  948   Monday, June 15, 2015, 14:14 David WangSouth Hot-CellStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015Weekly update Target Hall schedule 2015-06-15.
See attachment 1,2
 2015-06-19, Update the schedule
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf 
  949   Tuesday, June 16, 2015, 14:28 chad fisherSouth Hot-CellRepairTM2 TM2 Source Tray Installation/Water Block Sealing Surface CleanToday cleaning and polishing pads were
inserted into the hot cell.
Module side waterblock jig installation
 20150616_104240.jpg20150616_140505.jpg20150616_140506.jpg 
  950   Wednesday, June 17, 2015, 14:21 chad fisherSouth Hot-CellRepairTM2 TM2 Waterblock Clean PolishFiberglass that fell out yesterday was
put back in place (as well as possible).
Cleaning took place this morning
 20150617_080236_1.jpg20150617_081538_1.jpg20150617_083830.jpg 
  951   Thursday, June 18, 2015, 08:03 chad fisherSouth Hot-CellRepairTM2 TM2 Optics Tray TransferThe TM2 optics tray has been transferred
from the source tray to the transfer fixture
in preparation for installation of the source
 20150618_075326_1.jpg 
  952   Friday, June 19, 2015, 09:37 Isaac EarleSouth Hot-CellRepairTM2 TM2 Source Tray Installation - June 18, 2015 The following work was done on
June 18 2015:
- Finished cleaning and polishing
  
  955   Friday, June 19, 2015, 11:57 chad fisherSouth Hot-CellRepairTM2 TM2 Source Tray ProgressWindow waterline has been successfully
connected using 1 1/2 inch long non-blunt
start 1/4-28 bolts.
  
  956   Friday, June 19, 2015, 13:00 chad fisherSouth Hot-CellRepairTM2 TM2 Source Tray Install StatusLeft manipulator now broken. Master side
however, so repair can take place Monday
or Tuesday.
  
  957   Tuesday, June 23, 2015, 10:55 chad fisherSouth Hot-CellRepair  Left Manipulator RepairThe master wrist/tong cable has been replaced
on the left manipulator. Everything appears
to function well so far.
  
  958   Tuesday, June 23, 2015, 14:19 chad fisherSouth Hot-CellRepairTM2 TM2 Water Block Jigs RemovedBoth halves of the water block jigs have
been removed and the module is now ready
for base vacuum leak and electrical checks.
 20150623_140917.jpg 
  960   Wednesday, June 24, 2015, 10:16 chad fisherSouth Hot-CellRepairTM2 TM2 Vacuum Leak CheckThe following circuits have been vacuum
leak checked and have not registered any
leaks:
  
  961   Wednesday, June 24, 2015, 13:49 David WangSouth Hot-CellRepairTM2 TM2 new source tray vacuum leak check.All water blocks seals and joints have
been leak checked. No leak has been found
on any of them. See attachment
 TM2_new_source_tray_water_block_leak_check_at_SHC.pdf 
  963   Friday, June 26, 2015, 09:44 chad fisherSouth Hot-CellRepairTM2 TM2 Retrofit StatusOn June 25th the following work was completed:
Optics tray was installed into TM2.
The lower fastener on the vertical cable
 20150625_075616_1.jpg20150625_083457.jpg20150625_105735.jpg20150625_110053.jpg 
  964   Friday, June 26, 2015, 09:45 chad fisherSouth Hot-CellRepairTM2 TM2 StatusContainment box window waterlines have
been connected and leak checked and new containment
box cover installed.
  
  968   Tuesday, June 30, 2015, 09:47 chad fisherSouth Hot-CellRepair  manipulator repairThe right hand manipulator has been repaired.
It took 43 minutes and I received ~ 0.56
mSv
  
  970   Tuesday, June 30, 2015, 12:37 chad fisherSouth Hot-CellStandard OperationTM1UCx#12UCx #12 RemovalUCx#12 has been removed from TM1 and placed
in a pail with argon.
Right leg (B) of target is clearly
  
  974   Thursday, July 02, 2015, 11:49 Travis CaveSouth Hot-CellStandard OperationTM1no targetModule movedTM#1 has been moved from the south hot
cell to the south west silo.
  
  976   Friday, July 03, 2015, 09:11 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule movedTM#2 has been moved from the conditioning
station to the south hot cell.
  
  979   Friday, July 03, 2015, 11:33 chad fisherSouth Hot-CellRepairTM2 TM2 Coil Leak ProgressFirst thing this morning the hot cell was
"cleaned up" in preparation for
the return of TM2 for attempted verification
 TM2_coil_leak_20150703_11.jpg20150703_111248.jpg 
  980   Friday, July 03, 2015, 13:29 chad fisherSouth Hot-CellRepairTM2 Hot Cell/ Module FieldsField measured at block "R" through
tool port with pole monitor is 6.65 mSv/H.
There are three air hoods and two
  
  983   Wednesday, July 08, 2015, 12:18 chad fisherSouth Hot-CellRepairTM2 R U Coil line RemovalR U coil line removal started at 11:30.
Water block jig installed and coil line disconnected
from module.
 TM2_20150708_coil_line_leak.jpg 