Entry  Friday, August 16, 2019, 14:23, Carla Babcock, ITE, Repair, TM2, ZrC#8, TM2 electrical checks in ITE 

Ramped voltage on TM2 up to 30kV with no problems. Bias current is at 29uA, same as original TM2 bias current (see archiver for ITE June 15th, before protons) and similar to 31uA right after protons went off on Aug. 6.

TGHT=0A

TBHT=0A

BIAS V=30kV

BIAS current = 29uA

EZL V= 15kV

EZL current= 51uA

EE V= 1kV

EE current= 0.952mA

IG1= 8.6e-7

protons=0

This seems ok despite poor electrical checks showing 300 MOhm resistance between HV and ground. These values indicate a resistance of 1 GOhm. Let's see what happens when protons are on.

For future (optimistic) reference when testing protons:

BIAS=35kV, 35uA

EZL-17.5kV, 60uA

BIAS=38kV, 37uA

EZL=18.5kV, 63uA

Entry  Tuesday, September 17, 2019, 07:37, Carla Babcock, ITE, Development, TM2, ZrC#8, end of run HV investigations HVtests_TM2_Sept172019.xlsx

Ramping up HV to ~30kV, encountered problems and had to drop back to 28kV. No response on IG1 or anything else during sparks. Lots of charging-type behaviour on the bias current. Protons at 55uA

Tuesday, September 17, 2019, 02:02 : 15 mins with only 1 spark at 30kV so increased the bias

Tuesday, September 17, 2019, 02:31 : 32kV. Current unstable

Tuesday, September 17, 2019, 02:41 : Current continues extremely unstable but not much sparking....

Tuesday, September 17, 2019, 02:53 : Proton beam trip initially settled the bias current down, but then current began climbing pretty steeply with protons still off

Tuesday, September 17, 2019, 03:28 : Protons dropped to 40uA from 55uA, Bias current is much more stable and no sparks for 25mins

Tuesday, September 17, 2019, 03:36 : Raising voltage easy to about 33.5kV then instability and sparking similar to around 31kV at 55uA p+

Tuesday, September 17, 2019, 04:45 : Lowered protons to 25uA and no sparks though the current is not stable

More things but forgot to write them down. Spreadsheet attached.

Entry  Monday, September 30, 2019, 11:36, Travis Cave, South Hot-Cell, Standard Operation, TM2, ZrC#8, Module move 

 TM#2 with ZrC#8 has been moved from the east station to the south hot cell.

Entry  Monday, September 30, 2019, 14:05, Travis Cave, South Hot-Cell, Standard Operation, TM2, ZrC#8, Electrical Check TM2_elec_chk_ZrC8_post_beam_SHC_09-30-2019.pdf

 Results of the electrical check on TM#2 with ZrC#8 post beam.

Entry  Tuesday, October 01, 2019, 09:23, Don Jackson, ITE, Maintenance, TM2, ZrC #8, 60KV Common Connections TM2_Wiring.jpg

1 Jumpers between 60KV common and FEBIAD lines were connected in an unusual way.  This should of had no impact on the ZrC run but would have to be corrected for any future FEBIAD runs.

2 Feedthrough U was mislabeled (label has been removed)

 

Entry  Tuesday, October 01, 2019, 10:22, chad fisher, South Hot-Cell, Standard Operation, TM2, ZrC#8, ZrC#8 Removed Ta#59 installed 20190930_140918[1].jpg

ZrC#8 has been removed from TM2. Upon removal of the high current tube heater bolts it was noticed that the tube was broken. Also the 9 pin connector has an arc mark (see pictures attached).

Ta#59 has been installed with new fasteners. High current fasteners torqued to 130 in lbs.

Entry  Tuesday, October 01, 2019, 14:38, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#59, Electrical Check TM2_no_target_SHC_elec_chk_Oct-1-2019.pdfTM2_Ta59_SHC_elec_chk_Oct-1-2019.pdf

 The results of the electrical check on TM#2 with the Ta#59 target and without before the target was mounted on the module.

Entry  Tuesday, October 01, 2019, 16:30, Anders Mjos, Conditioning Station, Standard Operation, TM2, Ta#58, Conditioning of Ta#58 

Tuesday, October 01, 2019, 15:15: Started roughing.

