Entry  Tuesday, July 07, 2015, 12:12, David Wang, Conditioning Station, Repair, , , CS TP1S replacement 

CS TP1S had been replaced with a new TP-301 pump this morning.The old pump was broken last week.

Entry  Wednesday, July 08, 2015, 14:05, David Wang, South Hot-Cell, Repair, TM2, , leak check coil line(R,U) on TM2 at SHC  

Chad and I leak checked coil line(R,U) on TM2 at SHC yesterday. The leak detector was pumped down to 0.0Xe-9 atm.cc/sec before the check. Chad sprayed helium on the soldering joints connecting the cooling copper lines to the small holding blocks for the coil terminal(R,U).  After sprayed helium 2 seconds, I saw the leak rate on LD started to climbed up. The highest leak rate is 4.0xE-8 atm.cc/sec. It is a very positive response. We waited the leak detector pumped back to 0.0xE-9am.cc/sec, and tested again on the same joints. The result is same. Chad also sprayed helium on the R,U water blocks to check the C-seal. I saw a delayed tiny response on LD ( from 0.0 to 1.3xE-9atm.cc/sec). We think this tiny response is caused by the helium drifting to the leak soldering joint, but not a real C seal leak.

Entry  Wednesday, July 08, 2015, 14:24, David Wang, South Hot-Cell, Repair, TM2, , TM2 pressure bubble test on RU water blocks. 

July-06, 2015. Chad , Grant and I did the bubble test on R,U water blocks. We suspected the leak on the R,U circuit is from C seals on the water blocks so we did this test first. I applied both air and helium to R,U circuit , Chad applied snoop soap on the R,U water blocks.The air and helium pressure was increased from 40 psi to 90 psi Max step by step.Chad did not see any bubbles on the water blocks during the test. Since we did not find the leak source, we decided to do vacuum helium check on the all joints and c-seals of the R,U lines later.  Finally, We found the leak by vacuum helium spray the day after this bubble test. See other e-log.

Entry  Thursday, July 09, 2015, 14:02, David Wang, Conditioning Station, Development, TM1, , TM1 is pumping down at CS 

TM1 and CS  vacuum system are connected. All turbo-pumps are started. The new TP1S works fine also. The pumping down looks good so far. During the TM1 and CS roughing down time, Joe .M noticed a Rn-220 level surge up in TH . Then,the Rn220  level slowly dropped back. Anders suspected this Rn-220 surging is related to the TM1 roughing down at CS. We decided we will stop the pumps , vent the CS , and roughing  again tomorrow. During the same time Joe will monitor  Rn-220 level in TH to see if the surging is repeatable. We want to learn more on this TH Rn-220 issue.

Entry  Wednesday, July 15, 2015, 11:18, David Wang, South Hot-Cell, Repair, TM2, , leak check coil line(R,U) on TM2 at SHC 007.JPG008.JPG

Chad and I leak checked the coil 1 circuit(R,U) after rebuilt coil line is installed on TM2 source tray. The pumping down on the circuit is very quick and smooth. The LD base lake rate 0.0xE-9 atm.cc/sec. Base pressure0.0xE-4 torr.

Chad sprayed lots helium on the R( coil 1+)and U(coil 1 -) water blocks. During  1 minute waiting time, there is no any response on LD. The R and U water blocks and C-seals are leak tight.

Entry  Thursday, July 16, 2015, 07:38, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 07 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp

Update the TH schedule according to present TM2 refurbishment process. See attachments 1,2

2015-07-20 , Update the TH schedule after some changes on TM2 and TM4 arrangement. See attachments 3,4

Entry  Tuesday, July 21, 2015, 12:29, David Wang, ITE, Maintenance, , , target pit Hepa filter 

Target pit Hepa filter has been replaced today. There is 500 counts on swipe which is taken inside of the replaced filter. The field measurement on the filter wood box  is less than 0.5 usv/hr on contact. Right now,The outlets of the old filter are sealed with thick plastic and duct tape. The whole filter is wrapped with plastic sheet and tape. It has been moved to SHC ante room.  It will be moved out of there by Tony.N soon with RPG help.

