Thursday, June 27, 2024, 09:49, David Wang, North Hot-Cell, Standard Operation, , Nb#10, Nb#10target has been remotely transferred from NHC to SHC.
|
Nb#10target has been remotely transferred from NHC to SHC. |
Tuesday, July 02, 2024, 11:38, Frank Song, ITE/ITW/Storage Area, Standard Operation, , , shielding blocks transfer
|
5 shielding blocks have been moved from ITW to ITE, MAA area has been secured. |
Friday, July 05, 2024, 14:13, Adam Newsome, Waste Package/Ship, Standard Operation, , , F-308 flask loading - five flasks loaded
|
Today (2024-07-05), five flasks were loaded in preparation for shipment with the following targets: SiC#43 (Pail 272), SiC#44 (Pail 275), Ta#63 (Pail
266), UC#40 (Pail 278), UC#38 (Pail 274).
The crimped lifting loop has been applied to each pail. The locks have not yet been applied to the flasks at the time of writing this log, but |
Tuesday, July 09, 2024, 16:14, Carla Babcock, ITE, Repair, , , Attempts to reduce ITE:EL trips from HV sparks 8x
|
ITE:EL has been tripping off due to HV sparks. Usually this also trips ITE:Q1/2. These are sitting in side-by-side racks.
The working theory is that HV sparks are returning to ground through the EL and quads, tripping them off. Possibly this is the result of a changed
low impedance ground path. How this change happened could be either something we did during shutdown or the changes we made in TM3, no clear evidence yet. |
Wednesday, July 10, 2024, 09:55, Adam Newsome, Safe Module Parking, Maintenance, , , Annual electrical and mechanical inspection of Safe Module Parking
|
An annual electrical and mechanical inspection was performed on the SMP today by Adam Newsome, Travis Cave, Riley Sykes, Maico Dalla Valle, and Jason
Zhang as per Work Permit I2024-07-10-1. The following items were checked:
Check condition of wiring for physical/radiation/UV damage
OK, no signs of significant damage
|
Wednesday, July 10, 2024, 10:44, Riley Sykes, South Hot-Cell, Maintenance, , , Spring idler install
|
New spring idlers were installed onto rotational chain drive for SHC roof. Operation ran smoothly in both directions to full limit. Chain was noted
to have adequate slack when not on driven side. Periodic checks to confirm operation will continue in the following months to guarantee proper operation. |
Friday, July 12, 2024, 08:51, Riley Sykes, Safe Module Parking, Maintenance, , , SMP chain guard
|
SS washers were added to all slotted holes on SMP chainguard cover plate |
Wednesday, July 17, 2024, 15:06, Adam Newsome, Facilities, Standard Operation, , , Safety Walkaround Complete - SHC/NHC Area
|
A safety walkaround for July 2024 was completed for the B2 level by A. Newsome. No deficiencies to report.
Results can be found in the master
spreadsheet |
Thursday, July 18, 2024, 11:22, Travis Cave, Spent Target Vault, Standard Operation, , UC#45, Spent Target Move
|
The UC#45 target was moved from the south hot cell to the spent target vault. It was place in Pail#292 spot 1A of the vault, was 19.5mSv/hr. Also
this pail contains the target material of UC#44. See attached PDF for more details. |
Wednesday, July 24, 2024, 10:10, Frank Song, ITE/ITW/Storage Area, Standard Operation, , , shielding blocks transfer
|
5 shielding blocks have been transferred from ITE to ITW. MAA is secured again after moving. |
Wednesday, August 14, 2024, 11:29, Aaron Tam, Waste Package/Ship, Standard Operation, , SiC#46, Target Disposal and visual check
|
SiC#46 loaded into pail 293 successfully along with other hotcell waste
Upon visual inspection of the target, a spark-sign was spotted on the perimeter of the extraction electrode. Metallic looking material also found
built up between the extraction electrode and the backing plate of the target |
Friday, August 16, 2024, 08:47, Travis Cave, Spent Target Vault, Standard Operation, , SiC#46, Spent Target Move
|
SiC#46 (pail 293) was placed in the vault (spot 3B) on Wednesday the 14th of August. It was 111 mSv/hr when removed from the south hot
cell. See attached PDF for details. |
Tuesday, August 20, 2024, 11:36, Carla Babcock, South Hot-Cell, Standard Operation, , TiC#7, TiC#7 PIE
|
TiC#7 failed after two weeks of operations - measurements in the electrical room indicated that the negative side of the CHT was broken (35kOhms to the
rest of the target). This was likely due to a large number of proton trips during this target run. At every trip I could see the CHT voltage getting higher
and more unstable. This cahnge in voltage was reflected in the unstable anode current and fluctuating RIB beam intensity, as a direct result of the fluctuating |
Tuesday, August 20, 2024, 11:53, Carla Babcock, South Hot-Cell, Standard Operation, , Nb#10, Nb#10 PIE
|
Nb#10 never worked online - repeller had no effect on the beam and one of the RF wires was touching HVC. Max 60pA was seen on the source cup. See notes
here ITW-TM2-Nb#10/#11-LP-IGLIS
(Web |
Wednesday, August 21, 2024, 10:53, Travis Cave, Spent Target Vault, Standard Operation, , TiC#7, Spent Target Move
|
TIC#7 was placed in pail #294 and then moved from the south hot cell to the spent target vault spot 4B. It was 82.3mSv/hr when removed from the
SHC. See attached PDF for details. |
Monday, August 26, 2024, 09:57, Travis Cave, Spent Target Vault, Standard Operation, , Nb#10, Spent Target Move
|
Nb#10 was placed in pail#295 and moved from the south hot cell to the spent target vault, spot 4A, it was 230uSv/hr when removed from the SHC.
See attached PDF for vault details. |
Thursday, September 05, 2024, 12:50, Adam Newsome, Crane, Maintenance, , , Overhead crane: up/down hoist delayed start issue
|
D. Wang reports that recently the overhead crane has been exhibiting a delayed start (approx. 1 min) when operating in local mode. This issue applies
to the main hoist's up/down functionality only and does not seem to apply to other motion axes. T. Kauss briefly investigated but did not find any obvious
cause. |
Friday, September 06, 2024, 14:28, Aaron Tam, South Hot-Cell, Standard Operation, , Ta#68(Spare), Ta#68(Spare) removed from TM4 and into Anteroom
|
September 5, 2024 -AT
Plastic and clean target tray added to SHC
TM4 moved to SHC
TM4 containment box cover removed
September
6, 2024 - AT |
Wednesday, September 11, 2024, 13:38, Adam Newsome, North Hot-Cell, Repair, , , Spare Manipulator - Y-axis motion not functioning
|
Update 2024-09-12: C. Fisher confirms this is actually normal behaviour. The Y-axis motion is inhibited when X and Z
are in a certain configuration, which was true when the manipulator was mounted on the wall in storage position. Non-issue. A note about this has been
made in the operator manual. |
Thursday, September 12, 2024, 14:12, Adam Newsome, Waste Package/Ship, Development, , SiC#44, Failed waste emplacement at CNL: Flask #22, Pail 275 (SiC#44)
|
On 2024-09-12, CNL reported difficulty with lowering Pail 275 from F-308 flask #22 into their tile hole. The four other pails associated with this shipment
were successfully emplaced. It is suspected that the issue was related to a kink in the lowering cable, causing a jam during lowering. This was observed
approximately 1 year ago. |
|