Entry  Thursday, March 05, 2015, 07:17, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update 6x
TH shut down jobs are processing as scheduled this week. Discussed with Don, and we think the jobs scheduled in next week should be processed as we planned.
See attachments for updated schedule.
I updated the schedule today. See attachment 3, 4 for updating.  2015-Mar-10.
Entry  Tuesday, April 21, 2015, 13:01, Grant Minor, ITW, Development, TM2, , TM2 MK4 Optics Tray - banana plug bore modification (on bench) ita6092_redlines_gminor_21apr2015.pdfTM2_Optics_Tray_Bore_Mod_21Apr2015_1.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_2.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_3.JPG
The MK4 optics tray prepared for TM2 (as per ITA6082) had an undersized bore for the banana plug, making insertion of the plug extremely difficult /
impossible.
Reference stores parts were collected to check the fit:  male plug 3-4/01152 and female jack 1-6/1201.  The size of the female jack was
Entry  Tuesday, April 28, 2015, 10:26, David Wang, ITW, Standard Operation, TM1, UCx12, ITW target pit o-ring seal replacement. 
Dan and I replaced ITW target pit o-ring seal(.275DIA X42"ID). It is an annual job before first beam to ITW. The old o-ring was moved and the groove
was vacuum cleaned. The new o-ring has been installed properly.
Entry  Tuesday, April 28, 2015, 11:09, Anders Mjos, ITW, Maintenance, , , Resistance measured of TGHT and TBHT lines to ITW Resistance_from_Electrical_Room_to_Target_Station.xlsx
The new TBHT and TGHT power supplies were brough up to high current; 350 A and 420 A respectively. The TGHT power supply was limited by PLC to 420 A.
The resistance calculated for both the TBHT and TGHT copper lines from the electrical services room to the ITW pit was 1.35 mOhm. See attached spreadsheet
for details.
Entry  Tuesday, April 28, 2015, 11:14, Travis Cave, ITW, Standard Operation, TM1, UC#12, Module move 
TM#1 with UC#12 has been moved from the conditioning station to the west target station.
Entry  Tuesday, April 28, 2015, 17:17, David Wang, ITW, Standard Operation, TM1, UCx12, TM1 has been connected in ITW. 
TM1 has been connected in ITW. Five turbo pumps have  been started. The TM1 containment box window line is capped on the service cap and the line
is pump town to E-4 torr range.
Entry  Friday, May 22, 2015, 15:44, David Wang, ITW, Standard Operation, TM1, UCx12, 5 Shielding blocks have been transferred from ITE to ITW. 
5 shielding blocks have been transferred from ITE to ITW. I  checked all ITW water signals, and they are good.  ITW is configured to take proton
beam.
Entry  Friday, June 19, 2015, 11:43, David Wang, ITW, Repair, TM1, , ITW external water leak on dump circuit 6x
There was an external water leak in ITW during the last beam running time. The leak started after the shielding blocks transfer(May 22). It cause a constantly
water level drop on S-tank(0.5 "/day average). Today , after the blocks are moved , the leak source has been found. Water seeped through a fitting
on ITW dump circuit pressure gauge. The leak water slowly flow around the TM1 on the tank flange. most of them are dried out, but left some stain on dump
Entry  Tuesday, June 30, 2015, 11:27, Travis Cave, ITW, Standard Operation, TM1, UC#12, Module moved 
TM#1 with UC#12 has been moved from the west station to the south hot cell.
Entry  Tuesday, June 30, 2015, 15:41, David Wang, ITW, Standard Operation, TM1, , TM1 was disconnected in ITW this morning. 
TM1 was disconnected in ITW  this morning. The ITW was vented with argon last night.
Entry  Tuesday, July 21, 2015, 12:38, David Wang, ITW, Repair, , , ITW external water leak on dump circuit has been fixed. 
The leaking 1/8 NPT(M)-1/4NPT(F) adapter on the ITW dump circuit is replaced.
Entry  Tuesday, September 01, 2015, 10:32, Travis Cave, ITW, Standard Operation, TM2, ZrC #7, Module moved 
TM#2 with ZrC#7 has been moved from the conditioning station  to the west target station.
Entry  Tuesday, September 01, 2015, 10:38, David Wang, ITW, Maintenance, TM2, , ITW top tank flange clean up and r-ring replacement. ITW_o-ring_replacement_2015-09-01_008.JPGITW_o-ring_replacement_2015-09-01_007.JPGITW_o-ring_replacement_2015-09-01_006.JPG
During last run, ITW dump circuit had a water leak on an adaptor below the pressure gauge. The top tank flange, slot, and O-ring were water contaminated
by the leak. I removed the old o- ring, cleaned up the flange and o-ring slot, and put a new o-ring into the flange. Some  pictures will be attached
in this mail later.
Entry  Tuesday, September 01, 2015, 14:54, David Wang, ITW, Standard Operation, TM2, , TM2 has been connectec in ITW. 
TM2 has been connected in ITW. During the connection, Anders and I  found the TM2  high current cables used in ITE and CS are short in ITW. 
Anders and Grant found the original TM2 ITE high current cables in target hall. We replaced them. They works fine. But, a little bit longer on cable length
would be easy to connect them. All other connections and HV cover in ITW work for the TM2 so far.
Entry  Tuesday, September 01, 2015, 16:03, Grant Minor, ITW, Standard Operation, TM2, ZrC #7, Photos of TM2 Connection Procedure on Docushare 1Sept2015 
https://documents.triumf.ca/docushare/dsweb/View/Collection-15323
Entry  Tuesday, September 08, 2015, 10:11, David Wang, ITW, Standard Operation, TM2, ZrC, 5 Shielding blocks have been transferred from ITE to ITW. 
Maico and Dan moved 5 shielding blocks from ITE to ITW. The ITW is configured to take proton beam.
Entry  Wednesday, October 14, 2015, 12:42, David Wang, ITW, Standard Operation, TM2, ZrC#7, TM2 has been disconnected in ITW  
Dan and I disconnected TM2 in ITW this morning.
Entry  Wednesday, October 14, 2015, 12:44, David Wang, ITW, Standard Operation, TM2, ZrC#7, TM2 has been moved from ITW to SHC 
Bill and I remotely removed TM2 from ITW to SHC. The move is smooth.
Entry  Tuesday, October 20, 2015, 10:18, Travis Cave, ITW, Standard Operation, TM2, SiC#32, Module moved 
TM#2 with SiC#32 has been moved from the south hot cell to the west target station.
Entry  Tuesday, October 20, 2015, 12:49, Dan McDonald, ITW, Standard Operation, , SiC#32, Tm2 hook up In ITW 
Lower and disconnect TM2 from crane in ITW, proceed with hooking up TM2 as per checklist with Anders. Double check flow meters and coils, reset TP1 and