1134
|
Wednesday, November 25, 2015, 11:55 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | UC#14 | Module moved and electrical check. |
TM#4 with UC#14 was moved from the south hot cell to the conditioning station. Here are the results of the electrical check of the module with the UC#14 target while at the hot cell. |
Attachment 1: TM4_UC14_elecchk_SHC.PDF
|
|
1135
|
Wednesday, November 25, 2015, 14:13 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UC#14 | UCx#14 |
UCx#14 installed onto TM4. High current fasteners torqued to 130 in lbs. |
1137
|
Wednesday, November 25, 2015, 15:37 |
Anders Mjos | Conditioning Station | Standard Operation | TM4 | UC#14 | Conditioning |
Wednesday, November 25, 2015, 15:36: RGA on
Thursday, November 26, 2015, 09:55: PS energized. EE connected to power supply.
Thursday, November 26, 2015, 11:41: Applied some current and voltage to all power supplies. All looks good.
Some sparking around 5 kV. Turned out to be a bad cable connection. Fixed with David W.
Thursday, November 26, 2015, 15:04: BIAS/EL/EE 20 / 15 1.5 kV
Thursday, November 26, 2015, 15:43: Handed TCS over to ISAC operations
Target heated over the weekend. EE went into current limiting (down to ~100 V) a while after the target was at temperature.
Monday, November 30, 2015
Target conditioned by ISAC operators to 30 kV without any problems.
EE current limit increased to about 26 mA in an attempt to recover. Cooling down target to investigate. |
1138
|
Thursday, November 26, 2015, 06:25 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | TM4 vacuum has been connected in TCS. |
TM4 vacuum has been connected in TCS. All vacuum pumps were started yesterday. The pumping down of TM4 and TCS are good so far. |
1139
|
Thursday, November 26, 2015, 07:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | Helium pressure test on TM4 HS line at CS |
I did helium pressure test on TM4 HS line at TCS this morning. 70psi helium 3 minutes, 0.0xE-9 atm.cc/sec base leak rate. No response. No leak. |
1140
|
Thursday, November 26, 2015, 07:37 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | TM4 has been connected at CS |
TM4 has been connected at TCS. The water system is started. The TCS HV cover for TM4 is installed also. Basically, The TM4 is ready for conditioning. |
1143
|
Tuesday, December 01, 2015, 06:41 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | Turned off TCS all vacuum pumps and water pumps. |
I turned off TCS vacuum and water pumps. The TSC and TM4 are still under vacuum condition. |
1144
|
Tuesday, December 01, 2015, 11:26 |
Travis Cave | ITE/ITW Cooling | Standard Operation | TM4 | UC#14 | Module moved |
TM#4 with UC#14 has been moved from the conditioning station to the east target station. |
1145
|
Tuesday, December 01, 2015, 11:47 |
Anders Mjos | Conditioning Station | Maintenance | TM4 | UC#14 | Short on Extraction Electrode |
After conditioning over the weekend the EE developed a short. This was confirmed by measuring the resistance between EE and Heat Shield on the module yesterday. |
1194
|
Wednesday, April 06, 2016, 09:37 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#14 | module moved |
TM#4 with UC#14 has been moved from the east target station to the south hot cell. |
1204
|
Monday, April 11, 2016, 10:07 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#14 | Spent Target move |
The spent UC#14 target has been moved into the ISAC spent target vault. See the attached PDF for the details. |
Attachment 1: Vault_Storage_April_11_2016.pdf
|
|
1014
|
Monday, July 27, 2015, 13:38 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#13 | Electrical Check |
Electrical check of TM#4 with UC#13 at the south hot cell. See PDF for details. |
Attachment 1: TM4UC13IGLISelecchkSHC.PDF
|
|
1015
|
Monday, July 27, 2015, 14:37 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#13 | Module moved |
TM#4 has been moved from the east target station (morning with SiC#31), and moved to the conditioning station from the south hot cell with UC#13 on it. |
1021
|
Tuesday, July 28, 2015, 14:31 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | UC#13 | Electrical Check |
TM#4 with UC#13 electrical check at the conditioning station under vacuum. See attached PDF. |
Attachment 1: TM4UC13IGLISelecchkCS.PDF
|
|
1025
|
Wednesday, July 29, 2015, 08:59 |
Travis Cave | ITE | Standard Operation | TM4 | UC#13 | Module moved |
TM#4 with UC#13 has been moved from the conditioning station to the east target station. |
1072
|
Tuesday, September 22, 2015, 11:12 |
Travis Cave | ITE | Standard Operation | TM4 | UC#13 | Module moved |
TM#4 with UC#13 has been moved from the east target station to the south hot cell. |
1073
|
Tuesday, September 22, 2015, 11:35 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#13 | Electrical Check |
TM#4 with UC#13 post beam electrical check. Also and electrical check was done without the target on. |
Attachment 1: TM4elecchkUC13postbeamSHC.PDF
|
|
Attachment 2: TM4_elecchk_totgt_with_IGLISline.PDF
|
|
1083
|
Friday, September 25, 2015, 08:21 |
Travis Cave | South Hot-Cell | Standard Operation | | UC#13 | Spent Target move |
The spent UC#13 target has been moved from the south hot cell to the ISAC spent target vault. It was placed pail #128 and in tray spot 1A. It was 21.5mSv/hr upon removal from the hot cell. See attached PDF for details. |
Attachment 1: Vault_Storage_September_24_2015.pdf
|
|
888
|
Friday, April 17, 2015, 11:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#12 | Electrical check |
Electrical check of TM#1 with UCx#12 attached. See attached PDF for details. |
Attachment 1: TM1_UC#12_tgt_elec_chk_SHC.PDF
|
|
889
|
Friday, April 17, 2015, 14:04 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#12 | Module move |
TM#1 with UCx#12 has been moved from the south hot cell to the conditioning station. |