  213   Tuesday, November 13, 2012, 10:55 Travis CaveITWStandard OperationTM1TiC#3module move

TM#1 with TiC #3 moved from the conditioning station to the west target station,  move went well.

  227   Tuesday, January 08, 2013, 08:48 Travis CaveSouth Hot-CellStandard OperationTM1TiC#3Electrical check

TM#1 with TiC #3 post beam. See attached PDF for results.

Attachment 1: TiC#3_Elec_Check_Post_beam.PDF
TiC#3_Elec_Check_Post_beam.PDF
  232   Tuesday, January 15, 2013, 14:37 Travis CaveSpent Target VaultStandard Operation TiC#3Spent target move

TiC #3 was moved from the south hot cell in to the vault storage today, it was placed in slot 4B and was in pail #104, it had a reading of 98.7mSv/hr upon removal from the south hot cell. See attached PDF for vault details.

Attachment 1: Vault_Storage_January_15_2013.pdf
Vault_Storage_January_15_2013.pdf Vault_Storage_January_15_2013.pdf Vault_Storage_January_15_2013.pdf Vault_Storage_January_15_2013.pdf
  2689   Monday, September 23, 2024, 11:35 David WangITWStandard OperationTM4TiC #9.vacuum leak check on TM4 service cap in ITW.

vacuum leak check on TM4 service cap in ITW was done this morning.   leak detector leak rate 0.0XE-9 atm.cc/sec. No leak on TM4 service cap module top.

  2640   Tuesday, July 16, 2024, 11:15 David WangITWStandard OperationTM4TiC #7 febiad. TM4 has been moved from TCS to ITW.

TM4 has been moved from TCS to ITW.  the move is smooth.

  2641   Tuesday, July 16, 2024, 11:15 David WangITWStandard OperationTM4TiC #7 febiad. TM4 has been moved from TCS to ITW.

TM4 has been moved from TCS to ITW.  the move is smooth.

  2661   Friday, August 16, 2024, 09:50 David WangSouth Hot-CellStandard OperationTM4TiC #7 febiad.TM4 has been moved from SMP to SHC.

TM4 has been moved from  SMP to SHC. The move is smooth.

 

  209   Thursday, November 08, 2012, 08:42 David WangConditioning StationStandard OperationTM1TiC #3TM1 TiC #3 target heat shield helium pressure check is done.

TM1 TiC #3 target  heat shield  helium pressure check  is done at conditioning station. Applied 80 psi helium to HS circuit for 5 minutes . There is no response had been found on leak detector. The leak detector base LR 0.0x E-9 atm.cc/sec, and BP 0.0xE-4 torr. CS and TM1 vacuum are at low E-6 torr range. The HS circuit is leak tight.

  208   Wednesday, November 07, 2012, 11:09 David WangSouth Hot-CellStandard OperationTM1TiC TM1 heat shield circuit leak check with TiC target at hot cell

Chad and i did a leak check on TM1(Lp-TiC) heat shield water circuit at south hot cell. There is no leak had been found on it. The circuit  is leak tight at present. I will do  helium pressure check on this circuit at  conditioning station once the vacuum is good enough.

  776   Monday, November 03, 2014, 11:16 chad fisherSouth Hot-CellStandard OperationTM1ThO#1ThO#1 Installed

ThO#1 has been installed onto TM1 and is ready for leak and electrical checking. High current fasteners torqued to 130 in lbs.

  777   Monday, November 03, 2014, 13:47 Travis CaveSouth Hot-CellStandard OperationTM1ThO#1Electrical check

TM#1 with ThO#1 electrical check see attatched PDF for details.

Attachment 1: TM1_elec_check_ThO1_SHC.PDF
TM1_elec_check_ThO1_SHC.PDF
  778   Tuesday, November 04, 2014, 11:05 David WangSouth Hot-CellStandard OperationTM1ThO#1Leak check on TM1 HS water line withThO#1 installed.

Chad and I leak checked HS line on TM1 with ThO#1 target installed. The LD pumped down to base leak rate 0.0xE-9 atm.cc/sec, base leak rate 0.0xE-4 torr. The pumping down process is normal. Chad sprayed helium on both VCR joints (each for 2 seconds) , and he did a flush spray around the target for 5 seconds. No any response had been found on LD during and after the spray( 40seconds waiting time). The target is leak tight.

  779   Tuesday, November 04, 2014, 13:17 chad fisherSouth Hot-CellStandard OperationTM1ThO#1TM1 w/ ThO#1 ready

Tm1 with ThO#1 is buttoned up and ready for transport.

  780   Wednesday, November 05, 2014, 10:20 Travis CaveSouth Hot-CellStandard OperationTM1ThO#1module move

TM#1 with ThO#1 has been moved from the south hot cell to the west target station.

  782   Thursday, November 06, 2014, 08:07 David WangITWStandard OperationTM1ThO#1TM1 has been connected in ITW.

TM1 has been connected in ITW. All turbo pumps are started. The pumping down on ITW is good so far. The water is supplied to TM1 for HV conditioning.

  783   Thursday, November 06, 2014, 08:55 David WangITWRepairTM1ThO#1 primary vacuum back up pressureITH CG1 ,CG2,CG4A were high.

I found primary vacuum back up pressure ITH CG1, CG2, and CG4A were unusually high this morning. They should be about 10 -20 mtorr after one night pumping, but all of thier reading were 340-350-mtorr. Thease cause the current draw on primary turbo pumps were all over 2.0A(should be about 1.0A). I let Paul closed all BVs on primary side . The pressure dropped quickly to normal range after all BVs were closed. This shows the back up line are good. The problem are from   one of  the connections  on primary BVs. I let Paul opened the BVs one by one,but the problem did not show again. Now ,the current draw on the turbo pumps are back to normal also.

I will keep monitoring the system and take a look on all KF25 clamps on BVs once I have a chance to access to ITW.

  785   Thursday, November 13, 2014, 13:52 David WangITWStandard OperationTM1ThO#15 Shielding blocks have been transferred from ITE to ITW.

Dan and I transferred 5 shielding blocks from ITE to ITW. The ITW is configured to take proton beam.

  856   Monday, March 09, 2015, 14:01 chad fisherSouth Hot-CellStandard OperationTM1ThO#1ThO#1 removed

ThO#1 has been removed from TM1 and placed into the plastic dissection box.

Containment box cover has been reinstalled as per usual.

  857   Tuesday, March 10, 2015, 09:01 Travis CaveSouth Hot-CellStandard OperationTM1ThO#1Module move

TM#1 has been moved from the west station to the south hot cell had the ThO#1 target removed and then the modules was moved from the south hot cell to the south west silo. Also an electrical check was done on the target before it was removed.

Attachment 1: TM1_THO_elec_chk_postbeamSHC.PDF
TM1_THO_elec_chk_postbeamSHC.PDF
  860   Thursday, March 12, 2015, 13:33 Anders MjosSouth Hot-CellStandard OperationTM1ThO#1Target inspection

Chad, Anders and Alex inspected the target this morning. The target had no significant visible damage to the container. Some material was deposited on the Extraction Electrode.

Phots on DocuShare