  RH-ISAC, Page 55 of 140  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Categorydown Type Module Target/Number Subject Text Attachments
  1865   Monday, February 11, 2019, 10:26 Isaac EarleSafe Module ParkingDevelopment  SMP shield box and vacuum vessel moved to Target Hall  On February 8th the SMP shield
box (IRH1675) and the vacuum vessel (IRH1806)
were both raised from a horizontal to vertical
 6x 
  1873   Thursday, February 21, 2019, 15:10 Isaac EarleSafe Module ParkingDevelopment  Seismic requirements for SMPDragan Mitrovic, TRIUMF structural engineer,
was consulted earlier this week regarding
seismic requirements for the SMP assembly. 
  
  1903   Monday, April 01, 2019, 14:56 Isaac EarleSafe Module ParkingDevelopment  SMP shield box and vacuum vessel installed in final location Last week drilling of the additional
required holes in the SMP shield box was
completed in the Target Hall.  This
 20190401_101459.jpg20190401_110433.jpg20190401_144133.jpg20190401_110353.jpg 
  1904   Thursday, April 04, 2019, 14:49 Isaac EarleSafe Module ParkingDevelopment  SMP vacuum vessel support roller friction checkWith the SMP vacuum vessel now installed
inside the shield box, a test was performed
to measure the torque required to rotate
 CRR_check_for_as-built_SMP_-_April_4_2019.pdf 
  1921   Wednesday, May 15, 2019, 16:06 Isaac EarleSafe Module ParkingDevelopment  SMP module support flange installed and leak checkedThe SMP module support flange sub-assembly
(IRH1755) was installed today according to
drawing IRH1683.  Dow Corning 111 sealing
 20190515_094730.jpg20190515_094740.jpg20190515_103253.jpg20190515_103824.jpg 
  1925   Friday, May 17, 2019, 16:46 Adam NewsomeSafe Module ParkingDevelopment  SMP Controls Installation Update 
The following controls-related
 IMG_20190417_100838.jpgIMG_20190417_100843.jpgIMG_20190517_162230.jpgIMG_20190517_162305.jpg 
  1944   Thursday, June 20, 2019, 15:09 Isaac EarleSafe Module ParkingDevelopment  SMP motor wiring inspected by electricianThe AC wiring for the SMP motor was inspected
by Randy Boehm (TRIUMF electrician) as recommended
by Franco Mammarella (TRIUMF electrical engineer). 
  
  1946   Thursday, July 04, 2019, 08:57 Isaac EarleSafe Module ParkingDevelopment  SMP vacuum system installed July 3:
- Assembled exhaust line flexible
hose and fittings as per ISK0529 Rev D then
 20190703_122635.jpg20190703_122646.jpg20190703_122702.jpg 
  1955   Friday, July 26, 2019, 15:43 Isaac EarleSafe Module ParkingDevelopment  SMP vacuum control system completed The SMP vacuum control system has
been wired and setup to be controlled from
EPICS.  Backing valve control (SMP:BV1)
 SMP_vacuum_system_EPICS_screen.png 
  1970   Friday, August 23, 2019, 14:27 Isaac EarleSafe Module ParkingDevelopment  SMP camera video cabling installed and tested Installation of the video lines for
the SMP cameras was completed yesterday according
to IRH1670 Rev B.  All four cameras
  
  1971   Tuesday, August 27, 2019, 13:12 Adam NewsomeSafe Module ParkingDevelopment  SMP Remote Control Wiring InspectionThe wiring for the SMP remote control module
was inspected by Joel Semilla (TRIUMF  electrician).
 The module was plugged in to verify there
  
  1990   Monday, September 30, 2019, 11:27 Isaac EarleSafe Module ParkingDevelopment  SMP vacuum vessel modifications completedThe SMP vacuum vessel welds were reinforced
to match the specifications on IRH1710 Rev
D.  In addition a tube stub was added
  
  2006   Thursday, October 10, 2019, 16:17 Adam NewsomeSafe Module ParkingDevelopment  SMP Main Panel: Relay Addition for E-Stop CircutAn update was made for the E-stop and power
supply system in the SMP main panel. Upon
testing remote control, it was determined
 Changes_to_IRH1869.JPGIMG_20191009_153336_-_new_relay_for_E-stop.jpg 
  2007   Tuesday, October 15, 2019, 16:42 Isaac EarleSafe Module ParkingDevelopment  SMP flange alignment tested using shield plug As a preliminary test in preparation
for SMP commissioning, one of the steel module
shield plugs was installed into the SMP to
 smp1.jpgsmp2.jpgsmp3.jpgsmp4.jpg 
  2010   Tuesday, October 22, 2019, 16:26 Isaac EarleSafe Module ParkingDevelopment  SMP shield box groundingA braided grounding strap was attached
to the aluminum gear box support on the SMP
shield box structure, and grounded by attaching
  
  2014   Friday, October 25, 2019, 06:43 David WangSafe Module ParkingDevelopmentTM3 SMP vacuumTM3 was moved into SMP Oct 25 morning. 
After two nights pumping down, SMP CG1 read
30mtorr this morning.  The pump is stopped.
  
  2016   Monday, October 28, 2019, 12:00 Isaac EarleSafe Module ParkingDevelopment  SMP shielding attenuation measured & compared to theoretical valuesThe attenuation of the SMP shielding was
measured as part of SMP commissioning (Document-170404,
R1, Section 4, Test #8)
  
  2017   Tuesday, October 29, 2019, 10:00 Adam NewsomeSafe Module ParkingDevelopment  SMP Updates to E-stop circuit and feedback signalsThe SMP main control panel and remote control
module were updated in  order to implement
the following items which were deemed desirable
  
  2037   Thursday, December 12, 2019, 14:39 Isaac EarleSafe Module ParkingDevelopment  SMP assembly shifted 1.0" northThe SMP assembly was shifted approximately
1.0" north today by pushing it, braced
against the south wall, using a 100 Ton capacity
  
  2071   Thursday, February 27, 2020, 09:50 Travis CaveSafe Module ParkingStandard OperationTM2SiC#39Module move TM#2 with SiC#39 has been moved from
the east station to the smp.
  