Tuesday, October 01, 2019, 16:30: Started TPs

Tuesday, October 01, 2019, 16:34: All TPs at speed


Conditioning completed over the weekend by RIB operations. The shutter was left closed on the module, so no beam could be seen on the FC. Conditioning otherwise OK.

Entry  Friday, October 04, 2019, 16:43, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been connected at TCS. 

TM2 has been connected at TCS this morning. helium pressure test on Tm2 HS line is done. No leak.

Entry  Monday, October 07, 2019, 09:56, Adam Newsome, ITE, Standard Operation, TM2, Ta 59, TM2 Move 

TM2 has been moved from the Conditioning Station to ITE with Ta#59 target.

Entry  Monday, October 07, 2019, 14:03, David Wang, ITE, Standard Operation, TM2, Ta 59, TM2 has been connected in ITE. Ta_59_TM2_ITE__connection_checklist..pdf

Tm2 with Ta 59 has eben connected in ITE. Turbo pumps are started. See checklist

Entry  Thursday, October 31, 2019, 10:17, David Wang, Assembly/Bench Test, Maintenance, TM2, , Febiad target gas line leak check. 

Feibiad gas line for ITE and its adapter fittings for TM2 are tested today by installing them on a dummy water stem. No leak on VCO fitting, adapter o-rings, and all Swagelock fittings of this assembly. Manual valve on gas line works fine.  The positional check on gas line between TM2 and ITW will be fulfilled next Tuesday during module disconnection. 

Entry  Tuesday, November 05, 2019, 10:19, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#59, Module move 

 TM#2 with Ta#59 has been moved from the ITE to the south hot cell.

Entry  Tuesday, November 05, 2019, 11:57, David Wang, ITE, Standard Operation, TM2, Ta 59, Ta#59 disconnection checklist Ta#59_disconnection_checklist.pdf

See attachment

Entry  Tuesday, November 05, 2019, 12:46, chad fisher, South Hot-Cell, Standard Operation, TM2, ta#59, Ta#59 removed 

Ta#59 has been removed from TM2 and it is now ready for electrical check.

Entry  Tuesday, November 05, 2019, 14:27, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#59, Electrical Check Elec_Chk_TM2_with_Ta59_post_beam_SHC_Nov_05_2019.pdfElec_Chk_TM2_SHC_no_target_Nov_5_2019.pdf

 Results of the electrical check of TM#2 with the old Ta#59 target and target free.

Entry  Thursday, November 07, 2019, 08:56, David Wang, Conditioning Station, Standard Operation, TM2, SiC#38, TM2 in TCS. 

Helium pressure leak check on TM2 HS line at TCS is done. No leak. Also, Helium are sprayed to gas line adapter and fittings. No leak. TM2 is connected at TCS. Anode plug on TCS is connected to module 52pin connector. Water system is started. Vacuum pumping down is good. HV cover will be installed today.

    Reply  Thursday, November 07, 2019, 10:39, Anders Mjos, Conditioning Station, Standard Operation, TM2, SiC#38, Conditioing SiC#38 SiC#38_ANODE_bias_2019-11-07.PNG

Thursday, November 07, 2019, 10:35: Tested source to 30 A on TGHT, TBHT and COIL. ANODE at 100 V.


Tuesday, November 12, 2019

The FEBIAD source worked well over the weekend. The anode current limit was adjusted twice to stop voltage limiting. About 5E-8 A on the FC with TGHT=580A, TBHT=300A, ANODE=200V,150 mA, COIL=50A. Bias was conditioned to 30 kV

Entry  Tuesday, November 12, 2019, 10:02, Adam Newsome, ITE, Standard Operation, TM2, SiC#38, TM2 Move 

TM2 was moved from the Conditioning Station to ITE, with SiC#38 target.

Entry  Tuesday, November 19, 2019, 13:41, David Wang, ITE, Standard Operation, TM2, SiC 38# febiad, TM2 SiC#38 connection check list. SiC_#_38_febiad_connection_checklist.pdf

TM2 was connected in ITE 12th Nov. attach checklist