  RH-ISAC, Page 14 of 138  Not logged in ELOG logo
Entry  Wednesday, June 10, 2015, 10:02, Travis Cave, ITE, Standard Operation, TM4, SiC#31, Module moved 

TM#4 has been moved from the conditioning station to the east target station.

Entry  Wednesday, June 10, 2015, 11:49, David Wang, ITE, Standard Operation, TM4, SiC #31, TM4 has been connected in ITE 

Dan and I connected TM4 in ITE. At this stage, water is supplied to TM4 only. We checked the TM4 water signals from electrical room.They are good. The turbo-pumps will be started today once the roughing is done.

Entry  Friday, June 19, 2015, 11:52, David Wang, ITE, Standard Operation, TM4, SiC #31, 5 Shielding blocks have been transferred from ITW to ITE. 

5 shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

Entry  Monday, July 27, 2015, 12:12, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#31, Electrical Check TM4_elecchk_notgt.PDFTM4SiC31postbeamelecchk_.PDF

Electrical check of TM#4 post beam with target (SiC#31) on and module without target on. There is a short between the target and EE when the target is on and when the target was removed short went away. See the PDF for details.

Entry  Monday, July 27, 2015, 13:38, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#13, Electrical Check TM4UC13IGLISelecchkSHC.PDF

Electrical check of TM#4 with UC#13 at the south hot cell. See PDF for details.

Entry  Monday, July 27, 2015, 14:37, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#13, Module moved 

TM#4 has been moved from the east target station (morning with SiC#31), and moved to the conditioning station from the south hot cell with UC#13 on it.

Entry  Monday, July 27, 2015, 15:34, David Wang, ITE, Standard Operation, TM4, , Leak check on TM4 HS water line with new UCX target. at SHC 

Chad and I leak checked the HS line at SHC after UCX target installation. On first round helium spray, one of VCR fitting has a leak to E-6 atm.cc/sec range. Chad tightened the fitting, and solved the problem. We leak checked both VCR fittings twice. No leak. The line will be helium pressured at CS tomorrow.

Entry  Monday, July 27, 2015, 17:03, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, UCx13 and TM4 under vacuum at CS. 

I connected the CS  vacuum system  to TM4. The CS and TM4 turbo pumps are started. Everything is good so far. The HS line will be pressured with helium tomorrow for leak checking. The CS and TM4 will be vented with Argon on Wednesday morning as planned before moved to ITE.

Entry  Tuesday, July 28, 2015, 10:12, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, Helium pressure test on TM4 HS line at CS 

I did the helium pressure test on TM4 HS line at CS. Applied 70 psi helium  2 minutes. base leak rate0.0x E-9 atm.cc/sec.  No response during the test. No leak.

Entry  Tuesday, July 28, 2015, 14:31, Travis Cave, Conditioning Station, Standard Operation, TM4, UC#13, Electrical Check TM4UC13IGLISelecchkCS.PDF

TM#4 with UC#13 electrical check at the conditioning station under vacuum. See attached PDF.

Entry  Tuesday, July 28, 2015, 14:36, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#31, SiC#31 Autopsy 

Extraction electrode was removed from SiC#31 and target inspected.

Pictures of findings can be found at          https://documents.triumf.ca/docushare/dsweb/View/Collection-15131

 

 

 

Entry  Tuesday, July 28, 2015, 14:40, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#31 UCx#13, SiC#31 removed UCx#13 installed 20150727_115314.jpg

SiC#31 has been removed from TM4 and UCx#13 installed. UCx#13 connection to the 9 pin connector was VERY VERY tight to the tube heater insulator on both the test jig and module.

 

 

Entry  Wednesday, July 29, 2015, 06:24, David Wang, Conditioning Station, Standard Operation, TM4, UCx 13, Stopped the CS and TM4 pumps and vent with argon. 

Dan and I stopped the CS and TM4 pumps. We are venting the CS with argon for UCX13 target.

Entry  Wednesday, July 29, 2015, 08:59, Travis Cave, ITE, Standard Operation, TM4, UC#13, Module moved 

TM#4 with UC#13 has been moved from the conditioning station to the east target station.

Entry  Wednesday, July 29, 2015, 10:14, David Wang, ITE, Standard Operation, TM4, , TM4 has been connected in ITE 

Dan and I connected TM4 in ITE. We checked all water signals on ITE cooling circuits. Everything is good.

Entry  Tuesday, September 22, 2015, 11:12, Travis Cave, ITE, Standard Operation, TM4, UC#13, Module moved 

TM#4 with UC#13 has been moved from the east target station to the south hot cell.

Entry  Tuesday, September 22, 2015, 11:35, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#13, Electrical Check TM4elecchkUC13postbeamSHC.PDFTM4_elecchk_totgt_with_IGLISline.PDF

TM#4 with UC#13 post beam electrical check. Also and electrical check was done without the target on.

Entry  Tuesday, September 22, 2015, 11:39, Travis Cave, South Hot-Cell, Standard Operation, TM4, Ta#46, Electrical Check TM4Ta46elecchkSHC.PDF

TM#4 electrical check with Ta#46 attached.

Entry  Wednesday, September 23, 2015, 08:38, Travis Cave, Conditioning Station, Standard Operation, TM4, Ta#46, Module moved 

TM#4 with Ta#46 has been moved from the south hot cell to the conditioning station.

Entry  Wednesday, September 23, 2015, 13:56, Travis Cave, Conditioning Station, Standard Operation, TM4, Ta#46, Electrical Check TM4Ta46elecchkCS.PDF

TM#4 electrical check at the conditioning station with Ta#46 target.