  1170   Friday, March 18, 2016, 09:34 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Sep)

I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for  beam schedule 130 is under construction, and will be posted later.

Attachment 1: Target_Hall_shedule_130_Apr_to_Sep_2016.xlsx
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
  1169   Friday, March 18, 2016, 08:34 Travis CaveConditioning StationStandard OperationTM2no targetmodule moved

TM#2 with no target has been moved to the conditioning station from the south hot cell.

  1168   Thursday, March 17, 2016, 14:57 David WangSouth Hot-CellRepairTM2 TM2 first round leak check in SHC

Chad and I finished the first round check on Tm2 water lines. The lines and spots checked are: Target oven + and - (front side braze joints) , Tube heater+and -(front side braze joints and water blocks), coil2 and coil 1(front side braze joints and area close to water blocks),. No leak has been found on all above of them.  The last, we checked   the GE which has the biggest leak so far. The leak detector base leak rate only can get to 4XE-9 atm.cc/sec. Chad sprayed helium very close to GE water block, and I got a quick response on leak detector. The leak rate climbed from 4Xe-9 atm.cc/sec to 1.4 atm.cc/sec. We confirmed the GE is leaking now. The exact location need to be pinpointed later once the containment box is out after the module is back to SHC. The module will be moved to TCS tomorrow morning and pressurized again there. Anders will use RGA to monitor the helium response during the check.  

  1167   Wednesday, March 16, 2016, 14:23 chad fisherSouth Hot-CellStandard OperationTM2SiC#32SiC#32 removal Target Module Inspection

SiC#32 has been removed from TM2. Quick inspection shows some troubling discoloration on the water cooled connection blocks of C and D as well as the left target heater A.

As for the target, both legs are broken and is has the normal "charge up" marks on the 9 pin connector.

Attachment 1: 20160316_141127.jpg
20160316_141127.jpg
Attachment 2: 20160316_141146.jpg
20160316_141146.jpg
  1166   Wednesday, March 16, 2016, 09:20 Travis CaveITEStandard OperationTM2SiC#32module moved

TM#2 with SiC#32 has been moved from the west station to the south hot cell.

  1165   Monday, March 14, 2016, 15:22 David WangConditioning StationStandard OperationTM2 2016 Winter Shut Down Target Hall Schedule

update schedule according to change. See attachment 1,2

 

Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
  1164   Monday, March 14, 2016, 11:24 David WangITE/ITW CoolingMaintenance  HALCW resin tank filter cartridges are changed today

Two of resin tank filter cartridges(supply and return) are changed today. Old cartridges and bagged and tagged. The contact field on them are 650usv/hr. The new cartridges are fiber-glass, Triumf store item. After replacement, the field on contact with the filter case are about 10 usv/hr. But the field on contact with top resin tank  has been increased from 45usv/hr  to 225 usv/hr

 The flow rate is relatively stable before and after change. See attachment

Attachment 1: 002.JPG
002.JPG
Attachment 2: 003.JPG
003.JPG
Attachment 3: 006.JPG
006.JPG
  1163   Friday, March 04, 2016, 13:58 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule

Update Schedule according to changes.See attachment1, 2.

 Re-post it after some minor correction See attachment 3,4.

Update schedule according changes. See attachments 5,6

 update schedule according to changes. See attachment 7,8

Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 3: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 4: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 5: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 6: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 7: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 8: 2016_winter_shut_down__target_hall_schedule.mpp
  1162   Friday, March 04, 2016, 12:34 David WangITEStandard OperationTM4 TM4 ITE annual leak check

Dan and I finished TM4 and ITE annual leak check on primary and secondary vacuum vessel. We found one leak on a KF25  blank off which is located on the top of the service cap. It is a low E-7 atm.cc/sec range leak. But, it is very close to turbo-pumps so ITE IG1 and other gauges are not affected by it very much. It is an easy fix. TheKF -25 center ring on the blank off  will be replaced  after vent . It be will leak checked again at CS after replacement.  That is only leak we found on TM4 and ITE primary and secondary vessel air to vaccum leak check.

Dan and I also finished the helium pressure test on all TM4 using water circuits. 70 psi helium. base LR 0.0xE-9 atm.cc/sec. All of them are leak free. No any response has been found on leak detector during test.

  1161   Wednesday, March 02, 2016, 10:04 David WangITWStandard OperationTM2 Leak check on ITW and TM2.

Dan and I leak checked TM2 and ITW primary vacuum vessel. It was found a 1X E-7 atm.cc/sec leak on top T flange seal between TM2 and dump module in first time check. But it is not a repeatable leak. I checked the same spot and around area two more times with increased helium volume.It did not show up again. The first response could  be a helium drift to dry scroll pump. I will check it again later. The primar vacuum vessel on ITW and TM2 are leak free. 

