  2716   Friday, November 08, 2024, 10:54 Aaron TamSouth Hot-CellStandard Operation TiC#9TiC#9 Pail Loading into Pail#299

 Nov. 8, 2024 - Aaron Tam 

Tong cable snapped when attempting to remove multipin connector bracket 

Assistance from Chad required for the rest of procedure 

Tic#9 was loaded into Pail#299 

  • Along with fixing and conductor bolts (no other material was loaded)

 

  2718   Monday, November 18, 2024, 12:18 Aaron TamSouth Hot-CellRepair  SHC West Manipulator Repair

 November 14, 2024 - Aaron Tam w/ Chad Fisher 

Following ID: 2716   
"Nov. 8, 2024 - Aaron Tam 
Tong cable snapped when attempting to remove multipin connector bracket"

Repair went as follows:

  • weighted clip attached to tong return side to tension/keep tapes on pulleys
  • Manipulator was pinned from both sides (Pinning from master side first makes it easier to position slave side)
  • clamps were used to suspend all tapes and cables near the relay bracket 
  • extension tube limit clamps were moved to the top to stop it from dropping when Z motion tapes disconnected
  • Z motion tapes/tension adjusting screws taken off master carriage and suspended with equalizing weight ~10+ lbs)
  • Extension tube limit clamps and extension tube lowered give space to expose multiplier later 
  • Wrist joint and handle removed as a unit 
  • extension tube to multiplier screws taken out
  • Extension tube raised to expose multiplier - using extension tube to wrist joint positioning clamp to keep it in place 
  • Old cable removed
  • new cable installed

installation in reverse with spare master handle 

Notes:

Spare master wrist joint was missing gears that connect wrist drums 

  • this had to be disassembled and installed with gears from old wrist joint

Handle ratcheting pawl spring was not oriented properly, so this had to be disassembled and reinstalled properly (in the process one spring was lost Part#: A-5800)
 

 

 

 

  2723   Tuesday, November 26, 2024, 14:52 Aaron TamSouth Hot-CellStandard OperationTM3UCx#47 UC#47 LP-SIS w/ gas Install

 November 26, 2024 - Aaron Tam 

Handover from TPO and inspection

  • Completed
  • Some modification to the center Inner-Outer conductor had to be made (hole enlarged as tab was slightly short)

Target Insertion:

  • Successful 

Target Mounting:

  • Upon fully seating UC#47 on service tray locating pins, the gas line VCR gasket came off 
    • Operator doesn't have line-of-sight to this area, so there has to be healthy clearance (Foreshadowing) 
    • Gas line VCR gasket reinstalled using manipulators  
  • 2nd seating of UC#47 on service tray locating pins, the gas line VCR gasket came off again
    • Some alignment interference with the gas line coupling is the cause of the gasket falling off during placement (photo attached)
    • Gas line on service tray was loosened, raised to highest position and fastened (Photo attached)
    • Failed to re-install VCR gasket (Plastic separated from gasket material)
  • Target removed from Hot cell to reinstall gaskets and make modifications to the gas-line coupling
    • Gas line coil plastically deformed to give less of a spring action so the coupling can stay down under friction until it is time to couple
    • Target carefully inserted into hot cell without disturbing spring/friction of gas-line coupling. 
      • This had to be repeated several times. Once for the waterline gaskets coming off, and a few other times to insert the target/tray without disturbing sprung coupling
  • Target mounted without issue after the above steps successfully 

Gas and Water Services:

  • VCR connections coupled 
  • Leak test passed
    • leak test faster today because module had been left in silo for a long time to dry out. 
  • Gas line no-longer needed, so was not checked

Electrical Services:

  • Conductor bolts installed
  • All bolts (including mounting bolts) checked for fit with mirror
  • Coil conductor bolts torqued to at least 130inch-lbs 
  • Electrical test completed 

Containment box panel reinstalled 

Cleared area around module for craning out. 

 

Attachment 1: Gas_line_interference.jfif
Attachment 2: Gas_line_Gasket_reinstalled.jfif
Attachment 3: Gas_line_moved_to_highest_position.jfif
Attachment 4: Target_Installed_photo.jfif
Attachment 5: Inside_of_containment_box_panel.jfif
Attachment 6: Completed_photo_(module_with_panel_on).jfif
  2724   Thursday, November 28, 2024, 16:13 Aaron TamSouth Hot-CellStandard Operation TiC#9 ParasiticsTiC#9 Parasitics Leak Check and removal from hotcell

 November 27th, 2024 - Aaron Tam with Farran & David 

Parasitic Assembly Leak Check (Aaron, Farran, David)

-Note that the furthest upstream (right of the target) parasitic top cap screws had been loosened and retightened in error when attempting to remove it off TiC#9

-This puts this data point into question 

-Leak check starting from upstream to down stream 

-First parasitic had no leak 

-Second parasitic had some leak 

-Third parasitic was not pumping down at all

-First parasitic checked on test hose again with same success

Parasitic Dis-assembly (Aaron) 

-First parasitic had good tension in all 3 screws

-second parasitic had 2 screws with a perceptible breaking-loose of the screws, but one was imperceptible 

-Third parasitic had lower (than first parasitic), but okay tension in all 3 screws 

In an attempt to move the PEEK seal into a safe spot with tweezers, this one was accidentally sprung across the hotcell in the direction of the tool port 

A lengthy attempt to find it was conducted, but no PEEK seal was recovered 

This may effect our ability to do work during hot cell entries coming up. 

