ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  517   Tuesday, October 22, 2013, 14:23 Anders MjosITEStandard OperationTM3NiO#2Padlle wheel frequency measurementsas measured today in the electrical room
by David and Anders
 ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow.pdf 
  529   Friday, October 25, 2013, 13:39 Anders MjosITEStandard OperationTM3NiO#2Padlle wheel frequency measurementswith TM4 in ITW as measured today in the
electrical room by David and Anders.
 
 ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow_wITW-TM4.pdf 
  532   Thursday, October 31, 2013, 11:38 Anders MjosITEStandard OperationTM3NiO#2Padlle wheel frequency measurementswith TM4 in ITW as measured today in the
electrical room by David and Anders.
 ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow_EOB.pdf 
  537   Tuesday, November 12, 2013, 09:51 David WangITEStandard OperationTM3 TM3 disconnectionTM3 has been disconnected this morning
and  purged all HV water lines. I found
the power plug for all turbo pump fans wasnt
  
  548   Tuesday, November 19, 2013, 10:52 Travis CaveSouth Hot-CellStandard OperationTM3NiO#2module moveTM#3 with NiO#2 moved from ITE to the south
hot cell.
  
  551   Wednesday, November 20, 2013, 08:50 chad fisherSouth Hot-CellStandard OperationTM3NiO#2NiO#2 removedNiO#2 has been removed from TM3  TM3_20131120.jpgTM3_20131120_2.jpg 
  552   Wednesday, November 20, 2013, 09:52 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 with no target has been moved from
the south hot cell to the north east silo.
  
  554   Thursday, November 21, 2013, 12:12 Anders MjosSouth Hot-CellStandard OperationTM3NiO#2End of beam target inspection - ANODE does not hold 250VThe target was inspected by Chad and Anders
in the Hot Cell. Electrical megger tests
were done during the assembly. It was found
  
  556   Monday, November 25, 2013, 11:48 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 with no target has been moved from
the north east silo to the south hot cell.
  
  558   Wednesday, November 27, 2013, 12:50 Bevan MossSouth Hot-CellStandard OperationTM3 Ground devices wiring check Travis and I completed an electrical
check on the wiring harness for the devices
on the ground plane. All lines passed 500V
  
  559   Wednesday, November 27, 2013, 15:24 Bevan MossSouth Hot-CellMaintenanceTM3 Wiring Harness Electrical Test Maico removed the containment box
today allow Travis and I to further test
the wiring harness. I disconnected the junction
 IMG_1269.JPG 
  560   Friday, November 29, 2013, 11:54 chad fisherSouth Hot-CellRepairTM3 Steerer short investegationUsing in cell camera and transit the suspect
line on the steerers was inspected as best
as possible. An existing photo of the complete
 TM3_20131129_Steerer_1.jpgTM3_20131129_Steerer_2.jpgTM3_20131129_Steerer_3.jpg 
  561   Friday, November 29, 2013, 11:57 Bevan MossSouth Hot-CellRepairTM3 Steerer short investegation

    

       
            
  
  562   Monday, December 02, 2013, 11:29 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 with no target has been moved from
the south hot cell to the northeast silo.
  
  610   Tuesday, March 04, 2014, 10:19 Travis CaveITEStandard OperationTM3no targetmodule moveTM#3 has been moved from the silo to the
east target station.
  
  613   Thursday, March 06, 2014, 06:58 David WangITEMaintenanceTM3 ITE vacuum and leak check on ITE BL2A window flange.ITE and TM3 Turbo pumps have been started
successfully yesterday. The vacuum reading
on all ITE high vacuum gauges are at low
  
  616   Friday, March 07, 2014, 12:45 David WangITEStandard OperationTM3 TM3 and ITE air to vacuum leak check and TM3 water lines helium test.With TM3 located in ITE, All air to vacuum
seals  on ITE primary and secondary
vacuum vessel have been leak  checked
 001.JPG002.JPG003.JPG010.JPG013.JPG 
  617   Monday, March 10, 2014, 09:39 Travis CaveITEStandard OperationTM3no targetmodule moveTM#3 with no target has been moved from
the east target station to the south west
silo.
  
  637   Friday, April 04, 2014, 14:16 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 with no target has been moved from
the south west silo to the south hot cell.
  
  640   Monday, April 07, 2014, 10:48 Travis CaveSouth Hot-CellStandard OperationTM3no targetElectrical checkTM#3 electrical check at the south hot 
cell with no target to give us a base line
and show that things are ok with the module
 TM#3_elec_test_no_target.PDF 