Entry  Thursday, August 02, 2018, 14:12, Travis Cave, Spent Target Vault, Standard Operation, , Nb#8, Spent Target Move Target_Index_2018-08-02.pdf
 The spent Nb#8 target was moved from the south hot cell to the spent target vault. It was placed in pail #168 and place in spot 2A in the vault.
See the attached pdf for vault details.
Entry  Thursday, August 02, 2018, 07:57, David Wang, Conditioning Station, Standard Operation, , , Leak check on TM2 UCx #23 @ TCS and SHC. 
I did a helium pressure test on TM2 HS line at TCS. At 70psi helium, the leak rate is 2.5 xE-7 atm.cc/sec. I think this is the number that close to result
before which is 1.7xE-9 atm.cc/sec. WE know there is a small leak on this water block seal. Chad  and I did helium  spray check yesterday at
SHC. It was good at bottom scale.  No much worry on this low E-7 range leak. 
Entry  Wednesday, August 01, 2018, 15:12, Anders Mjos, South Hot-Cell, Standard Operation, TM2, UC#23, Target mounted - water leak on HS line 20180801_180130904_iOS.jpg
The heat shield water lines were not purged ahead of target exchange  in the hot cell. This resulted in water leaking onto the new target  assembly (heat
shield) when the cooling lines were opened at top and  bottom (for connecting leak detector). Excess water was wiped up with  paper towels.
Entry  Wednesday, August 01, 2018, 14:48, Travis Cave, Conditioning Station, Standard Operation, TM2, UC#23, Spent Target Move 
 TM#2 with UC#23 has been moved from the south hot cell to the conditioning station.
Entry  Wednesday, August 01, 2018, 09:47, Isaac Earle, North Hot-Cell, Development, , , NHC diagnostic signals and control panel tested 
 On July 30th the NHC diagnostic signals were tested:
- 9 pin CPC: a shorting plug was installed on the hot side - continuity check results were as expected
- 4 pin CPCs:  snake camera installed in both hot side connectors with portable monitor on cold side - both connectors worked as expected
Entry  Tuesday, July 31, 2018, 11:16, Travis Cave, Spent Target Vault, Standard Operation, , UC#22, Spent Target Move Target_Index_2018-07-30.pdf
 Yesterday the spent UC#22 target was moved from the south hot cell to the spent target vault. It was placed in pail #167 and placed in spot 4A
see attached PDF for details.
Entry  Tuesday, July 31, 2018, 10:20, Travis Cave, South Hot-Cell, Standard Operation, TM2, Nb#8, Module move 
 TM#2 with Nb#8 has been moved from ITW to the south hot cell.
Entry  Wednesday, July 25, 2018, 13:21, Anders Mjos, ITW, Repair, TM2, Nb#8, Leak check of ITW Entrance_Module_Leak_2018-07-25.docx
ITW Entrance Module was leak checked yesterday with the support of Vacuum Group (Dimo & Edi). The leak detector was connected to primary backing
vacuum line. A leak response was found near the bellow for the beam profile monitor on top of the Entrance Module. It could be confirmed today by actuating
the monitor, that the leak was indeed at that location. The plan is to move the TM and Entrance Module out for target exchange and repair, respectively.
Entry  Monday, July 23, 2018, 10:31, Travis Cave, ITE, Standard Operation, TM4, Ta#56, Module move 
 TM#4 with Ta#56 has been moved from the conditioning station to the east target station.
Entry  Thursday, July 19, 2018, 14:22, Isaac Earle, North Hot-Cell, Development, , , NHC diagnostic signals - connector and wiring details 
Installation of the diagnostic connections between the NHC hot and cold sides has been completed.  The cable bundle was prepared by Travis Cave
in the electronics workshop with connectors attached at one end only.  Metal fish tape was first ran through the conduit from the cold side to hot
side, the non-terminated end of the cable bundle was attached to the fish tape inside the cell, cable pulling lubricant was applied, then the cable bundle
Entry  Thursday, July 19, 2018, 09:17, chad fisher, South Hot-Cell, Repair, TM4, , New Optics Tray Modification 20180719_TM4_2.jpg20180709_TM4.jpg
The waterline loop bracket has been installed onto the new loop holding bracket and both installed onto the new source tray.
Entry  Wednesday, July 18, 2018, 14:20, chad fisher, South Hot-Cell, Standard Operation, TM4, Ta#56, Ta#56 Installed 
Ta#56 has been installed onto TM4 with new fasteners. High current fasteners torqued to 130 in lbs.
RIB "shield" has been removed in  preparation for insertion of new optics tray.
Entry  Monday, July 16, 2018, 17:41, Anders Mjos, ITE, Standard Operation, TM4, UC#22, Target module disconnected TM4_UCx_22#__disconnection_check_list_1.pdfTM4_UCx_22#__disconnection_check_list_2.pdf
The water and electrical connections were disconnected today as protons remained off after power interruption during the weekend. Vacuum is still connected
and operating.
 The vacuum system are disconnected 2018-07-17.  See attachment .
Entry  Wednesday, July 11, 2018, 15:09, Anders Mjos, ITW, Maintenance, TM2, Nb#8, Uncovered ITW to toubleshoot 2A2M19 
The 2A2M19 beam profile monitor did not work and was e-faulted.
After initial troubleshooting 2 blocks were removed form ITW to inspect the entrance module where the beam monitor is installed. The cable was found not
to be connected and was quickly fixed. Blocks reinstalled. The work was done by Maico, Travis and Anders
Entry  Wednesday, July 11, 2018, 15:06, Anders Mjos, ITW, Standard Operation, TM2, Nb#8, Block move 
Maico and Travis moved blocks from ITE to ITW yesterday
Entry  Tuesday, July 03, 2018, 14:42, David Wang, ITW, Standard Operation, TM2, Nb#8, TM2 has been connected to ITW. Nb#4_Module_connection_checklist.pdf
TM2 has been connected to ITW. All turbo pumps are started. See attachment for connection checklist.
Entry  Tuesday, July 03, 2018, 14:38, David Wang, ITW, Standard Operation, , , ITW water signals interlock check. 
Annual ITW water signals interlock check are done. Everything works good.
Entry  Tuesday, July 03, 2018, 09:57, Travis Cave, ITW, Standard Operation, TM2, Nb#8, Module move 
 TM#2 with Nb#8 has been moved from the south hot cell to the west target station.
Entry  Friday, June 29, 2018, 13:36, Travis Cave, South Hot-Cell, Standard Operation, TM2, Nb#8, Electrical Check TM2_elec_chk_steerers_and_lens_062818.pdfTM2_Nb8_elec_chk_shc.pdfTM2_notgt_elec_chk_shc_062918.pdf
 The results of the various electrical checks performed on the TM#2 with and without the Nb#8 target attached.
Entry  Friday, June 29, 2018, 10:27, chad fisher, South Hot-Cell, Maintenance, , , South Hot Cell Filter Change 
At the end of manipulator repair Thursday the ventilation pre-filter in the hot cell was changed. Old filter remains in the hot cell until such time
as it can be removed.