  ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015I attach new Target Hall schedules here
for 2015 fall and winter runs (beam schedule
129). The TH excel sheet schedule for beam
 Target_Hall_shedule_129_Sep_to_Dec.xlsxTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1063   Tuesday, September 08, 2015, 10:11 David WangITWStandard OperationTM2ZrC5 Shielding blocks have been transferred from ITE to ITW.Maico and Dan moved 5 shielding blocks
from ITE to ITW. The ITW is configured to
take proton beam.
  
  1068   Tuesday, September 15, 2015, 08:24 David WangSouth Hot-CellRepairTM1UCx 13Leak check on TM1 window circuit soldering stems in service cap.I did a leak check on TM1 window circuit 
2 soldering  stems in service cap.The
round side panel was opened for the job.
  
  1071   Thursday, September 17, 2015, 11:50 David WangSpent Target VaultRepairTM1 TM1 window circuit leak check Leak check TM1 window circuit soldering
stems inside service cap when module is located
at NE silo. LD base LR 0.0xE-9atm.cc/sec. 
 TM1_leak_soldering_stems_001.JPGTM1_leak_soldering_stems_003.JPG 
  1075   Tuesday, September 22, 2015, 13:15 David WangSouth Hot-CellStandard Operation Ta#46Leak check on TM4 HS water line with new Ta#46 target. at SHCChad and I leak checked the HS line at
SHC. No leak. Leak rate 0.0xE-9atm.cc/sec.
  
  1078   Wednesday, September 23, 2015, 14:32 David WangConditioning StationStandard OperationTM4Ta#45Helium pressure test on TM4 HS line at CSHelium pressure test HS line at CS with
70 psi for 2 minutes. Base  leak rate
0.0xE-9atm.cc/sec. No response. The line
  
  1079   Wednesday, September 23, 2015, 14:35 David WangConditioning StationStandard OperationTM4Ta#46TM4 has been connected at CSTM4 has been connected at CS. Turbo- pumps
and water system are started and running
. The HV cover has been installed on the
  
  1080   Thursday, September 24, 2015, 07:00 David WangConditioning StationMaintenanceTM4Ta#46Turned off TCS all vacuum pumps and water pumps.TCS:MP1 back up pressure went up too high
(700mtorr).I turned off all the pumps.The
TCS is under vacuum still. TCS water 
  
  1082   Friday, September 25, 2015, 07:56 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015weekly update see attachment  Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1084   Monday, September 28, 2015, 10:10 David WangConditioning StationStandard OperationTM4Ta#46Switched off CS vacuum pumps and water systemI switched off CS vacuum pumps and water
system after Isac opps finished the TM4 conditioning
at CS.
  
  1086   Tuesday, September 29, 2015, 12:31 David WangITEStandard OperationTM4Ta#46TM4 has been connected in ITEDan and I connected TM4 in ITE. The turbo-
pumps are started. Water supply to TM4 only
at this stage. Everything is good so far.
  
  1091   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.The ITE is configured to take proton beam.   
  1092   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.The ITE is configured to take proton beam.   
  1093   Tuesday, October 06, 2015, 13:00 David WangITERepairTM4  spark on top of TM4 in ITEDuring the weekend condition The TM4 spark
at 30KV without vacuum response. It is confirmed
the spark is from the top TM4 this morning.The
  
  1094   Tuesday, October 06, 2015, 13:25 David WangITEStandard OperationTM4 Target Hall schedule from Sep 08th 2015 to Dec 25th 2015Weekly update target hall schedule. See
attachment 1,2.
 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf 
  1096   Thursday, October 08, 2015, 14:08 David WangSouth Hot-CellStandard OperationTM3Dummy target febiad.TM3 has been moved from SHC to NW siloBill and I moved TM3 from SHC to NW silo
with a dummy febiad target installed on it.
The move is smooth.
  
  1097   Tuesday, October 13, 2015, 10:53 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015Weekly update schedule. TM3 evaluation
schedule in Nov is added.  
update the schedule after  the
 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1098   Wednesday, October 14, 2015, 12:42 David WangITWStandard OperationTM2ZrC#7TM2 has been disconnected in ITW Dan and I disconnected TM2 in ITW this
morning.
  
  1099   Wednesday, October 14, 2015, 12:44 David WangITWStandard OperationTM2ZrC#7TM2 has been moved from ITW to SHCBill and I remotely removed TM2 from ITW
to SHC. The move is smooth.
  
  1100   Wednesday, October 14, 2015, 12:48 David WangSouth Hot-CellStandard OperationTM2ZrC#7TM2 ZrC#7 after run electrical check at SHC.I did an electrical check on TM2 with ZrC
#7 on it. The EE is short to 60KV bias. See
attachment
 ZrC_#7_after_run_electrical_check.pdf 