Entry  Thursday, June 02, 2016, 11:59, David Wang, South Hot-Cell, Repair, TM3, , 5K mega test on TM3 5K_mega_check_on_TM3.pdf
I did a 5KV mega test on TM3.  Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines
are ok. See attachment.
    Reply  Thursday, June 02, 2016, 18:04, Aurelia Laxdal, South Hot-Cell, Repair, TM3, , 5K mega test on TM3 DSC_0821.JPGDSC_0822.JPG


    
        
            David Wang wrote:
        
        
            
            I did a 5KV mega test on TM3.  Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed
Entry  Friday, June 03, 2016, 11:35, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, module moved 
TM#3 has been moved back to the north east silo.
    Reply  Friday, June 03, 2016, 16:04, Aurelia Laxdal, South Hot-Cell, Repair, TM3, , 5K mega test on TM3 


    
        
            Aurelia Laxdal wrote:
        
        
            
            
            
              
Entry  Wednesday, July 13, 2016, 08:47, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, module moved 
TM#3 has been moved from the north east silo to the conditioning station.
Entry  Monday, July 18, 2016, 13:56, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, module moved 
TM#3 is now in the south hot cell.
Entry  Monday, July 18, 2016, 14:14, David Wang, Conditioning Station, Repair, TM3, , TM3 leak checked at TCS 
Last Friday July-15, TM3 was leak checked at TCS. All air to vacuum seals on service cap are good.  Helium pressure test on  TM3 water lines(except
GE, HS, and Window) were done. Leak detector has no response at 0.0xE-9 atm.cc/sec. They are leak free.
    Reply  Tuesday, July 19, 2016, 14:35, Aurelia Laxdal, Conditioning Station, Repair, TM3, , TM3 leak checked at TCS 


    
        
            David Wang wrote:
        
        
            
            Last Friday July-15, TM3 was leak checked at TCS. All air to vacuum seals on service cap are good.  Helium pressure
Entry  Friday, July 22, 2016, 10:57, David Wang, Conditioning Station, Repair, TM3, , TM3 has been moved and connected at TCS 
I started vacuum system.
I started TCS water system. The chiller does not work properly still. But, It will not affect the TM3 HV conditioning.  HV cover is installed
on TM3 in TH. The module is ready for HV conditioning.
Entry  Monday, July 25, 2016, 08:15, Anders Mjos, Conditioning Station, Repair, TM3, , HV Test TM3_HV_conditioning_2016-07-25.docxTCS-2016-07-25_TM3_no_target.rgaTCS-2016-07-26_TM3_no_target.rga
 Monday, July 25, 2016, 08:14: Enabled staging for chiller
Monday, July 25, 2016, 08:33: Disabled staging. Fault 2. Staging does not work at this point.
Monday, July 25, 2016, 08:34: Running CP1 manually to cool down water.
Entry  Thursday, July 28, 2016, 11:27, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, module moved 
TM#3 with no target has been moved from the conditioning station to the NE silo.
Entry  Wednesday, August 10, 2016, 09:44, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, module moved 
TM#3 has been moved from the north east silo to the conditioning station.
Entry  Thursday, August 11, 2016, 10:37, David Wang, Conditioning Station, Repair, TM3, , TM3 service tray cover plate ITA2108 has been removed. 
Requested by Aurelia, and approved by Friedhelm, TM3 service tray cover plate ITA2108 has been remove out of the module. The plated is checked for active
and contamination after removal. Then,It is double bagged, sealed ,  tagged, and placed downstairs in TH between south wall and green block . The
ram contact reading on the plate is about 10 usv/hr.  We will do anther TM3 HV test at TCS without this cover plate.
Entry  Friday, August 12, 2016, 10:59, Anders Mjos, Conditioning Station, Development, TM3, , HV Test with Service Chase Panel removed TM3_HV_conditioning_2016-08-12.docxTCS-2016-08-11_TM3_Service_Chase_Panel_Removed.rga
Water cooling is performed manually with CP1. RGA is ON since yesterday. EE is not connected and in conditioning mode.

Friday, August 12, 2016, 10:43: BIAS at 10 kV, EL at 0.5 kV. IG1 at 1.8E-6 T
 Friday, August 12, 2016, 11:04: BIAS at 20 kV
Entry  Tuesday, August 16, 2016, 12:35, David Wang, Conditioning Station, Repair, TM3, , CS vacuum pumps have been stopped 
The TCS is venting now. The TM3 blue insulator replacement job will be started soon.
Entry  Thursday, August 18, 2016, 14:19, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, module moved 
TM#3 is now back in the the north east silo.
Entry  Wednesday, September 07, 2016, 11:44, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, module moved 
TM#3 has been moved from the NE Silo to the conditioning station.
Entry  Thursday, September 08, 2016, 16:28, David Wang, Conditioning Station, Repair, TM3, , TM3 blue insulators have been replaced. 
All TM3 blue insulators except Gas,EL, and 60 KV common  on top of the module have been replaced with new designed insulators. The new blue insulator
for gas line need to be modified to fit for the bent on the gas  line.   EL, and 60KV common blue insulators were replaced during last time
TM3 refurbishment so they are relative new, and  not replaced this time. All seals related to the blue insulators are changed to new seals. The o-
Entry  Thursday, September 08, 2016, 16:30, David Wang, Conditioning Station, Repair, TM3, , TM3 vacuum system have been connected at TCS. 
start of roughing now.
 start of TCS and TM3 turbo-pumps. Everything is good so far.
Entry  Monday, September 12, 2016, 09:25, David Wang, Conditioning Station, Repair, TM3, , TM3 leak checked at TCS 
After blue insulators replacement, TM3 service cap are leak checked. LD base leak rate 0.0xe-9 atm.cc/sec. I sprayed lots helium on all blue insulator
seals. No leak has been found. Double checked them again, and got same result. All other seals on top of TM3 also have been checked. They are leak free.
OVEN, TUBE, MSP, COIL, and EE water lines are pressurized with 70 psi helium for 3minutes each. They are good also.