PEEK Seal extraction (Aaron, Farran) 

-A labeled bag was inserted into the hotcell via the tool port and onto an existing tray in the Hotcell

-PEEK seal placed inside bag, placed back on tray, and moved back to the tool port for extraction

-With tool port open, the draft was able to push the bag across the lift table. Changing the cross section exposed to the draft works to keep the bag from moving

-Farran used picker to extract the bag into the tool port where he wiped and placed into separate bag.

-This process was repeated for the second PEEK seal 

-Bags were wiped and swiped, put in another bag, swiped and brought over to Hot cell Service area Lab 

 

 

 

Attachment 1: Leak_Test.jpg
Leak_Test.jpg
Attachment 2: Dissassembly.jpg
Dissassembly.jpg
Attachment 3: Seal_Seat.jpg
Seal_Seat.jpg
Attachment 4: PEEK_seal.jpg
PEEK_seal.jpg
Attachment 5: PEEK_Seal_Closer_look.jpg
PEEK_Seal_Closer_look.jpg
  2728   Tuesday, December 03, 2024, 15:53 Aaron TamSouth Hot-CellStandard OperationTM2Ta#68Ta#68 Removal

  Note: Ta#68 had a difficult install. See E-log ID# 2698 for more info 

First look:

  • Containment box cover looks the same as previous (See:ID: 2697)
  • Target shows large amount of soot-like deposits (See photos for locations)
  • Deposits seem to have been left on parts of the service tray as well ie.: Multipin connector 

Removal:

  • Removal was smooth
  • Water-line bracket fixing bolts seemed loose even before I put a tool to them 

Eyes of sides:

  • Better photos of where deposits are 
  • Everything else seems normal 
Attachment 1: Containment_Cover_Internal.jpg
Containment_Cover_Internal.jpg
Attachment 2: First_Look.jpg
First_Look.jpg
Attachment 3: First_look_Water_Lines_and_bracket.jpg
First_look_Water_Lines_and_bracket.jpg
Attachment 4: First_look_Water_Lines_and_bracket.jpg
First_look_Water_Lines_and_bracket.jpg
Attachment 5: First_Look_water_line_bracket_closer.jpg
First_Look_water_line_bracket_closer.jpg
Attachment 6: First_Look_Triplet_Conductos.jpg
First_Look_Triplet_Conductos.jpg
Attachment 7: Triplet_conductors_2.jpg
Triplet_conductors_2.jpg
Attachment 8: Multi_Pin.jpg
Multi_Pin.jpg
Attachment 9: Top.jpg
Top.jpg
Attachment 10: Top_Closer.jpg
Top_Closer.jpg
Attachment 11: Top_Closer_(2).jpg
Top_Closer_(2).jpg
Attachment 12: Right.jpg
Right.jpg
Attachment 13: Left.jpg
Left.jpg
Attachment 14: Bottom.jpg
Bottom.jpg
Attachment 15: Bottom_Closer.jpg
Bottom_Closer.jpg
Attachment 16: Extraction_electrode.jpg
Extraction_electrode.jpg
Attachment 17: Extraction_electrode2.jpg
Extraction_electrode2.jpg
Attachment 18: Extraction_electrode3.jpg
Extraction_electrode3.jpg
Attachment 19: Extraction_electrode4.jpg
Extraction_electrode4.jpg
Attachment 20: Deposit.jpg
Deposit.jpg
Attachment 21: Deposit2.jpg
Deposit2.jpg
Attachment 22: Deposit_3.jpg
Deposit_3.jpg
  2732   Wednesday, December 04, 2024, 14:30 Aaron TamSouth Hot-CellStandard Operation Ta#68Ta#68 PIE

 Abstract:
This target has seen some irregular beam patterns 
Possibility that the beam hit the walls of the target tube or even the cooling fins
This PIE we want to investigate how the irregular beam physically affected the target 

Related ELOGS: 
ID: 2728
ID: 2698

PIE was performed by Aaron Tam, Directed by Aurelia Laxdal, Observed by Lucas Backes, Special help from Chad Fisher 

External views:

  • Windows are clear of any irregularities 
  • More pictures of this can be found in RH-ISAC E-log 2728

Internal Views:

  • Heatshield internal
    • Some discolouration from heat and soot deposits.
    • This seems to be fairly clean to normal amounts - not concerning 
  • Target tube
    • tube is bent with the middle higher than the sides
    • Target tube was not removed 9/64ths allen wrench could not be located for this operation 
  • Target tube Exit
    • Heatshield windows were punctured to reveal the target tube entraces/exits
    • Entrance is waterline side (ITE)
  • Extraction electrode parts were removed from the back off the target
    • These parts look normal
    • some of the extraction electrode would not pull out due to tight fitting parts and the investigation stopped here.

