  ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  1080   Thursday, September 24, 2015, 07:00 David WangConditioning StationMaintenanceTM4Ta#46Turned off TCS all vacuum pumps and water pumps.TCS:MP1 back up pressure went up too high
(700mtorr).I turned off all the pumps.The
TCS is under vacuum still. TCS water 
  
  1081   Thursday, September 24, 2015, 14:59 Friedhelm AmesConditioning StationStandard OperationTM4Ta#46start high voltage conditioning    
  1084   Monday, September 28, 2015, 10:10 David WangConditioning StationStandard OperationTM4Ta#46Switched off CS vacuum pumps and water systemI switched off CS vacuum pumps and water
system after Isac opps finished the TM4 conditioning
at CS.
  
  1085   Tuesday, September 29, 2015, 09:38 Travis CaveITEStandard OperationTM4Ta#46Module movedTM#4 with Ta#46 has been moved to ITE from
the conditioning station.
  
  1086   Tuesday, September 29, 2015, 12:31 David WangITEStandard OperationTM4Ta#46TM4 has been connected in ITEDan and I connected TM4 in ITE. The turbo-
pumps are started. Water supply to TM4 only
at this stage. Everything is good so far.
  
  1091   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.The ITE is configured to take proton beam.   
  1092   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.The ITE is configured to take proton beam.   
  1133   Wednesday, November 25, 2015, 11:52 Travis CaveSouth Hot-CellStandard OperationTM4Ta#46Module movedYesterday TM#4 with Ta#46 was moved from
the east station to the south hot cell.
  
  1141   Thursday, November 26, 2015, 08:52 Travis CaveSpent Target VaultStandard Operation Ta#46Spent Target moveTa#46 was placed in the ISAC spent target
vault yesterday. See attached PDF for details.
 Vault_Storage_November_26_2015.pdf 
  867   Monday, March 23, 2015, 14:03 chad fisherSouth Hot-CellStandard Operation Ta#45Ta#45 inserted into hot cellTa#45 has been inserted into the hot cell.
Swipe taken of inner tool port area: 100000
counts/min.
  
  869   Tuesday, March 24, 2015, 09:47 chad fisherSouth Hot-CellStandard OperationTM4Ta#45Ta#45 installedTa#45 has been installed onto TM4 and is
ready for leak and electrical check. High
current fasteners torqued to 130 in.lbs.
  
  870   Tuesday, March 24, 2015, 13:57 Travis CaveSouth Hot-CellStandard OperationTM4Ta#45Electrical checkTM#4 electrical checks with and without
the target installed, installed target is
Ta#45.
 TM4_no_tgt_elec_chk_CS.PDFTM4_Ta45_elec_chk_SHC.PDF 
  872   Wednesday, March 25, 2015, 14:25 David WangSouth Hot-CellStandard OperationTM4Ta#45Leak check on TM4 HS water line with new Ta#45 target. at SHCChad and I leak checked TM4 HS water line
with new Ta#45 target installed at SHC. Leak
detector base leak rate 0.0Xe-9 atm.cc/sec,
  
  873   Wednesday, March 25, 2015, 14:34 David WangConditioning StationStandard OperationTM4Ta#45 TM4 and CS turbo- pumps are started .I connected TM4 and CS vacuum system after
TM4 move. CS roughing pump was started first
this morning. Later, Anders, Bill and I started
  
  874   Thursday, March 26, 2015, 09:20 Travis CaveConditioning StationStandard OperationTM4Ta#45Electrical checkElectrical check of TM#4 with Ta#45 at
the conditioning station, see attached pdf
for details.
 TM4_Ta#45_tgt_elec_chk_CS.PDF 
  875   Friday, March 27, 2015, 10:03 David WangConditioning StationStandard OperationTM4Ta#45Helium pressure test on TM4 HS line at CSThe helium pressure test on TM4 HS line
at conditioning station is done. No leak.
I also leak checked all vacuum seals on TM4
 001.JPG005.JPG006.JPG 
  876   Friday, March 27, 2015, 11:29 David WangConditioning StationStandard OperationTM4Ta#45TM4 is connected at CSTM4 has been connected at CS which includes
high current cables, water lines, EE cable,
and Enizel lens cable. The HV cover has been 
 010.JPG013.JPG012.JPG 
  878   Monday, March 30, 2015, 09:03 Anders MjosConditioning StationStandard OperationTM4Ta#45Ta#45 ConditionoingMonday, March 30, 2015, 08:59: Reset chiller
by switching on off power (fault 2)
Monday, March 30, 2015, 09:02: Switched
 Ta#45_Conditioning.docx 
  880   Wednesday, April 01, 2015, 06:56 David WangConditioning StationStandard OperationTM4Ta#45TM4 has been disconnected at CS.TM4 has been disconnected at CS. The CS
and TM4 is venting for move. Anders stopped
vacuum and water system yesterday.
  
  881   Wednesday, April 01, 2015, 10:52 Travis CaveITEStandard OperationTM4Ta#45Module moveTM#4 with Ta#45 has been moved from the
conditioning station to the east target station.
  