Entry  Thursday, June 29, 2017, 11:55, David Wang, Conditioning Station, Repair, , , TCS HV cable and feed through installation 
John Chow and I installed new TCS HV cable and feed through with their mounting panel back to TCS Faraday cage this Tuesday. ECO-4269 has been issued
for the new cable feed through and mounting panel.
Entry  Tuesday, November 08, 2016, 07:47, David Wang, Conditioning Station, Standard Operation, TM4, , TCS water and vacuum pumps are switched off 
TCS is vented. TM4 is disconnected and TCS.
Entry  Friday, May 19, 2017, 12:25, David Wang, Conditioning Station, Standard Operation, TM4, , TCS and TM4 water flow measurement.  
 
 

    
        
             
 
Entry  Monday, April 24, 2017, 16:11, David Wang, Conditioning Station, Standard Operation, TM2, , TCS TP1s is restarted. 
TCS IG1S  is switched on as well. The reason to start the pump is to prepare a possible extended TM2 conditioning at TCS caused by TH crane issue.
TCS:TP1 and TP2 are not switched on for this.
Entry  Tuesday, August 23, 2022, 10:51, Carla Babcock, ITE, Repair, TM4, SiC#44, TBHT to HV common short on SiC#44-TM4 
TM4 with SiC#44 installed developed a short TBHT to HV common during its first heating in ITE. Was fine before installation. Now with everything cold
TBHT to HVC is 25kOhms. Removed short in electrical room, will rely on short in the module.
Entry  Tuesday, September 01, 2015, 16:55, Anders Mjos, Conditioning Station, Maintenance, , , TBHT power supply remvoed 
 The power supply is needed as a spare for the failed TGHT p/s in ITW
Entry  Friday, February 08, 2013, 11:42, Grant Minor, ITE, Maintenance, , , TAPC 477 resolved - ISAC elec. room gas cylinder TAPC-477_resolved_8Feb2013.pdf
See attached TAPC 477 documentation.
Entry  Tuesday, April 23, 2013, 15:59, Bevan Moss, Conditioning Station, Standard Operation, TM3, N/A, Systems off 
 Both the Cooling Package and Vacuum have been turned off in preparation for the module move tomorrow
Entry  Monday, January 28, 2013, 12:26, Travis Cave, Conditioning Station, Development, , , Switches connected 
the switches and the solenoid are all wire up to 24VDC, when you open either of the little doors the solenoid switches this is also true if there is
a power loss. currently the solenoid is powered.
Entry  Monday, September 28, 2015, 10:10, David Wang, Conditioning Station, Standard Operation, TM4, Ta#46, Switched off CS vacuum pumps and water system 
I switched off CS vacuum pumps and water system after Isac opps finished the TM4 conditioning at CS.
Entry  Tuesday, January 07, 2020, 08:02, David Wang, Cooling, Standard Operation, , , Switch on HALCW MP2 
HALCW MP2 is switched on this morning after yesterday cooling tower maintenance. LALCW P5 and P6 pumps are started by isac operator  as well. The
system is good so far. 
Entry  Monday, April 24, 2017, 09:52, David Wang, Conditioning Station, Standard Operation, TM2, , Switch off TCS water system and vacuums 
The TCS bias was turn off before that. The TM2 and TCS are still under vacuum now.
Entry  Wednesday, September 13, 2017, 10:05, David Wang, Conditioning Station, Repair, TM3, , Switch off TCS water system and vacuums 
Preparing vent the TCS/TM3. We will remove TM3 service tray cover plate  after venting.
Entry  Tuesday, May 13, 2025, 13:12, Frank Song, MAA, Repair, , , Swap out the target hall alpha CAM. 
 
 
Entry  Tuesday, May 13, 2025, 13:13, Frank Song, MAA, Repair, , , Swap out the target hall alpha CAM. 
AlphaCAM has been replaced and tested by RPG in MAA target hall. (per Document-154779)
WorkPermit # I2025-05-13-3
Entry  Friday, October 21, 2016, 15:10, Anders Mjos, South Hot-Cell, Repair, TM2, Ta#49, Stuck TGHT clamp bolt removal 
During target removal on Wednesday October 12th, the left target heater conductor bolt (ITD0058) could not be removed. The bolt was found to be stuck
in the threads (keensert) of the TGHT conductor block (ITA0583). In the process of attempting to remove the bolt, the conductor insulator (ITD0054) cracked
(ref assy ITD0052). To allow increased torque to be applied and support the conductor block, a clamping jig (ITD0612) was designed and fabricated. The
Entry  Tuesday, September 04, 2018, 08:18, David Wang, Conditioning Station, Standard Operation, TM4, UCx 24#, Stppped TM4 and TCS vacuum and water system at TCS. 
I stopped TM4 and TCS vacuum system at TCS. TCS and TM4 is venting with argon now.
Entry  Friday, November 17, 2023, 11:28, Adam Newsome, Spent Target Vault, Maintenance, , , Storage vault: issue observed with door opening PXL_20231117_200245076.jpgPXL_20231124_210005281.jpg
During operation today, it was observed that the main vault door had issues opening.. typically when the door was around 80-90% opened, it would stop
motion. Note that this issue has allegedly been present since early 2023. It appeared that the motor was still spinning but the clutch was slipping. This
issue was consistent and observed multiple times when trays 2, 5, and 6 were engaged (note these are all on the same side of the vault). It was overcome
Entry  Wednesday, September 14, 2022, 13:45, Adam Newsome, Spent Target Vault, Development, , , Storage Vault: cable replaced and e-chain upgrade PXL_20220914_183329159.jpg
The motor cable for the storage vault was replaced as the old one was showing signs of wear. The U-track that the old cable ran through was also bent
as a result of being hit.
In the process of replacing the cable, an e-chain was installed for cable management purposes. Mounting brackets were modified and a new U-track
Entry  Wednesday, July 29, 2015, 06:24, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, Stopped the CS and TM4 pumps and vent with argon. 
Dan and I stopped the CS and TM4 pumps. We are venting the CS with argon for UCX13 target.