Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 15 of 140  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Categorydown Type Module Target/Number Subject
  149   Wednesday, July 18, 2012, 16:49 Grant MinorSouth Hot-CellDevelopment  South Hot Cell Ventilation Alarm Trip

Today (Wednesday July 18th) at around 4:15 pm I was taking a small tour group from VECC into the Target Hall. In the process of discussing the mechanical design of the Target Modules and South Hot Cell turntable I inadvertently lifted the Aluminum Hatch Cover of the Hot Cell about 2 inches in an effort to explain something. This tripped the ventilation alarm before I realized what I was doing. I evacuated the visitors from the Target Hall, checked booties and gloves at the check station before having the visitors step over the boot box. I called operations and let them know what I had done. The Target Hall was locked out and is awaiting a survey for the morning of July 19th before work can proceed.

  152   Tuesday, July 31, 2012, 10:50 Travis CaveSouth Hot-CellStandard OperationTM1Ta#38module move

TM#1 with Ta#38 has been moved from the west target station to the south hot cell, no problems with the move.

  153   Tuesday, July 31, 2012, 12:24 chad fisherSouth Hot-CellStandard OperationTM1UCx#4UCx#4 Installed

Starting at 11:00 am and finishing at 12:10 Ucx#4 previous target was removed and UCx#4 installed and leak checked on TM1.

During module move to the hot cell UCx#4 was housed in a bag under argon.

  154   Tuesday, July 31, 2012, 12:50 David WangSouth Hot-CellStandard OperationTM1UC xTM1 heat shield circuit leak check with UC x target

Chad and i did a leak check on TM1heat shield with UCx target on.The circuit are pumped  down to the bottom leak rate and base pressure is 3xE-3 torr on the leak detector. There are two VCR caps on heat shield circuit. Chad sprayed helium on both of them   ( tested individually,2 seconds every time ) . The test repeated 1 time.There is no response on leak detector during 45 seconds waiting time on both time.Chad flushed helium around the target for 15 second. During 1 minutes waiting time , there is no response on leak detector.The heat shield circuit is leak tight at this stage. It will be helium pressure  in CS later.

  166   Friday, August 31, 2012, 12:10 chad fisherSouth Hot-CellMaintenance  Hot Cell Maitenance

Entered south hot cell Wednesday and replaced the pre-filter air filter as well as the front two light bulbs. Also removed two bags of compressible garbage, one bag of metal, and of course the bagged air filter (as Joe M. expressed as interest in havung it).

Inital checks found approximately 4000 cpm on the cell side of the temporary Al. panel used during the cell entry, 2000 cpm on the tacky mats layed out beside the work area but nothing on the floor under the plastic that had been layed down for the job.

 

Chad

  167   Tuesday, September 04, 2012, 11:11 Travis CaveSouth Hot-CellStandard OperationTM4UO#3module move

TM#4 with UO#3 has been moved from the east target station to the south hot cell for a target exchange. The move went well.

  168   Tuesday, September 04, 2012, 14:34 David WangSouth Hot-CellStandard OperationTM4NiO #1TM4 heat shield circuit leak check with NiO#1 target

Chad and i did a leak check on TM4 heat shield circuit with new NiO#1 target installed. It took about 40 mins(much longer than usual) to pump down the circuit to leak rate 0.6x E-9atm.cc/sec and 0.0x E-4 torr o leak detector.

All vacuum lines and joints which connected to the leak detector had been helium sprayed and they are leak  tight.Chad sprayed helium on each VCR joints for 2 seconds every time. During 1min waiting time, there is no any response on leak detector. Chad repeated same test again for double checking and we got same result. Chad finally flushed the helium around the target heat shield for 10 seconds.we waited for 1minute and found no response on the leak detector. The heat shield circuit is leak tight at this stage. I will do a helium pressure test on this circuit when TM4 is in CS and under vacuum.

  170   Wednesday, September 05, 2012, 14:36 chad fisherSouth Hot-CellStandard OperationTM4NiO #1UOx removal NiO installation

UOx was removed from TM4 yesterday and NiO#1 installed.

Video was taken.

Main stand-off insulators continue to deteriorate.

  177   Thursday, September 13, 2012, 11:03 Travis CaveSouth Hot-CellStandard OperationTM1UCx#4module move

TM#1 with UCx#4 has been moved from the west target station to the south hot cell. Move went well.

