1 window circuit 
2 soldering  stems in service cap.The
round side panel was opened for the job.
  
  1071   Thursday, September 17, 2015, 11:50 David WangSpent Target VaultRepairTM1 TM1 window circuit leak check Leak check TM1 window circuit soldering
stems inside service cap when module is located
at NE silo. LD base LR 0.0xE-9atm.cc/sec. 
 TM1_leak_soldering_stems_001.JPGTM1_leak_soldering_stems_003.JPG 
  1075   Tuesday, September 22, 2015, 13:15 David WangSouth Hot-CellStandard Operation Ta#46Leak check on TM4 HS water line with new Ta#46 target. at SHCChad and I leak checked the HS line at
SHC. No leak. Leak rate 0.0xE-9atm.cc/sec.
  
  1078   Wednesday, September 23, 2015, 14:32 David WangConditioning StationStandard OperationTM4Ta#45Helium pressure test on TM4 HS line at CSHelium pressure test HS line at CS with
70 psi for 2 minutes. Base  leak rate
0.0xE-9atm.cc/sec. No response. The line
  
  1079   Wednesday, September 23, 2015, 14:35 David WangConditioning StationStandard OperationTM4Ta#46TM4 has been connected at CSTM4 has been connected at CS. Turbo- pumps
and water system are started and running
. The HV cover has been installed on the
  
  1080   Thursday, September 24, 2015, 07:00 David WangConditioning StationMaintenanceTM4Ta#46Turned off TCS all vacuum pumps and water pumps.TCS:MP1 back up pressure went up too high
(700mtorr).I turned off all the pumps.The
TCS is under vacuum still. TCS water 
  
  1082   Friday, September 25, 2015, 07:56 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015weekly update see attachment  Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1084   Monday, September 28, 2015, 10:10 David WangConditioning StationStandard OperationTM4Ta#46Switched off CS vacuum pumps and water systemI switched off CS vacuum pumps and water
system after Isac opps finished the TM4 conditioning
at CS.
  
  1086   Tuesday, September 29, 2015, 12:31 David WangITEStandard OperationTM4Ta#46TM4 has been connected in ITEDan and I connected TM4 in ITE. The turbo-
pumps are started. Water supply to TM4 only
at this stage. Everything is good so far.
  
  1091   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.The ITE is configured to take proton beam.   
  1092   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.The ITE is configured to take proton beam.   
ELOG V2.9.2-2455