  ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  333   Wednesday, May 08, 2013, 13:48 chad fisherSouth Hot-CellRepairTM3 IMG wiring checkChecks of the wiring for the IMG are complete
and have passed.
  
  334   Thursday, May 09, 2013, 10:13 chad fisherSouth Hot-CellDevelopment  Mock-up ProgressThe source tray for the mock-up has been
setup for waterline bending and soldering/brazing.
Thanks to Travis for finding the
 IMG_1056[1].JPGIMG_1057[1].JPGIMG_1058[1].JPG 
  335   Thursday, May 09, 2013, 14:23 chad fisherSouth Hot-CellRepairTM3 Water Block Jig RemovalThe source tray side of the water block
jig has been removed in preparation for moving
the module to the  conditioning station
 IMG_1059[1].JPG 
  336   Friday, May 10, 2013, 09:26 chad fisherSouth Hot-CellRepairTM3 Containment box reinstalledthe containment box has been reinstalled
onto TM3. After electrical checks it is ready
to move to the conditioning station...for
 IMG_1062[1].JPGIMG_1063[1].JPG 
  343   Wednesday, May 15, 2013, 10:00 David WangITEStandard OperationTM4 Disconnected TM4 in ITE.HS had been purged. The ITE is under venting.
The TM4 will be moved to SH on next Tuesday
which is May 21th.
  
  345   Wednesday, May 15, 2013, 10:20 Bevan MossConditioning StationRepair  Roof top chiller failedI have been getting a fault on the roof
top chiller for the 2 tandem 7.5  ton chillers.
I have checked and we have water flow and
  
  346   Wednesday, May 15, 2013, 10:25 Bevan MossConditioning StationRepair  ONICON flow meter Scott Adair from Riada sales came
to site to complete diagnostics on the ONICON
flow meter. He could not determine the problem
  
  347   Wednesday, May 15, 2013, 16:21 Bevan MossConditioning StationRepair  BIAS Current readings off by a factor of 5 A special thanks to Kazuya, Jane
and Ray who jumped on this issue right  away!
The limit of the BIAS PS was set as 20000uA
  
  349   Wednesday, May 15, 2013, 17:32 Bevan MossConditioning StationStandard OperationTM3 TM3 in place but not connected To confirm that the sparking was
coming from the module rather than the conditioning
station TM3 was grounded and the conditioning
 15052013_TM3_in_place_but_not_connected.xlsx 
  351   Friday, May 17, 2013, 10:04 chad fisherSouth Hot-CellRepair  Manipulator RepairManipulator has been sucessfully repaired.
Recieved 0.19 mSv. Took Approx. 10-20 minutes
  
  352   Friday, May 17, 2013, 12:02 Travis CaveConditioning StationStandard OperationTM3 module moveTM#3 with no target or source trays has
been moved from the conditioning station
to the NE silo.
  
  359   Thursday, May 23, 2013, 14:07 Bevan MossConditioning StationRepair  Chiller Unit Repaired ESC came today and "repaired"
the chiller. There was something wrong with
the VFD controller. The were able to get
  
  361   Thursday, May 23, 2013, 14:12 Bevan MossConditioning StationMaintenance  Primary Circuit Drained and Flushed Rob Walker has drained the primary
side of the conditioning station. It will
be flushed, filled  and chemically treated.
  
  363   Monday, May 27, 2013, 10:37 Bevan MossConditioning StationMaintenanceTM4 Cooling Systems topped offRob walker has flushed and refilled the
primary side of the system (note the water
still looks nasty). This morning the primary
  
  364   Monday, May 27, 2013, 11:55 chad fisherSouth Hot-CellStandard Operation  Special Tooling for RFQ targetThe special tool made for the RFQ target
autopsy has been inserted into the hot cell.
 
  
  365   Monday, May 27, 2013, 15:59 Bevan MossConditioning StationRepair  Compressor fault Once again the 7.5 compressors are
tripping due to faults. I believe it is due
to over pressure as a result of the chiller
  
  366   Monday, May 27, 2013, 16:01 Bevan MossConditioning StationRepair  CanBUS card During HV conditioning of TM4 with
Ta#40 there was a spark at ~43 kV that caused
the Bias card to "fry". Dave Morris
  
  374   Tuesday, June 04, 2013, 12:36 David WangITEStandard OperationTM4 5 shielding blocks are transferred from ITW to ITEDan an I  transferred 5 shielding
blocks from ITW to ITE. The ITE is configured
to take proton beam.
  
  375   Tuesday, June 04, 2013, 15:34 Bevan MossConditioning StationRepair  Relay replacedESC was called out again to inspect the
chiller as it was showing the same problem
as before. This time when started one fan
  
  376   Tuesday, June 11, 2013, 10:05 David WangITWStandard OperationTM1 Disconnected TM1 in ITW.Dan and I  disconnected TM1 in ITW.   