Dan and I found a small  leak on ITW dump module  top flange seal. The leak detector got a response  to 7xE-9 atm.cc/sec when I spray the helium to west side of dump module top flange. We tested again, and got same result. The o-ring which seals ITW dump module top flange is deteriorating. It need to be replaced at a proper time. This is the only air to vacuum leak we confirm so far on primary and secondary vacuum vessel on TM2 and ITW. The module and station no other air to vacuum leak.

The TM2 water lines helium pressure tested started in ITW. The helium pressure 70psi. The result so far is: Window: good, GE: huge leak directly shoot over E-7 atm.cc/sec( need to be confirmed tomorrow), HS: good, EE: good, MSP: tiny leak which is response to 3-4xE-9 atm.cc/sec. Coil 1 : small leak which is response to 1.3XE-8 atm.cc/sec. Tomorrow, We will test the rest water lines on TM2which are TA+, TA-, Tube+, Tube-, and coil 2. And We will confirm the GE huge leak at the last.

Finished the helium pressure test on TM2 water line.70 psi helium, The result of the rests 5 circuits: coil 1: leak 7.2xE-8atm.cc/sec,Ta(+): small leak 1.7XE-8 atm.cc/sec, Ta(-) small leak 8.7xE-9atm.cc/sec,Tube(-) 1.5 x E-8 atm.cc/sec. Tube(+)small leak 3.7xE-8 atm.cc/sec.    We repeated the helium pressure test on GE. There is a huge leak on TM2 GE circuit. The leak detector shoot up to E-7  atm.cc/sec right after the helium was applied.It went up to E-6 range in less than 1 minutes.

 

 

  1160   Wednesday, March 02, 2016, 09:51 David WangITWStandard OperationTM2 all water lines on TM2 and TM4 are purged.

All water lines on TM2 and TM4 are purged for upcoming water lines helium pressure test.

  1159   Thursday, February 25, 2016, 09:29 David WangITEStandard OperationTM4 TM4 has been disconnected in ITE.

TM4 has been disconnect in ITE(except  vacuum lines). The ITE vacuum system is still operating.

  1158   Thursday, February 25, 2016, 09:27 David WangITWStandard OperationTM2 TM2 has been disconnected in ITW

TM2 has been disconnected in ITW (except vacuum lines). The vacuum system is still operating.

  1157   Thursday, February 25, 2016, 06:52 David WangConditioning StationStandard Operation  stop CS vacuum pumps.

I stopped the conditioning station vacuum pumps. The CS is still under vacuum without venting.

  1156   Thursday, February 25, 2016, 06:48 David WangITEStandard Operation  4 Shielding blocks have been transferred from ITE to block storage area.

Dan and I transferred 4 shielding blocks from ITE to block storage area. The ITE pit is opened now.

  1155   Friday, February 19, 2016, 06:58 maicodallavalleSpent Target VaultMaintenance  F-308's serviced/loaded/ bolts torqued

Five F-308's were loaded with spent ISAC targets. All five F-308's were serviced two weeks ago. All bolts were torqued and security  cables were installed  for shipment.

  1154   Friday, February 12, 2016, 13:00 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule

2016 Winter shut down target hall schedule. See attachments1,2.

 update the schedule weekly. Everything is on time so far. see attachment 3,4.

Update the schedule according to beam new beam schedule and target process. see attachment 5,6

Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 3: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 4: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 5: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 6: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
  1153   Friday, January 22, 2016, 14:24 David WangSouth Hot-CellStandard Operation  2016 Winter Shut Down Target Hall Schedule (sketch)

Post a sketch of 2016 winter shut down target hall schedule. see attachment 1,2

 UPDATE THE SCHEDULE ACCORDING TO CYCLOTRON SIDE JOB. SEE ATTACHMENTS 3,4

Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 3: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 4: 2016_winter_shut_down__target_hall_schedule.mpp
  1152   Wednesday, January 13, 2016, 09:57 Travis CaveSpent Target VaultStandard Operation Ta#35, Ta#39, SiC#27, UC#12, ThO#1Spent targets moved to mini storage.

Five spent targets have been moved from the Spent Target Vault to Mini Storage in preparation for transfer to F-308s in February. The following targets were moved Ta#35, Ta#39, SiC#27, UC#12, ThO#1

  1151   Friday, January 08, 2016, 09:29 chad fisherSouth Hot-CellRepair  Window Decon

Entered the hot cell to perform final decon on the window. Initial swipes this morning were 11000 c.p.m. on 44-2. After decon approximately 100 counts.