Conclusion: Target physical condition is normal as far as we could investigate 

Attachment 1: Waterline_disconnect.jpg
Waterline_disconnect.jpg
Attachment 2: Heatshield_inside.jpg
Heatshield_inside.jpg
Attachment 3: Target_tube_first_look.jpg
Target_tube_first_look.jpg
Attachment 4: Heatshield2.jpg
Heatshield2.jpg
Attachment 5: Heatshield3.jpg
Heatshield3.jpg
Attachment 6: Target_tube_2.jpg
Target_tube_2.jpg
Attachment 7: Target_tube_3.jpg
Target_tube_3.jpg
Attachment 8: Couldn't_undo_this_bolt.jpg
Couldn't_undo_this_bolt.jpg
Attachment 9: Exit_tube.jpg
Exit_tube.jpg
Attachment 10: Exit_tube2.jpg
Exit_tube2.jpg
Attachment 11: Exit_tube3.jpg
Exit_tube3.jpg
Attachment 12: Exit_tube4.jpg
Exit_tube4.jpg
Attachment 13: Exit_tube5.jpg
Exit_tube5.jpg
Attachment 14: Exit_tube6.jpg
Exit_tube6.jpg
Attachment 15: Exit_tube7.jpg
Exit_tube7.jpg
Attachment 16: Exit_tube8.jpg
Exit_tube8.jpg
Attachment 17: Exit_tube9.jpg
Exit_tube9.jpg
Attachment 18: Exit_tube10.jpg
Exit_tube10.jpg
Attachment 19: entrance_tube.jpg
entrance_tube.jpg
Attachment 20: entrance_tube2.jpg
entrance_tube2.jpg
Attachment 21: entrance_tube3.jpg
entrance_tube3.jpg
Attachment 22: entrance_tube4.jpg
entrance_tube4.jpg
Attachment 23: Exit_tube5.jpg
Exit_tube5.jpg
Attachment 24: entrance_tube6.jpg
entrance_tube6.jpg
Attachment 25: entrance_tube7.jpg
entrance_tube7.jpg
Attachment 26: entrance_tube8.jpg
entrance_tube8.jpg
Attachment 27: entrance_tube9.jpg
entrance_tube9.jpg
Attachment 28: entrance_tube10.jpg
entrance_tube10.jpg
Attachment 29: entrance_tube11.jpg
entrance_tube11.jpg
Attachment 30: Extraction_electrode.jpg
Extraction_electrode.jpg
Attachment 31: entrance_tube1.jpg
entrance_tube1.jpg
Attachment 32: Extraction_electrode2.jpg
Extraction_electrode2.jpg
  2733   Thursday, December 05, 2024, 11:43 Aaron TamSouth Hot-CellStandard Operation Ta#68 Pail loading - Ta#68 & Others into Pail#300

December 5, 2024 - Aaron Tam w/ help from Chad, Peter and Adam at the Crane  

Hot Cell Prep:

  • Tools organized, working space cleared, spot for clean tool to sit placed, Air tool is open and spinning clockwise for tightening 

Loading:

  • Ta#68 was loaded into pail# 300
  • PEEK seal parasitic assemblies loaded (PEEK seals were removed in ID: 2724)
  • Farran had some old samples that also went in (More details to come when Farran sends the info)

Lid/latching:

  • This went smoothly

Bail attachment:

  • Some difficulty in attaching the Lifting Bail, but went on smoothly with the help of Chad

Notes:

  • One of the PEEK seal parasitic Target assembly lids was missed in the loading. This will have to be loaded next time. 
  • All parasitic type targets remain in the yellow container shown in photos below. 
Attachment 1: Pail_Landing.jpg
Pail_Landing.jpg
Attachment 2: Loaded_Pail.jpg
Loaded_Pail.jpg
Attachment 3: Parasitic_Lid_that_was_missed.jpg
Parasitic_Lid_that_was_missed.jpg
Attachment 4: Location_of_all_parasitic_type_targets_and_fasteners.jpg
Location_of_all_parasitic_type_targets_and_fasteners.jpg
Attachment 5: Parastics_and_Target_stuff_that_went_inside_this_pail.jpg
Parastics_and_Target_stuff_that_went_inside_this_pail.jpg
  1897   Monday, March 25, 2019, 10:11 Aaron SchmidtSouth Hot-CellRepairTM2 LP-FEBIAD Test Target (empty)

Link to previous target information: https://elog.triumf.ca/TIS/RH-ISAC/1039

Monday, March 25, 2019, 10:00: Target electrical checks (See Attachment 1)

Tested for TM2 

Attachment 1: TM2_-_FEBIAD_target_-_Electrical_Test.pdf
TM2_-_FEBIAD_target_-_Electrical_Test.pdf
  2530   Thursday, January 25, 2024, 07:24 David WangCraneStandard Operation  targe hall annual crane inspection

Tom Kauss finished TH crane annual inspection yesterday. The crane woks fine. Tom has this inspection record in his file. The crane inspection tag has been issued for 2024.