  1888   Friday, March 08, 2019, 14:10 chad fisherSouth Hot-CellRepairTM2 Water block polishing

After trials with 2000 grid wet paper I have moved up to "red" scotch brite. This seems to have worked the best so far although it took two minutes to remove the ring that the other materials could not remove (see picture).

I have moved to next circuit. Currently at 3 minutes and 30 seconds with scotch brite but significant ring remains.

Attachment 1: B_after_SB_(2).jpg
B_after_SB_(2).jpg
  1887   Thursday, March 07, 2019, 13:59 chad fisherSouth Hot-CellRepairTM2 Polishing

Polishing of the water block sealing surfaces has commenced. First attempt was on block B with low nap brown polishing pad (the least aggressive pad prepared) and isopropyl for 30 seconds. This cleaned a little but did not remove the "ring" which I believe is water scale. I will step up to 2000 grit wet sand paper and iso next.

  1886   Thursday, March 07, 2019, 12:20 chad fisherSouth Hot-CellRepairTM2 Pre-polishing pictures

Pictures of the water blocks before polishing can be found on docushare, collection 24400

  1885   Thursday, March 07, 2019, 12:02 chad fisherSouth Hot-CellRepairTM2 Box Off water block jig on

The containment box has been removed from TM2 and the water block jig installed in preparation for water block polishing.

Attachment 1: 20190307_113548.jpg
20190307_113548.jpg
  1884   Thursday, March 07, 2019, 09:12 David WangConditioning StationStandard OperationTM2 TM2 move from TCS to SHC.

TM2 has been moved from TCS to SHC. The move is smooth.

  1883   Tuesday, March 05, 2019, 14:29 chad fisherSouth Hot-CellRepair  Tray Transfer Fixture Repair Complete

Repair of the tray transfer fixture is complete (minus testing).

A distorted ball nut lock plate was replaced and thread loc added. to the ball nut/plate assembly. Testing will take place tomorrow once the thread lock has a chance to cure.

Attachment 1: 20190305_130312.jpg
20190305_130312.jpg
Attachment 2: 20190305_132303.jpg
20190305_132303.jpg
Attachment 3: 20190305_133800.jpg
20190305_133800.jpg
Attachment 4: 20190305_141346.jpg
20190305_141346.jpg
  1882   Tuesday, March 05, 2019, 09:38 chad fisherSouth Hot-CellRepair  Transfer Fixture Repair

Transfer fixture has been remotely disassembled to the point where the ball nut lock plate assembly can be inserted into the tool port and the plate replaced by hand in the tool port without having to enter the hot cell. Straight head screws will be replaced with SHCS to facilitate easier re-assembly and future disassembly.

Attachment 1: 20190305_092228.jpg
20190305_092228.jpg
Attachment 2: 20190305_092231.jpg
20190305_092231.jpg
Attachment 3: 20190305_092326.jpg
20190305_092326.jpg
Attachment 4: 20190305_092558.jpg
20190305_092558.jpg
  1881   Tuesday, March 05, 2019, 07:20 David WangConditioning StationRepairTM2 TM2 HV test at TCS

Spark between HV cover vertical mesh plate and HS 60KV  bias connecting clamp 90degree angle at 55 KV on TM2 top. HV cover is removed to test above  55KV. The spark triggered TH and SHC ventilation secondary alarm.

  1880   Friday, March 01, 2019, 10:23 Travis CaveSpent Target VaultStandard Operation  Source tray moved

 The old TM#2 source tray and TM#4 optics tray have been removed from the vault and placed into the spent target storage on tray 9 which is meant for source trays.

  1879   Friday, March 01, 2019, 09:57 chad fisherSouth Hot-CellRepairTM2 TM2 Source tray removal

TM4 optics tray was installed onto the old TM2 source tray yesterday and tray filled with non-active metal scrap. Tray inserted into transfer frame 95% yesterday. During insertion the ball nut of the transfer jig became unfastened from its drive plate. This will have to be fixed before the jig can be used reliably again however we were able to finish the job...the transfer jig is 20 years old now so it is not entirely suprising that it needs some attention.

Today the Tm2 tray final install into the transport tray occurred by driving the tray drive screw and bringing the tray into the transfer frame the last inch 1/2 or so. "Feet" (ITA2380) had to be removed from sliding tray assembly to fit in the box however upon attempting this is was immediately clear that one of the screws was stuck and must have been cross threaded during assembly. As as result the entire drive bracket (ITA2375) had to be removed form the source tray to allow final insertion into the box.

11 handles from spent target transfers, 1 plastic bin box, Ta LP test target TRI coil, 1 aluminum box, sockets and extensions from spent target transfers and 5 obsolete legs from previous source tray replacements were amoung the items disposed of with the spent source tray.

