1834
|
Friday, November 30, 2018, 10:28 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#57 | Spent Target Move | The spent Ta#57 target has been moved
from the south hot cell to the spent target
storage it was placed in pail 174 and placed |
|
|
1855
|
Friday, January 11, 2019, 11:26 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#25 | Spent Target Move | The spent target in the south hot
cell has been moved to the spent target vault.
It was placed in pail 204 and placed in spot |
|
|
1880
|
Friday, March 01, 2019, 10:23 |
Travis Cave | Spent Target Vault | Standard Operation | | | Source tray moved | The old TM#2 source tray and TM#4
optics tray have been removed from the vault
and placed into the spent target storage |
|
|
1905
|
Friday, April 05, 2019, 13:44 |
chad fisher | Spent Target Vault | Development | | | 2019 Pail drop tests |
Drop test performed January
8, 2019 with 25 lb target, UN pail and lug
cover. Drop failed. Lug cover half removed. |
|
|
1910
|
Monday, April 29, 2019, 09:32 |
Travis Cave | Spent Target Vault | Standard Operation | | SiC#31,32 and UC#19,20,21 | Spent targets moved to mini vault. | The following targets have been moved
from the spent target vault to the mini vault:
#127 - SiC#31 (front) |
|
|
1916
|
Thursday, May 02, 2019, 09:37 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#26 | Spent Target Move | The spent UC#26 target was moved
from the south hot cell to the spent target
vault. It was place in pail #209 and put |
|
|
1937
|
Monday, June 10, 2019, 14:13 |
Travis Cave | Spent Target Vault | Standard Operation | | | Old TM#4 source tray moved | The old TM#4 source tray in the south
hot cell was moved to the spent target vault.
The tray had a low of 7.5mSv/hr to a high |
|
|
1987
|
Wednesday, September 18, 2019, 14:28 |
Travis Cave | Spent Target Vault | Standard Operation | | | Repacking of the targets. | Three of the five targets in the
mini storage have been repackaged into the
stronger pail. |
|
|
1988
|
Thursday, September 19, 2019, 10:11 |
Travis Cave | Spent Target Vault | Standard Operation | | | Repacking of the targets. | Another target in the mini storage
has been repackaged into the new pails. With
one remaining to do which will be done on |
|
|
1989
|
Monday, September 23, 2019, 13:21 |
Travis Cave | Spent Target Vault | Standard Operation | | | Repacking of the targets. | All targets in the mini vault have
been repackaged and are now ready to be loaded
into F-308s. All the target pails have new |
|
|
1998
|
Thursday, October 03, 2019, 10:25 |
Travis Cave | Spent Target Vault | Standard Operation | | ZrC#8 | Spent Target Move | The spent ZrC#8 was moved from the
south hot cell to the spent target vault.
It was placed in pail 217 and the pail was |
|
|
2005
|
Wednesday, October 09, 2019, 13:28 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#27 | Spent Target Move | The spent target in the south hot
cell has been moved to the spent target vault.
It was placed in spot 1B of the vault in |
|
|
2008
|
Thursday, October 17, 2019, 11:49 |
Travis Cave | Spent Target Vault | Standard Operation | | SiC#31,32 and UC#19,20,21 | Loading F-308 | The targets in the mini storage have
been loaded into the F-308. |
|
|
2015
|
Monday, October 28, 2019, 11:50 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#28 | Spent Target Move | UC#28 has been moved from the south
hot cell to spent target storage. The target
was placed in pail number 219 and placed |
|
|
2028
|
Tuesday, November 12, 2019, 10:07 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#59 | Spent Target Move | The spent Ta#59 was moved from the
south hot cell to the spent target vault.
See the attached for details. |
|
|
2029
|
Thursday, November 14, 2019, 13:52 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#22,23,24 | Targets repackaged | The targets UC#22,23,24 have been
repackaged into the newer stronger pails,
and have been placed back in the mini vault |
|
|
2036
|
Tuesday, December 03, 2019, 12:45 |
Adam Newsome | Spent Target Vault | Standard Operation | | SiC#38 | SiC#38 in Pail 205 moved to Storage Vault: 4B | SiC#38 in Pail 205 was moved to section 4B
of the storage vault. Dose rate when retrieving
from Hot Cell was 22.2 mSv/h. |
|
|
2047
|
Monday, January 13, 2020, 14:19 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#49 and Ta#52 | spent target repackaging and moved to mini vault. | Targeta Ta#49 and Ta#52 have been
repackaged anf moved to the mini vault. Ta#49
was taken out of pail number 146 and placed |
|
|
2063
|
Thursday, February 06, 2020, 13:31 |
Adam Newsome | Spent Target Vault | Standard Operation | | UC#29 | UC#29 moved to vault location 6A, in pail 225 | UC#29 in pail 225 was moved to the
storage vault, location 6A. Field measured
at 22.4 mSv/hr at ~1m. |
|
|
2069
|
Thursday, February 20, 2020, 09:27 |
David Wang | Spent Target Vault | Standard Operation | | | Inventory of mini storage and vault. | Repacked nSiC#1 in SHC and moved it to
mini storage vault. Transferred UCx26 and
UCx28# from vault to mini-storage. See attachment |
|