  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

I attach new Target Hall schedules here for 2015 fall and winter runs (beam schedule 129). The TH excel sheet schedule for beam 129 is included also.

Weekly update of Target Hall Schedule.See Attachments 3,4

Attachment 1: Target_Hall_shedule_129_Sep_to_Dec.xlsx
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 5: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1063   Tuesday, September 08, 2015, 10:11 David WangITWStandard OperationTM2ZrC5 Shielding blocks have been transferred from ITE to ITW.

Maico and Dan moved 5 shielding blocks from ITE to ITW. The ITW is configured to take proton beam.

  1068   Tuesday, September 15, 2015, 08:24 David WangSouth Hot-CellRepairTM1UCx 13Leak check on TM1 window circuit soldering stems in service cap.

I did a leak check on TM1 window circuit  2 soldering  stems in service cap.The round side panel was opened for the job. I sprayed helium on the stems for 10 seconds. The leak detector got a tiny response(from 0.0xE-9 atm.cc/sec to 2.0xE-9 atm.cc/sec). The test  repeated again. The second time, LD climbed  to 1.2xE-9atm.cc/sec. It looks like there is a very tiny leak on the stems soldering spots. But , this is not the same leak we found from SHC helium spray which LD climbed to 1.4xE-8atm.cc/sec with only one click helium spray by Chad.

 Because of the high air flow at SHC when the round panel is removed, The result is not conclusive. The same test is done at silo without  airflow. We found a big leak on this soldering stems . See later e-log.

  1071   Thursday, September 17, 2015, 11:50 David WangSpent Target VaultRepairTM1 TM1 window circuit leak check

 Leak check TM1 window circuit soldering stems inside service cap when module is located at NE silo. LD base LR 0.0xE-9atm.cc/sec.  Only 1 second tiny amount  helium sprayed on stems soldering joints . LD got a quick response to high E-7 atm.cc/sec.Test is repeated again with same result.  See attachments

Attachment 1: TM1_leak_soldering_stems_001.JPG
TM1_leak_soldering_stems_001.JPG
Attachment 2: TM1_leak_soldering_stems_003.JPG
TM1_leak_soldering_stems_003.JPG
  1075   Tuesday, September 22, 2015, 13:15 David WangSouth Hot-CellStandard Operation Ta#46Leak check on TM4 HS water line with new Ta#46 target. at SHC

Chad and I leak checked the HS line at SHC. No leak. Leak rate 0.0xE-9atm.cc/sec.

  1078   Wednesday, September 23, 2015, 14:32 David WangConditioning StationStandard OperationTM4Ta#45Helium pressure test on TM4 HS line at CS

Helium pressure test HS line at CS with 70 psi for 2 minutes. Base  leak rate 0.0xE-9atm.cc/sec. No response. The line is leak tight.

  1079   Wednesday, September 23, 2015, 14:35 David WangConditioning StationStandard OperationTM4Ta#46TM4 has been connected at CS

TM4 has been connected at CS. Turbo- pumps and water system are started and running . The HV cover has been installed on the module. Everything is good so far.

  1080   Thursday, September 24, 2015, 07:00 David WangConditioning StationMaintenanceTM4Ta#46Turned off TCS all vacuum pumps and water pumps.

TCS:MP1 back up pressure went up too high (700mtorr).I turned off all the pumps.The TCS is under vacuum still. TCS water  package cooling fans showed error on control page.The water pumps are stopped  also.

Restarted the vacuum pumps 40 minutes after stopping. Everything is back to normal. The MP1 back up pressure need to be monitored frequently before we have a final solution on this issue.

Reset the CS cooling package on roof and restarted the water  pumps. The system is running good so far.

  1082   Friday, September 25, 2015, 07:56 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

weekly update see attachment

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1084   Monday, September 28, 2015, 10:10 David WangConditioning StationStandard OperationTM4Ta#46Switched off CS vacuum pumps and water system

I switched off CS vacuum pumps and water system after Isac opps finished the TM4 conditioning at CS.

  1086   Tuesday, September 29, 2015, 12:31 David WangITEStandard OperationTM4Ta#46TM4 has been connected in ITE

Dan and I connected TM4 in ITE. The turbo- pumps are started. Water supply to TM4 only at this stage. Everything is good so far.

  1091   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.

The ITE is configured to take proton beam.

  1092   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.

The ITE is configured to take proton beam.

  1093   Tuesday, October 06, 2015, 13:00 David WangITERepairTM4  spark on top of TM4 in ITE

During the weekend condition The TM4 spark at 30KV without vacuum response. It is confirmed the spark is from the top TM4 this morning.The flexible cables in a  black wire sleeve which is used for febiad X pin connection drooped too close to the TM4 surface plate, and caused the sparking. The problem is fixed by Anders and David. The cables is put back where it should stay.  After test, no sparking on the top.

  1094   Tuesday, October 06, 2015, 13:25 David WangITEStandard OperationTM4 Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Weekly update target hall schedule. See attachment 1,2.

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
  1096   Thursday, October 08, 2015, 14:08 David WangSouth Hot-CellStandard OperationTM3Dummy target febiad.TM3 has been moved from SHC to NW silo

Bill and I moved TM3 from SHC to NW silo with a dummy febiad target installed on it. The move is smooth.

  1097   Tuesday, October 13, 2015, 10:53 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Weekly update schedule. TM3 evaluation schedule in Nov is added.  

update the schedule after  the cancellation of TM2 from SHC to CS trip.see attachments 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1098   Wednesday, October 14, 2015, 12:42 David WangITWStandard OperationTM2ZrC#7TM2 has been disconnected in ITW

Dan and I disconnected TM2 in ITW this morning.

  1099   Wednesday, October 14, 2015, 12:44 David WangITWStandard OperationTM2ZrC#7TM2 has been moved from ITW to SHC

Bill and I remotely removed TM2 from ITW to SHC. The move is smooth.

  1100   Wednesday, October 14, 2015, 12:48 David WangSouth Hot-CellStandard OperationTM2ZrC#7TM2 ZrC#7 after run electrical check at SHC.

I did an electrical check on TM2 with ZrC #7 on it. The EE is short to 60KV bias. See attachment

Attachment 1: ZrC_#7_after_run_electrical_check.pdf
ZrC_#7_after_run_electrical_check.pdf