Attachment 1: 20190228_095131.jpg
20190228_095131.jpg
Attachment 2: 20190228_143718.jpg
20190228_143718.jpg
Attachment 3: 20190301_074849.jpg
20190301_074849.jpg
Attachment 4: 20190301_092907.jpg
20190301_092907.jpg
  1878   Friday, March 01, 2019, 08:42 Anders MjosConditioning StationStandard OperationTM2 Conditioning TM2 without source tray

BIAS and EZL connected. No water flowing into the module (water looped on top of module)

Friday, March 01, 2019, 08:20: 10kV

Friday, March 01, 2019, 08:40: 20kV

Friday, March 01, 2019, 08:57: 30kV

Friday, March 01, 2019, 11:00: 40kV

Friday, March 01, 2019, 15:23: 50kV


Monday, March 04, 2019, 08:50: 50kV

Monday, March 04, 2019, 09:22: 52.5kV

Monday, March 04, 2019, 10:01: Spark tripped TPs at 54kV

Monday, March 04, 2019, 10:04: 50kV

Monday, March 04, 2019, 10:14: Multiple sparks at 54kV. Lowered to 30kV to stop.

Monday, March 04, 2019, 10:15: 40kV

Monday, March 04, 2019, 10:16: Sparking at 42kV. Lowered to 40kV

Monday, March 04, 2019, 10:19: 42kV

Monday, March 04, 2019, 10:48: 50kV

Monday, March 04, 2019, 11:11: 52.5kV

Monday, March 04, 2019, 11:25: 54kV

Monday, March 04, 2019, 11:50: 55kV

Monday, March 04, 2019, 13:33: 3 sparks observed for the last 1.5h

Removed HV cover to avoid sparking between F/T and cover.

Monday, March 04, 2019, 14:02:20kV

Monday, March 04, 2019, 14:06: 50kV

 Monday, March 04, 2019, 14:12: 55kV

Monday, March 04, 2019, 14:20: Multiple sparks at 56kV. Lowered to 30kV to stop.

Monday, March 04, 2019, 14:27: 40kV

Monday, March 04, 2019, 14:29: 50kV

Monday, March 04, 2019, 14:32: 55kV

Monday, March 04, 2019, 14:40: 56kV

Monday, March 04, 2019, 14:55: Multiple sparks at 57kV. Lowered to 30kV to stop

Monday, March 04, 2019, 15:01: 55kV

Monday, March 04, 2019, 15:36: 57kV

Monday, March 04, 2019, 15:51: 57.5kV

Monday, March 04, 2019, 16:30: ~1 spark in 0.5h, somewhat unstable current (see attached Word file)

Monday, March 04, 2019, 16:30: HV off

Attachment 1: TM2_BIAS_current_vs_voltage_2019-03.xlsx
Attachment 2: TM2_HV_Conditioning_2019-03-01.docx
  1877   Tuesday, February 26, 2019, 10:33 Travis CaveConditioning StationStandard OperationTM2no targetModule move

 TM#2 with no source tray has been moved from the south hot cell to the conditioning station.

  1876   Tuesday, February 26, 2019, 08:51 chad fisherSouth Hot-CellRepairTM2 TM2 containment box

The containment box has been reinstalled onto TM2 in prepatation for testing in the conditioning station.

  1875   Monday, February 25, 2019, 09:44 chad fisherSouth Hot-CellRepairTM2 Water block jig

module side water block jig has been removed in preparation for electrical checks.

  1874   Friday, February 22, 2019, 10:31 chad fisherSouth Hot-CellRepairTM2 TM2 Source tray removal

The source tray has been removed from TM2.

Attachment 1: 20190220_090149.jpg
20190220_090149.jpg
Attachment 2: 20190222_100828.jpg
20190222_100828.jpg
Attachment 3: 20190222_101507.jpg
20190222_101507.jpg
Attachment 4: 20190222_101507.jpg
20190222_101507.jpg
Attachment 5: 20190222_101624.jpg
20190222_101624.jpg
Attachment 6: 20190222_102240.jpg
20190222_102240.jpg
  1873   Thursday, February 21, 2019, 15:10 Isaac EarleSafe Module ParkingDevelopment  Seismic requirements for SMP

Dragan Mitrovic, TRIUMF structural engineer, was consulted earlier this week regarding seismic requirements for the SMP assembly.  Installation location, overall dimensions, total weight, and the center of mass for assembly IRH1670 were provided to him by e-mail.  On Feb 20th he communicated verbally that he had analyzed the assembly for seismic loads, and concluded that this equipment does not require anchoring or any other form of seismic restraint.

Update (May 30, 2019): Confirmed with Dragan that the approach he used for analysis was that specified in the BC Building Code (both 2012 edition and updated 2018 edition).

  1872   Wednesday, February 20, 2019, 09:07 chad fisherSouth Hot-CellRepairTM2 Module side waterblock jig

I have installed the module side water block jig.

  1871   Tuesday, February 19, 2019, 11:56 chad fisherSouth Hot-CellRepairTM2 Optics tray removal

Aaron has removed the optics tray in TM2 in preparation for source tray removal.

  1870   Tuesday, February 19, 2019, 10:20 chad fisherSouth Hot-CellRepairTM2 Containment box removed

Containment box has been removed from TM2 in preparation for source tray removal. I will walk Aaron through removal of the optics tray today also.

  1869   Friday, February 15, 2019, 12:09 David WangITEMaintenanceTM4 ITE water system maintenance.

The ITE water system maintenance job is done. Changed all paddle wheels and coils on ITE flow sensors. All using water poly-tubes in ITE are replaced .  Started high active water pump, and checked ITE water signals. They are good. No leak has been found on  replaced tubes and related fittings.