  178   Thursday, September 13, 2012, 13:27 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule move

TM#1 has been moved from the south hot cell to the south west silo. Move went well.

  180   Tuesday, September 18, 2012, 09:13 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule move

TM#1 moved from the south west silo to the south hot cell, move went well.

  181   Tuesday, September 18, 2012, 13:41 David WangSouth Hot-CellStandard OperationTM1Nb#7leak check heat shield circuit

Chad and i did a leak check on TM1 heat shield circuit with new Nb#7 target installed. It took about 5 mins pump down the circuit to leak rate 0.0x E-9atm.cc/sec and 0.0x E-4 torr on leak detector.

All vacuum lines and joints which connected to the leak detector had been helium sprayed and they are leak  tight. Chad sprayed helium on each VCR joints for 2 seconds every time. During 45sec waiting time, there is no any response on leak detector. Chad repeated same test again for double checking and we got same result. Chad finally flushed the helium around the target heat shield for 10 seconds.we waited for 45minute and found no response on the leak detector. The heat shield circuit is leak tight at this stage. I will do a helium pressure test on this circuit when TM1 is in CS and under vacuum.

  182   Tuesday, September 18, 2012, 13:47 chad fisherSouth Hot-CellStandard OperationTM1Nb#7Nb #7 install Cover Baseline

Nb #7 was installed and tested today.

Inside face of the containment box cover was cleaned with methanol and a baseline picture taken in an effort to track deposits and marking as requested bty Anders.

Attachment 1: IMG_3191.JPG
IMG_3191.JPG
Attachment 2: IMG_3192.JPG
IMG_3192.JPG
  183   Wednesday, September 19, 2012, 11:23 Travis CaveSouth Hot-CellStandard OperationTM1Nb#7Electrical check

TM#1 with Nb#7 attached was electrically checked at the south hot cell yesterday, see attached pdf for details. Some notes about this test the oven to the 60kV common is 2Mohm this was noticed on the target prior to installation on the module, and the 60kV common to chassis is low at 874Mohm (low as in a non infinite value).

Attachment 1: TM1_Nb7_Elec_chk_SHC.PDF
TM1_Nb7_Elec_chk_SHC.PDF
  194   Tuesday, October 09, 2012, 13:44 chad fisherSouth Hot-CellStandard OperationTM4UCx#5NiO#1 removal UCx#5 installation

NiO#1 was removed this morning.

UCx#5 was inserted into the hot cell around 1 pm, installed and leak checked and ready to go to the conditioning station 1:40pm

did have a little trouble with the 9 pin connector. It had to be lossened to get it to mate properly. It was le-tightened once the proper fit was achieved.

Attachment 1: IMG_0780[1].JPG
IMG_0780[1].JPG
  203   Tuesday, November 06, 2012, 11:34 chad fisherSouth Hot-CellStandard OperationTM1 Nb#7 Removal

Attached are pre-removal pictures of NB#7 and the inside face of the containment box cover before cleaning.

Attachment 1: IMG_0797[1].JPG
IMG_0797[1].JPG
Attachment 2: IMG_0798[1].JPG
IMG_0798[1].JPG
Attachment 3: IMG_0799[1].JPG
IMG_0799[1].JPG
  205   Tuesday, November 06, 2012, 14:00 chad fisherSouth Hot-CellStandard OperationTM1TiC#3TiC#3 Installed

TiC#3 sucessfully installed and ready for leak and electrical check.

  206   Wednesday, November 07, 2012, 09:25 Travis CaveSouth Hot-CellStandard OperationTM1TiC#3Electrical check

TM#1 with TiC#3 target has had the electrical performed on it. See attached PDF for details.

Attachment 1: TM_1_TiC_3_Elec_check_SHC.PDF
TM_1_TiC_3_Elec_check_SHC.PDF
  208   Wednesday, November 07, 2012, 11:09 David WangSouth Hot-CellStandard OperationTM1TiC TM1 heat shield circuit leak check with TiC target at hot cell

Chad and i did a leak check on TM1(Lp-TiC) heat shield water circuit at south hot cell. There is no leak had been found on it. The circuit  is leak tight at present. I will do  helium pressure check on this circuit at  conditioning station once the vacuum is good enough.

  210   Thursday, November 08, 2012, 09:37 chad fisherSouth Hot-CellStandard OperationTM1Nb#7Nb#7 Autopsy

Nb#7 was dismantled and ready for inspection.

ELOG V2.9.2-2455