Entry  Wednesday, September 03, 2014, 10:50, David Wang, ITW, Standard Operation, TM1, , TM1 has been disconnected in ITW. 

  TM1 has been disconnected in ITW.

Entry  Wednesday, September 10, 2014, 07:12, David Wang, ITW, Repair, TM1, , Removed ITW HS and COIL flow rate monitors. 

Removed ITW HS and COIL flow rate monitors installed at the beginning of this year. They were installed on these two circuits for testing.They are broken during last run in ITW due to radioactive field.

Entry  Wednesday, September 10, 2014, 08:52, Travis Cave, ITW, Standard Operation, TM1, ZrC#6, module move 

TM#1 with ZrC#6 has been moved from the conditioning station to west target station.

Entry  Wednesday, September 10, 2014, 11:47, David Wang, ITW, Standard Operation, TM1, , TM1 has been connected in ITW. 

TM1 has been connected in ITW.  ITW and TM1 turbo pumps have been started. Water is supplied to TM1 only. Everything is good so far.

Entry  Tuesday, September 16, 2014, 10:41, David Wang, ITW, Standard Operation, TM1, ZrC #4, 5 Shielding blocks have been transferred from ITE to ITW. 

5 Shielding blocks have been transferred from ITE to ITW. The ITW is configured to take proton beam

Entry  Tuesday, October 14, 2014, 12:19, David Wang, ITW, Standard Operation, TM1, , TM1 was disconnected in ITW. 

TM1 was disconnected in ITW this morning. Heat shield circuit is purged.

Entry  Thursday, November 06, 2014, 08:07, David Wang, ITW, Standard Operation, TM1, ThO#1, TM1 has been connected in ITW. 

TM1 has been connected in ITW. All turbo pumps are started. The pumping down on ITW is good so far. The water is supplied to TM1 for HV conditioning.

Entry  Thursday, November 06, 2014, 08:55, David Wang, ITW, Repair, TM1, ThO#1, primary vacuum back up pressureITH CG1 ,CG2,CG4A were high. 

I found primary vacuum back up pressure ITH CG1, CG2, and CG4A were unusually high this morning. They should be about 10 -20 mtorr after one night pumping, but all of thier reading were 340-350-mtorr. Thease cause the current draw on primary turbo pumps were all over 2.0A(should be about 1.0A). I let Paul closed all BVs on primary side . The pressure dropped quickly to normal range after all BVs were closed. This shows the back up line are good. The problem are from   one of  the connections  on primary BVs. I let Paul opened the BVs one by one,but the problem did not show again. Now ,the current draw on the turbo pumps are back to normal also.

I will keep monitoring the system and take a look on all KF25 clamps on BVs once I have a chance to access to ITW.

Entry  Thursday, November 13, 2014, 13:52, David Wang, ITW, Standard Operation, TM1, ThO#1, 5 Shielding blocks have been transferred from ITE to ITW. 

Dan and I transferred 5 shielding blocks from ITE to ITW. The ITW is configured to take proton beam.

Entry  Thursday, November 13, 2014, 14:01, David Wang, ITW, Repair, TM1, , I replaced flow wheel and coil on ITW MSP water flow sensor. 

I replaced flow wheel and coil on ITW MSP water flow sensor which is located in ITW pit. Before replacement, I checked the signal strength and frequency form e-board on this circuit. The signal was good in 10minutes watching. Still, I replaced them. The flow sensor works fine after replacement. I made a comment  on Isac e-fault system about this issue.

Entry  Tuesday, February 17, 2015, 13:07, Anders Mjos, ITW, Development, , , Resistance measured of TGHT and TBHT lines to ITW 

 See e-log entry for ITE for details. The copper bars have not been removed. They can be used for testing the new power supplies.

Local measurement was done by Ray with a voltmeter. The voltmeter was consistent with EPICS readback and local readback on the power supplies. A voltage drop of 0.137 V @ 580 A was measured across the bus bar from the TGHT power supply to the cooled transmission lines.