Entry  Tuesday, July 21, 2015, 12:38, David Wang, ITW, Repair, , , ITW external water leak on dump circuit has been fixed. 

The leaking 1/8 NPT(M)-1/4NPT(F) adapter on the ITW dump circuit is replaced.

Entry  Thursday, July 23, 2015, 10:23, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 019 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp

Update Target Hall schedule after the changing on TM2 process. See attachment 1,2

Entry  Friday, July 24, 2015, 10:04, David Wang, ITE, Standard Operation, , , 5 Shielding blocks have been moved from ITE to block storage area. 

Dan and I moved 5 shielding blocks from ITE to block storage area. The move is smooth.

Entry  Monday, July 27, 2015, 15:34, David Wang, ITE, Standard Operation, TM4, , Leak check on TM4 HS water line with new UCX target. at SHC 

Chad and I leak checked the HS line at SHC after UCX target installation. On first round helium spray, one of VCR fitting has a leak to E-6 atm.cc/sec range. Chad tightened the fitting, and solved the problem. We leak checked both VCR fittings twice. No leak. The line will be helium pressured at CS tomorrow.

Entry  Monday, July 27, 2015, 15:46, David Wang, South Hot-Cell, Standard Operation, , , The yellow steel plug is put on SHC in TH 

The yellow steel plug is put on SHC in TH. The spent target is inside the SHC.The field around the SHC area in TH is so high that we have put it on. It will be moved out on this Thursday just before the spent target move. 

Entry  Monday, July 27, 2015, 17:03, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, UCx13 and TM4 under vacuum at CS. 

I connected the CS  vacuum system  to TM4. The CS and TM4 turbo pumps are started. Everything is good so far. The HS line will be pressured with helium tomorrow for leak checking. The CS and TM4 will be vented with Argon on Wednesday morning as planned before moved to ITE.

Entry  Tuesday, July 28, 2015, 10:12, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, Helium pressure test on TM4 HS line at CS 

I did the helium pressure test on TM4 HS line at CS. Applied 70 psi helium  2 minutes. base leak rate0.0x E-9 atm.cc/sec.  No response during the test. No leak.

Entry  Tuesday, July 28, 2015, 10:17, David Wang, ITE, Repair, , , ITE TP4 has been replaced 

Tony and I replaced the ITE TP4 turbo pump today. The pumping time on controller has been reset to 0. The replaced broken  pump is bagged and stored at west end of TH.

Entry  Wednesday, July 29, 2015, 06:24, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, Stopped the CS and TM4 pumps and vent with argon. 

Dan and I stopped the CS and TM4 pumps. We are venting the CS with argon for UCX13 target.

Entry  Wednesday, July 29, 2015, 10:14, David Wang, ITE, Standard Operation, TM4, , TM4 has been connected in ITE 

Dan and I connected TM4 in ITE. We checked all water signals on ITE cooling circuits. Everything is good.

Entry  Friday, July 31, 2015, 09:47, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 019 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp

Weekly update of Target Hall schedule after so many jobs have been finished in this week.  See attachment 1, 2

Entry  Friday, August 07, 2015, 10:01, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 19 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf

Weekly update target hall schedule and activities. See attachment 1,2

Update and extend Target Hall schedule to Sep 08.  See attachment 3,4

Entry  Thursday, August 13, 2015, 17:17, David Wang, Conditioning Station, Repair, TM2, Dummy target, TM2 at CS 

TM2 has been moved to CS. All turbo-pumps have been started. The pumping down is good so far.  I connected the leak detector to service cap, and finished the leak check today.  The LD base LR:0.0Xe-9atm.cc/sec. 80psi helium were applied to coil1, coil 2. HS and window circuits, each for 2minutes. No any response has been found on LD. So all water lines are leak tight now. I also sprayed   helium to top service cap checking all air to   vacuum seals. They are all good either. But, The new installed PGN1 does not work. Other thing need to mention is The TP2 is running at 2.45A which is 1A higher comparing to TP1. It need to be monitored to see if we have to replace it or not. The high current cables and water lines will be connected tomorrow morning.