  RH-ISAC, Page 74 of 141  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subjectdown Text Attachments
  1921   Wednesday, May 15, 2019, 16:06 Isaac EarleSafe Module ParkingDevelopment  SMP module support flange installed and leak checkedThe SMP module support flange sub-assembly
(IRH1755) was installed today according to
drawing IRH1683.  Dow Corning 111 sealing
 20190515_094730.jpg20190515_094740.jpg20190515_103253.jpg20190515_103824.jpg 
  2745   Thursday, January 09, 2025, 11:46 David WangSafe Module ParkingStandard OperationTM4No targetSMP is under vacuum for TM4 storage during shut down.  SMP:MP1 is started with SMP BV1 is
opened. SMP is under vacuum for TM4 storage
during shut down.
  
  2007   Tuesday, October 15, 2019, 16:42 Isaac EarleSafe Module ParkingDevelopment  SMP flange alignment tested using shield plug As a preliminary test in preparation
for SMP commissioning, one of the steel module
shield plugs was installed into the SMP to
 smp1.jpgsmp2.jpgsmp3.jpgsmp4.jpg 
  2639   Friday, July 12, 2024, 08:51 Riley SykesSafe Module ParkingMaintenance  SMP chain guard SS washers were added to all slotted
holes on SMP chainguard cover plate
  
  1970   Friday, August 23, 2019, 14:27 Isaac EarleSafe Module ParkingDevelopment  SMP camera video cabling installed and tested Installation of the video lines for
the SMP cameras was completed yesterday according
to IRH1670 Rev B.  All four cameras
  
  2037   Thursday, December 12, 2019, 14:39 Isaac EarleSafe Module ParkingDevelopment  SMP assembly shifted 1.0" northThe SMP assembly was shifted approximately
1.0" north today by pushing it, braced
against the south wall, using a 100 Ton capacity
  
  2109   Tuesday, June 23, 2020, 10:56 David WangSafe Module ParkingStandard Operation  SMP annual service. Dan and I did the SMP annual  maintenance
service today. Lid open/close , vessel rotation
and limit switch check, lubricate chains,
  
  2017   Tuesday, October 29, 2019, 10:00 Adam NewsomeSafe Module ParkingDevelopment  SMP Updates to E-stop circuit and feedback signalsThe SMP main control panel and remote control
module were updated in  order to implement
the following items which were deemed desirable
  
  1971   Tuesday, August 27, 2019, 13:12 Adam NewsomeSafe Module ParkingDevelopment  SMP Remote Control Wiring InspectionThe wiring for the SMP remote control module
was inspected by Joel Semilla (TRIUMF  electrician).
 The module was plugged in to verify there
  
  2006   Thursday, October 10, 2019, 16:17 Adam NewsomeSafe Module ParkingDevelopment  SMP Main Panel: Relay Addition for E-Stop CircutAn update was made for the E-stop and power
supply system in the SMP main panel. Upon
testing remote control, it was determined
 Changes_to_IRH1869.JPGIMG_20191009_153336_-_new_relay_for_E-stop.jpg 
  1925   Friday, May 17, 2019, 16:46 Adam NewsomeSafe Module ParkingDevelopment  SMP Controls Installation Update 
The following controls-related
 IMG_20190417_100838.jpgIMG_20190417_100843.jpgIMG_20190517_162230.jpgIMG_20190517_162305.jpg 
  2068   Friday, February 14, 2020, 14:13 David WangSouth Hot-CellStandard OperationTM4 SIS dummy target for IGLIS TM4 electrical checkElectrical check and HS, window leak check
result at SHC. See attachment.
 Dumm_SIS_target_for_IGLIS_test_on_TM4.pdf 
  1358   Thursday, September 22, 2016, 13:04 David WangSouth Hot-CellStandard OperationTM4 SHC, TM4 leak check on HS line.Chad and I leak checked the TM4 HS line
after new target installation. base leak
rate:0.0Xe-9 atm.cc/sec.  No response
  
  1387   Tuesday, November 01, 2016, 14:58 David WangSouth Hot-CellStandard OperationTM4 SHC, TM4 leak check on HS line.Chad and I did a leak check on TM4 HS line
with new Ta target installed. Base leak rate
0.0xE-9 atm.cc/sec. base pressure 0.0XE-4.  
  
  1226   Tuesday, May 10, 2016, 13:54 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on window line and HS line.Chad and I leak checked the TM2 HS and
window lines after new target installation. 
The window line was very easy pumped down
  
  1332   Wednesday, August 24, 2016, 10:44 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.Chad and I leak checked Tm2 Hs line with
new target installed. Base LR 0.0Xe-9 atm.cc/sec.  
No leak has been found. This line will be
  
  1381   Monday, October 24, 2016, 14:54 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.Chad and I did the leak check on TM2 heat
shield line. LD base leak rate:0.0xE-9atm.cc/sec.
Base pressure:0.0X E-9 torr. The line is
  
  1403   Wednesday, November 23, 2016, 16:10 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.Chad and I leak checked TM2 HS line with
new UCx target installed. Helium spray 
2 seconds on each joint and 10seconds flushing
  
  1488   Tuesday, April 11, 2017, 14:06 David WangConditioning StationStandard OperationTM4 SHC, TM2 leak check on HS line.Chad and I did leak check on TM1 HS line
at SHC. 0.0XE-9 atm.cc/sec.  No leak.
  
  1591   Wednesday, August 02, 2017, 15:13 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.HS line is leak checked at SHC this afternoon
by helium spay.  Leak detector base
LR 0.0 XE-9atm.cc/sec. Base pressure 0.0Xe-4
  