Entry  Wednesday, July 16, 2014, 13:59, chad fisher, South Hot-Cell, Standard Operation, TM3, SiC#30, Sic#30 install 
Entry  Thursday, July 31, 2014, 08:08, chad fisher, South Hot-Cell, Standard Operation, TM3, SiC#30, SiC#30 Removed and inpect TM320140731_01.jpgTM320140731_02.jpgTM320140731_03.jpgTM320140731_04.jpg
Entry  Wednesday, August 06, 2014, 11:12, Travis Cave, South Hot-Cell, Standard Operation, , SiC#30, Spent target move Vault_Storage_August_6_2014.pdf
Entry  Wednesday, July 24, 2013, 08:40, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#29, Electrical check TM#4_SiC#29_FEBIAD_Tgt_Elec_Chk.PDF
Entry  Wednesday, July 24, 2013, 14:40, Travis Cave, Conditioning Station, Standard Operation, TM4, SiC#29, module move 
Entry  Thursday, July 25, 2013, 09:37, Travis Cave, Conditioning Station, Standard Operation, TM4, SiC#29, Electrical check TM#4_SiC#29_FEBIAD_TgtElecChkCS_.PDF
Entry  Tuesday, July 30, 2013, 10:44, Travis Cave, ITE, Standard Operation, TM4, SiC#29, module move 
Entry  Thursday, August 15, 2013, 16:35, Anders Mjos, ITE, Repair, TM4, SiC#29, Leak found on Coil 1 ITE_Leak_Test_2013-08-14.pdf
Entry  Monday, August 19, 2013, 10:08, Anders Mjos, ITE, Repair, TM4, SiC#29, Leak Check ITE_Leak_Test_2013-08-19.pdf
Entry  Thursday, September 12, 2013, 09:29, Travis Cave, ITW, Standard Operation, TM4, SiC#29, module move 
Entry  Thursday, September 12, 2013, 10:35, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#29, Electrical check TM#4SiC#29FEBIADelechkpostbeam.PDF
Entry  Monday, September 30, 2013, 15:59, Bevan Moss, South Hot-Cell, Standard Operation, TM4, SiC#29, Module move from SW Silo to SHC 
Entry  Tuesday, October 01, 2013, 10:59, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#29, Electrical check TM#4_elec_chk_SiC#29_SHC_post2.PDF
Entry  Tuesday, October 08, 2013, 13:11, Travis Cave, Spent Target Vault, Standard Operation, , SiC#29, Spent target move Vault_Storage_October_8_2013.pdf
Entry  Tuesday, October 08, 2013, 14:58, Anders Mjos, South Hot-Cell, Standard Operation, , SiC#29, Target to Heat Shield electrical short 
Entry  Wednesday, May 29, 2013, 12:07, chad fisher, South Hot-Cell, Development, , SiC#28 RFQ, RFQ Autopsy 
Entry  Tuesday, March 26, 2013, 14:17, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#28 (RFQ Target), Electrical check TM4_SiC28_RFQ_SHC_ELEC_CHK.PDF
Entry  Wednesday, March 27, 2013, 10:44, Travis Cave, ITE, Standard Operation, TM4, SiC#28 (RFQ Target), module move 
Entry  Tuesday, May 21, 2013, 11:38, Travis Cave, ITE, Standard Operation, TM4, SiC#28 (RFQ Target), module move 
Entry  Wednesday, May 22, 2013, 10:41, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#28 (RFQ Target), module move 