ID Date Author Category Type Moduledown Target/Number Subject
  960   Wednesday, June 24, 2015, 10:16 chad fisherSouth Hot-CellRepairTM2 TM2 Vacuum Leak Check

The following circuits have been vacuum leak checked and have not registered any leaks:

Circuit D, C, B, A, Coil2, EE, Ground Electrode, Mounting Support plate, Coil 1.

Left are Heat Shield and Window circuits which will be checked after blank offs are installed on the vcr terminations.

  961   Wednesday, June 24, 2015, 13:49 David WangSouth Hot-CellRepairTM2 TM2 new source tray vacuum leak check.

All water blocks seals and joints have been leak checked. No leak has been found on any of them. See attachment

Attachment 1: TM2_new_source_tray_water_block_leak_check_at_SHC.pdf
TM2_new_source_tray_water_block_leak_check_at_SHC.pdf TM2_new_source_tray_water_block_leak_check_at_SHC.pdf TM2_new_source_tray_water_block_leak_check_at_SHC.pdf
  962   Friday, June 26, 2015, 08:27 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015

Update the Target hall Schedule after some changes on TM2 refurbishment. See attachment 1,2

2015-06-30, updated the schedule after some jobs have been finished before Canada day. See attachment 3,4.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
  963   Friday, June 26, 2015, 09:44 chad fisherSouth Hot-CellRepairTM2 TM2 Retrofit Status

On June 25th the following work was completed:

Optics tray was installed into TM2. The lower fastener on the vertical cable tray (IRH1585) needed to be removed and vertical cable tray rotated upwards as optics tray would not clear cable tray. Optics tray was intstaled, cable tray repositioned and screw re-inserted.

Modified water block for 9 pin connector was installed.

Steerers connected.

Ground Electrode water blocks were "repositioned" closer to there specified position to attempt eliminating the short between the ground electrode line and coil 1 circuit. This was successful but could still use a clamp or other method of ensuring the ground electrode line is in its "proper" place.

9 pin connector line was rerouted to ensure it does not contact anything it is not suppose to (Rerouting directions provided by Anders).

Enzel lens cable was installed.

Blank offs removed from window water lines and new gaskets installed in preparation for installation of the containment box.

 

Attachment 1: 20150625_075616_1.jpg
20150625_075616_1.jpg
Attachment 2: 20150625_083457.jpg
20150625_083457.jpg
Attachment 3: 20150625_105735.jpg
20150625_105735.jpg
Attachment 4: 20150625_110053.jpg
20150625_110053.jpg
  964   Friday, June 26, 2015, 09:45 chad fisherSouth Hot-CellRepairTM2 TM2 Status

Containment box window waterlines have been connected and leak checked and new containment box cover installed.

Module ready for transport just before 9am.

  965   Friday, June 26, 2015, 14:33 David WangConditioning StationStandard OperationTM2 TM2 have been moved from SHC to CS

Bill and I mover TM2 from SHC to CS. The move is smooth. I connected the CS vacuum system after the move, and started the roughing.

  966   Friday, June 26, 2015, 15:38 Anders MjosConditioning StationDevelopmentTM2 Leak check and HV test

Roughing started by David.

Friday, June 26, 2015, 15:31: Started TP1S

Friday, June 26, 2015, 15:38: Started  TP1 & TP2

Friday, June 26, 2015, 15:47: TPs timed out. Restarted

Friday, June 26, 2015, 15:49: TP2 at speed

Friday, June 26, 2015, 15:49: TP1 at speed.

Friday, June 26, 2015, 15:54: IG1 on. 4.7E-5 T.

Friday, June 26, 2015, 15:56: IG2 on.  9.8E-5 T

Friday, June 26, 2015, 15:59: IG1S on. 2.9E-4 T


Leak found on service cap panels (David W)

Monday, June 29, 2015, 10:29: Stopped turbo pumps.

  967   Monday, June 29, 2015, 10:51 David WangConditioning StationRepairTM2 leak on TM2 side panel

There is an air to vacuum leak on TM2 service cap side panel which we moved out during the TM2 wiring job. The CS pumps are stopped now. The CS will be vented soon. The seal on this panel has to been changed.

2016-06-30.  The o-ring seal on this panel(PNG1 and steerers)  is replaced and leak checked. No leak now.

  972   Tuesday, June 30, 2015, 15:53 David WangConditioning StationDevelopmentTM2 leak on TM2 at CS

 I leak checked TM2 at CS this afternoon which including air to vacuum check on service cap and helium pressure test on water lines. There is a small leak on water line R ,U (COIL1) during the helium pressure test.. Below 20 psi helium, there is no leak on it. But , once the helium pressure is increased over 20 psi, it showed up on Leak Detector. At 60 psi helium, the leak rate is 9.4xE-9 atm.cc/sec. For detail information, See attachment.  All other water lines and air to vacuum seals are good.

