Entry  Monday, June 15, 2015, 14:14, David Wang, South Hot-Cell, Standard Operation, , , Target Hall Scheduled Activities April 07 - July 21 2015 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Weekly update Target Hall schedule 2015-06-15. See attachment 1,2
 2015-06-19, Update the schedule on  the end of the week. See attachment 3,4
Entry  Tuesday, June 16, 2015, 14:28, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Source Tray Installation/Water Block Sealing Surface Clean 20150616_104240.jpg20150616_140505.jpg20150616_140506.jpg
Today cleaning and polishing pads were inserted into the hot cell.
Module side waterblock jig installation was attempted however one of the locking tabs/latches (ITA2405?) came undone/fell off. Luckily, I had old,
obsolete jigs in the hot cell so I was able to remove parts I needed from an old one and rebuild the current one.
Entry  Wednesday, June 17, 2015, 14:21, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Waterblock Clean Polish 20150617_080236_1.jpg20150617_081538_1.jpg20150617_083830.jpg
Fiberglass that fell out yesterday was put back in place (as well as possible).
Cleaning took place this morning with excellent results. Cleaning was performed with red scotch brite on the cleaning tool, air pressure at 40
psi while running, with one 60 second cycle. Three blocks (EE, HS and Window) needed a second pass to remove the indium.
Entry  Thursday, June 18, 2015, 08:03, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Optics Tray Transfer 20150618_075326_1.jpg
The TM2 optics tray has been transferred from the source tray to the transfer fixture in preparation for installation of the source tray into the module.
Entry  Friday, June 19, 2015, 09:37, Isaac Earle, South Hot-Cell, Repair, TM2, , TM2 Source Tray Installation - June 18, 2015 
 The following work was done on June 18 2015:
- Finished cleaning and polishing all water blocks on module side (white felt with isopropyl, then buffing material with isopropyl, then canned
air).  Heat shield waterblock re-done because water marks visible (white scotchbrite, white felt w/ isopropyl, buffing material w/ isopropyl, then
Entry  Friday, June 19, 2015, 11:57, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Source Tray Progress 
Window waterline has been successfully connected using 1 1/2 inch long non-blunt start 1/4-28 bolts.
All bolt torques have been checked with dial torque wrench and are confirmed to be tight to 90 in lbs.
Entry  Friday, June 19, 2015, 13:00, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Source Tray Install Status 
Left manipulator now broken. Master side however, so repair can take place Monday or Tuesday.
Entry  Tuesday, June 23, 2015, 10:55, chad fisher, South Hot-Cell, Repair, , , Left Manipulator Repair 
The master wrist/tong cable has been replaced on the left manipulator. Everything appears to function well so far.
Entry  Tuesday, June 23, 2015, 14:19, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Water Block Jigs Removed 20150623_140917.jpg
Both halves of the water block jigs have been removed and the module is now ready for base vacuum leak and electrical checks.
During removal of the jigs the fiberglass that had been "shoved" by hand in between two of the lines in the early 2000's fell out again.
Entry  Wednesday, June 24, 2015, 10:16, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Vacuum Leak Check 
The following circuits have been vacuum leak checked and have not registered any leaks:
Circuit D, C, B, A, Coil2, EE, Ground Electrode, Mounting Support plate, Coil 1.
Left are Heat Shield and Window circuits which will be checked after blank offs are installed on the vcr terminations.
Entry  Wednesday, June 24, 2015, 13:49, David Wang, South Hot-Cell, Repair, TM2, , TM2 new source tray vacuum leak check. TM2_new_source_tray_water_block_leak_check_at_SHC.pdf
All water blocks seals and joints have been leak checked. No leak has been found on any of them. See attachment
Entry  Friday, June 26, 2015, 09:44, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Retrofit Status 20150625_075616_1.jpg20150625_083457.jpg20150625_105735.jpg20150625_110053.jpg
On June 25th the following work was completed:
Optics tray was installed into TM2. The lower fastener on the vertical cable tray (IRH1585) needed to be removed and vertical cable tray rotated
upwards as optics tray would not clear cable tray. Optics tray was intstaled, cable tray repositioned and screw re-inserted.
Entry  Friday, June 26, 2015, 09:45, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Status 
Containment box window waterlines have been connected and leak checked and new containment box cover installed.
Module ready for transport just before 9am.
Entry  Tuesday, June 30, 2015, 09:47, chad fisher, South Hot-Cell, Repair, , , manipulator repair 
The right hand manipulator has been repaired. It took 43 minutes and I received ~ 0.56 mSv
Entry  Tuesday, June 30, 2015, 12:37, chad fisher, South Hot-Cell, Standard Operation, TM1, UCx#12, UCx #12 Removal 
UCx#12 has been removed from TM1 and placed in a pail with argon.
Right leg (B) of target is clearly broken.
Containment Box cover re-installed and module ready to move.
Entry  Thursday, July 02, 2015, 11:49, Travis Cave, South Hot-Cell, Standard Operation, TM1, no target, Module moved 
TM#1 has been moved from the south hot cell to the south west silo.
Entry  Friday, July 03, 2015, 09:11, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Module moved 
TM#2 has been moved from the conditioning station to the south hot cell.
Entry  Friday, July 03, 2015, 11:33, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Coil Leak Progress TM2_coil_leak_20150703_11.jpg20150703_111248.jpg
First thing this morning the hot cell was "cleaned up" in preparation for the return of TM2 for attempted verification and locating of leak
on R/U coil circuit.
Containment box has been removed and front cover reinstalled to provide some modicum of shielding form the entrance and exit windows. Box was placed
Entry  Friday, July 03, 2015, 13:29, chad fisher, South Hot-Cell, Repair, TM2, , Hot Cell/ Module Fields 
Field measured at block "R" through tool port with pole monitor is 6.65 mSv/H.
There are three air hoods and two air lines currently available.
Entry  Wednesday, July 08, 2015, 12:18, chad fisher, South Hot-Cell, Repair, TM2, , R U Coil line Removal TM2_20150708_coil_line_leak.jpg
R U coil line removal started at 11:30. Water block jig installed and coil line disconnected from module.