Entry  Wednesday, February 25, 2015, 10:44, David Wang, ITW, Maintenance, , , 2015 shut dwon ITW water sensor coils and pedal wheels replacement 2015_shut_down_ITW_water_sensors__replacements.pdf

Dan and I replaced pedal wheels and coils on ITW water flow sensors. It is a shut down job we did every two years. See attachment for detail.

Entry  Thursday, February 26, 2015, 09:22, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Mar 25th Target_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdf

TH shut down activities schedule from Feb 23th-March 25th. The schedule will be updated each week. See attachment 1.

Feb-27-2015: Updated the schedule, and uploaded as PDF file. See attachment 2.

Entry  Thursday, March 05, 2015, 07:17, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update 6x

TH shut down jobs are processing as scheduled this week. Discussed with Don, and we think the jobs scheduled in next week should be processed as we planned. See attachments for updated schedule.

I updated the schedule today. See attachment 3, 4 for updating.  2015-Mar-10.

2013-Mar -13, I updated the schedule to show the jobs we finished this week. See attachment 5,6

Entry  Tuesday, April 21, 2015, 13:01, Grant Minor, ITW, Development, TM2, , TM2 MK4 Optics Tray - banana plug bore modification (on bench) ita6092_redlines_gminor_21apr2015.pdfTM2_Optics_Tray_Bore_Mod_21Apr2015_1.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_2.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_3.JPG

The MK4 optics tray prepared for TM2 (as per ITA6082) had an undersized bore for the banana plug, making insertion of the plug extremely difficult / impossible.

Reference stores parts were collected to check the fit:  male plug 3-4/01152 and female jack 1-6/1201.  The size of the female jack was checked with a #21 drill at .159".

The bore on the optics tray was drilled out dry using the #21 drill to the same depth as the original blind hole, by Maico and Dan McDonald.  Chips were carefully collected in a rag, and the hole was blown out with compressed air.

The fit was checked to be snug but possible, using the male plug and the Remote Handling ultem base (ref ITA6023).

Redlines and photos are attached.

 

Entry  Tuesday, April 28, 2015, 10:26, David Wang, ITW, Standard Operation, TM1, UCx12, ITW target pit o-ring seal replacement. 

Dan and I replaced ITW target pit o-ring seal(.275DIA X42"ID). It is an annual job before first beam to ITW. The old o-ring was moved and the groove was vacuum cleaned. The new o-ring has been installed properly.

Entry  Tuesday, April 28, 2015, 11:09, Anders Mjos, ITW, Maintenance, , , Resistance measured of TGHT and TBHT lines to ITW Resistance_from_Electrical_Room_to_Target_Station.xlsx

The new TBHT and TGHT power supplies were brough up to high current; 350 A and 420 A respectively. The TGHT power supply was limited by PLC to 420 A. The resistance calculated for both the TBHT and TGHT copper lines from the electrical services room to the ITW pit was 1.35 mOhm. See attached spreadsheet for details.

Dave Morris has been contacted to correct the current limit for the TGHT supply to 600 A.

Entry  Tuesday, April 28, 2015, 11:14, Travis Cave, ITW, Standard Operation, TM1, UC#12, Module move 

TM#1 with UC#12 has been moved from the conditioning station to the west target station.

Entry  Tuesday, April 28, 2015, 17:17, David Wang, ITW, Standard Operation, TM1, UCx12, TM1 has been connected in ITW. 

TM1 has been connected in ITW. Five turbo pumps have  been started. The TM1 containment box window line is capped on the service cap and the line is pump town to E-4 torr range.

Entry  Friday, May 22, 2015, 15:44, David Wang, ITW, Standard Operation, TM1, UCx12, 5 Shielding blocks have been transferred from ITE to ITW. 

5 shielding blocks have been transferred from ITE to ITW. I  checked all ITW water signals, and they are good.  ITW is configured to take proton beam.