Attachment 1: TM2_leak_check_2015-06-30.pdf
TM2_leak_check_2015-06-30.pdf TM2_leak_check_2015-06-30.pdf TM2_leak_check_2015-06-30.pdf TM2_leak_check_2015-06-30.pdf
Attachment 2: leak_check_2015-06-30_007.JPG
leak_check_2015-06-30_007.JPG
Attachment 3: leak_check_2015-06-30_009.JPG
leak_check_2015-06-30_009.JPG
  973   Thursday, July 02, 2015, 10:22 Anders MjosConditioning StationMaintenanceTM2 TP1S failed

 See e-fault 8233. Edi assisted in diagnosing the problem. The pump will have to be replaced.

  976   Friday, July 03, 2015, 09:11 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule moved

TM#2 has been moved from the conditioning station to the south hot cell.

  978   Friday, July 03, 2015, 09:41 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015

Updated the schedule before the weekend 2015-07-03. See attachment 1,2

Updated the schedule according to present TM2 refurbishment process. See attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
  979   Friday, July 03, 2015, 11:33 chad fisherSouth Hot-CellRepairTM2 TM2 Coil Leak Progress

First thing this morning the hot cell was "cleaned up" in preparation for the return of TM2 for attempted verification and locating of leak on R/U coil circuit.

Containment box has been removed and front cover reinstalled to provide some modicum of shielding form the entrance and exit windows. Box was placed at an angle in the corner to try and minimize line-of-sight with potential worker(s).

Did notice some funny discoloration of both sides of coil water block "R" as seen in attached picture.

Attachment 1: TM2_coil_leak_20150703_11.jpg
TM2_coil_leak_20150703_11.jpg
Attachment 2: 20150703_111248.jpg
20150703_111248.jpg
  980   Friday, July 03, 2015, 13:29 chad fisherSouth Hot-CellRepairTM2 Hot Cell/ Module Fields

Field measured at block "R" through tool port with pole monitor is 6.65 mSv/H.

There are three air hoods and two air lines currently available.

  983   Wednesday, July 08, 2015, 12:18 chad fisherSouth Hot-CellRepairTM2 R U Coil line Removal

R U coil line removal started at 11:30. Water block jig installed and coil line disconnected from module.

Attachment 1: TM2_20150708_coil_line_leak.jpg
TM2_20150708_coil_line_leak.jpg
  984   Wednesday, July 08, 2015, 14:05 David WangSouth Hot-CellRepairTM2 leak check coil line(R,U) on TM2 at SHC

Chad and I leak checked coil line(R,U) on TM2 at SHC yesterday. The leak detector was pumped down to 0.0Xe-9 atm.cc/sec before the check. Chad sprayed helium on the soldering joints connecting the cooling copper lines to the small holding blocks for the coil terminal(R,U).  After sprayed helium 2 seconds, I saw the leak rate on LD started to climbed up. The highest leak rate is 4.0xE-8 atm.cc/sec. It is a very positive response. We waited the leak detector pumped back to 0.0xE-9am.cc/sec, and tested again on the same joints. The result is same. Chad also sprayed helium on the R,U water blocks to check the C-seal. I saw a delayed tiny response on LD ( from 0.0 to 1.3xE-9atm.cc/sec). We think this tiny response is caused by the helium drifting to the leak soldering joint, but not a real C seal leak.

  985   Wednesday, July 08, 2015, 14:24 David WangSouth Hot-CellRepairTM2 TM2 pressure bubble test on RU water blocks.

July-06, 2015. Chad , Grant and I did the bubble test on R,U water blocks. We suspected the leak on the R,U circuit is from C seals on the water blocks so we did this test first. I applied both air and helium to R,U circuit , Chad applied snoop soap on the R,U water blocks.The air and helium pressure was increased from 40 psi to 90 psi Max step by step.Chad did not see any bubbles on the water blocks during the test. Since we did not find the leak source, we decided to do vacuum helium check on the all joints and c-seals of the R,U lines later.  Finally, We found the leak by vacuum helium spray the day after this bubble test. See other e-log.

  986   Wednesday, July 08, 2015, 14:48 chad fisherSouth Hot-CellRepairTM2 TM2 Status

Water block jig has been removed. Stuck source tray side water block jig component has been removed. An attempt was made to connect the gas lines to there bracket however they contact/interfer with the tube heater lines...Anders is looking into a solution.

Containment box and front cover have been replaced and TM2 is ready to move to the silo.

  987   Thursday, July 09, 2015, 09:55 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule moved

TM#2 has been moved from the south hot to the north east silo. TM#1 has been moved from the south west silo to the conditioning station.

  989   Thursday, July 09, 2015, 13:51 chad fisherSouth Hot-CellRepairTM2 Coil line removal hot cell

coil line has been removed from the hot cell. Initial decon was performed...after it still appears to have approximately 200 counts. It will now be transfered to the rad waste decon facility for further decon.