725
|
Thursday, August 07, 2014, 10:45 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | module move |
TM#4 has been moved from the south west silo to the south hot cell. |
726
|
Thursday, August 07, 2014, 13:58 |
David Wang | South Hot-Cell | Standard Operation | TM4 | UCx #10 | Leak check on TM4 HS water line with new UCX target. |
Isaac and I leak checked TM4 HS line with new UCX target. The leak detector base LR 0.0xE-9 atm.cc/sec, base pressure0.0xE-4torr. Isaac sprayed helium on both VCR connections(5 seconds each) and flushed helium around the target for 6 seconds. No response on leak detector. |
730
|
Monday, August 11, 2014, 10:38 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#10 | Electrical check |
Electrical check of TM#4 with UC#10 from thursday. |
736
|
Wednesday, September 03, 2014, 13:55 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | Ta#43 | module move |
TM#1 with Ta#43 has been moved from the ITW to the south hot cell. |
737
|
Wednesday, September 03, 2014, 13:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | ZrC#6 | Electrical check |
TM#1 with ZrC#6 electrical check at the south hot cell. The conductance of target on circuit A-D is a little lower then normal. |
739
|
Thursday, September 04, 2014, 09:47 |
David Wang | South Hot-Cell | Standard Operation | TM1 | | Leak check on TM1 HS water line with new target installed |
Chad and I leak checked the TM1 HS line with new target installed. Base leak rate 0.0xe-9 atm.cc/sec. No any response has been found on LD. The line will be pressurized at CS with helium tomorrow. |
750
|
Tuesday, September 23, 2014, 10:50 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#10 | module move |
TM#4 with UC#10 has been moved from the east target station to the south hot cell. |
752
|
Tuesday, September 23, 2014, 12:24 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | Ta#44 | Ucx10 removed Ta#44 installed |
Ucx#10 has been removed from TM4 and placed in a pail with argon.
Ta#44 has been installed onto TM4 and target heater bolts torqed to 130 in.lbs. |
753
|
Tuesday, September 23, 2014, 13:31 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#10, Ta#44 | Electrical check |
Electrical checks of TM#4 with UC#10 post beam and Ta#44 before beam see attached PDF for details. |
755
|
Wednesday, September 24, 2014, 15:03 |
David Wang | South Hot-Cell | Standard Operation | TM4 | Ta#44 | Leak check on TM4 HS water line with new Ta#44 target. at SHC |
This morning Chad and I leak checked TM4 HS line with new Ta#44 target installed. I calibrated LD before the check. Before check, the LD base LR 0.0xE-9 atm.cc/sec, base LP 0.0xE-4 torr. Chad sprayed helium on both VCR fittings and did a flush around the target. There is no any response had been found on LD,. The line is good on leak tight. with spray method. No helium pressure test on the HS line at CS since TM4 was moved back to ITE directly. |
760
|
Tuesday, October 14, 2014, 11:51 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | ZrC#6 | module move |
TM#1 with ZrC#6 has been moved from ITW to the south hot cell. |
761
|
Tuesday, October 14, 2014, 11:52 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | ZrC#6 | Electrical check |
TM#1 with ZrC#6 post beam electrical check see attached pdf for results. |
763
|
Tuesday, October 14, 2014, 13:31 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | Electrical check |
Electrical check of TM#1 with no target attached at the south hot cell see attached PDF for details. |
765
|
Wednesday, October 15, 2014, 12:55 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | module move |
TM#1 with no target has been moved from the south hot cell to the south west silo. |
770
|
Monday, October 20, 2014, 14:18 |
chad fisher | South Hot-Cell | Repair | | | Manipulator Repair |
The broken cable on the east manipulator has been replaced.
The handle will need some adjustments which will take place first thing tomorrow. |
771
|
Tuesday, October 21, 2014, 08:55 |
chad fisher | South Hot-Cell | Repair | | | Manipulator repair |
The east manipulator handle has been adjusted and is ready for use. |
775
|
Monday, November 03, 2014, 10:27 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | module move |
TM#1 has been moved from the south west silo to the south hot cell. |
776
|
Monday, November 03, 2014, 11:16 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | ThO#1 | ThO#1 Installed |
ThO#1 has been installed onto TM1 and is ready for leak and electrical checking. High current fasteners torqued to 130 in lbs. |
777
|
Monday, November 03, 2014, 13:47 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | ThO#1 | Electrical check |
TM#1 with ThO#1 electrical check see attatched PDF for details. |
778
|
Tuesday, November 04, 2014, 11:05 |
David Wang | South Hot-Cell | Standard Operation | TM1 | ThO#1 | Leak check on TM1 HS water line withThO#1 installed. |
Chad and I leak checked HS line on TM1 with ThO#1 target installed. The LD pumped down to base leak rate 0.0xE-9 atm.cc/sec, base leak rate 0.0xE-4 torr. The pumping down process is normal. Chad sprayed helium on both VCR joints (each for 2 seconds) , and he did a flush spray around the target for 5 seconds. No any response had been found on LD during and after the spray( 40seconds waiting time). The target is leak tight. |